Argyll and Bute Council
Planning, Protective Services and Licensing Committee, Wednesday 23 August 2017 at 10.30am

A AND L MCCRAE LTD: DEVELOPMENT OF A QUARRY ALLOWING FOR THE EXTRACTION AND PROCESSING OF SAND AND GRAVEL AND THE FINAL RESTORATION OF THE LAND: GLASDRUM, FASNACLOICH, APPIN (REF: 16/02911/MIN)

Agreed Planning 4 papers

Planning, Protective Services and Licensing Committee agreed this item on Wednesday 23 August 2017. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

Decision The Committee agreed to refuse the planning application for the following reasons:- 1. The application site lies within Glen Creran which is an upland glen defined in the ‘Landscape Assessment of Argyll and the Firth of Clyde’ (SNH 1996) as being within the Mountain Glen Landscape Character Type (LCT). The glen has a distinctive narrow form and strong sense of enclosure by steep sides and irregular ridgelines containing a small scale landscape, characterised by dispersed rural settlement, pockets of woodland and a marked field enclosure pattern. The experience within the glen contrasts markedly with the views into the glen from the adjacent Craggy Upland and High Tops LCT’s. Upland enclosing the glen to the west lies within the SNH defined Loch Etive Wild Land Area, characterised by an absence of development and elevated vantage points affording a sense of remoteness. The site and its wider surroundings all lie within a Local Development Plan defined Area of Panoramic Quality in recognition of the area’s scenic qualities of regional importance. The proposed mineral operations would be conspicuous from frequented upland vantage points affording views down into Glen Creran, which reveal a distinctive mosaic field pattern sensitive to intrusive and disruptive forms of development, which might not otherwise be so readily experienced from within the glen itself. The development by virtue of its impact on the landform, and the presence and operation of plant required to support the winning of minerals from the site, would constitute a conspicuous and intrusive form of development within this settled rural landscape, to the detriment of landscape character, the scenic qualities of the Area of Panoramic Quality, and the experience of the adjoining Wild Land Area. Although the extraction is only proposed for a five year period, the less than satisfactory restoration scheme proposed does not provide confidence that lasting adverse effects would be avoided. The proposal therefore fails to meet the requirements of Policies LDP STRAT 1 – Sustainable Development, LDP 9 – Development Setting, Layout and Design, LDP 10 – Maximising our Resources and Reducing our Consumption, SG LDP ENV 13 - Development Impact on Areas of Panoramic Quality (APQs), SG LDP ENV 14 – Landscape and SG LDP MIN 2 - Mineral Extraction of the ‘Argyll and Bute Local Plan’ 2015. 2. This proposal for mineral extraction is subject to the effect of sector specific Policy SG LDP MIN 2, which is derived from Policy LDP 10 of the adopted ‘Argyll and Bute Local Plan’ 2015, and which sets out a criteria based approach to the determination of minerals consent applications. This establishes a presumption against new mineral workings other than where an exceptional local need can be demonstrated, or where it is intended to supply the export of specialised minerals. The applicant has sought to demonstrate an exceptional local need founded around a needs assessment supported by anecdotal comments from local businesses involved in the North Lorn economy. Having regard to the development plan, the expectation is that the settlements of Oban and Dunbeg will be the main focus of development during the life of the current plan. Within a 30 mile radius of this area there are operational quarries able to provide a sufficient local supply of mineral resources, including Benderloch, North Connel, Dornie and Kilmartin, with the ability to provide a range of materials over the lifespan of the development plan. Although Scottish Planning Policy requires a ten year land bank of permissions within market areas, the limited life expectancy of the quarry proposed will only be comparable to that of North Connel, whilst both Kilmartin and Benderloch will continue to provide material thereafter. The proposal will not meaningfully add to the available supply within the North Lorn market area, or address any anticipated serious shortfall in supply, and any contribution which it could make would be offset by adverse local environmental consequences identified in the preceding reason for refusal. ... view the full minutes text for item 4.
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Planning, Protective Services and Licensing Committee

Argyll and Bute Council Planning and Regulatory Services

Delegated or Committee Planning Application Report and Report of handling as required by Schedule 2 of the Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013 relative to applications for Planning Permission or Planning Permission in Principle ____________________________________________________________________________

Reference No: 16/02911/MIN

Planning Hierarchy: Major Development

Applicant: A and L McCrae Ltd

Proposal: Development of a quarry allowing for the extraction and processing of sand and gravel and the final restoration of the land

Site Address: Glasdrum, Fasnacloich, Appin ____________________________________________________________________________

DECISION ROUTE

(i) Local Government Scotland Act 1973 ____________________________________________________________________________

(A) THE APPLICATION

(i) Development Requiring Express Planning Permission

 Extraction of 83,000 tonnes of sand and gravel over a period of 5 years and 6 months (approximate annual extraction 15,000 tonnes) with two months initial site preparation and a further eight months of final site restoration works;  Siting of weigh bridge and formation of settling ponds,  Use of existing cottage for site office,  Installation of sump  Formation of soil storage bund at northern boundary of the site,  Formation of car parking area,  Improvement to three existing passing places along U37 Salachail Road.  Site restoration works including importation of inert materials (aggregate waste) to raise levels and re-use of top soil. Site will be returned to agricultural use.

(ii) Other specified operations

 The site extends to some 5.35ha with the working area to some 3.05ha,  Working hours proposed are 7am to 6pm Monday to Friday and 7am to 12noon on Saturdays,  There will be an average of six HGV movements a day (three in and three out) with four daily car movements (two in and two out).  Minor tree felling ____________________________________________________________________________ (B) RECOMMENDATION:

It is recommended that in consideration of the Local Development Plan and all other material considerations that the application be refused for the reasons appended below. ____________________________________________________________________________

(C) HISTORY:

16/01059/PAN – Proposal of Application Notice for proposed sand and gravel quarry. – Closed 27/5/2016

16/01060/SCRSCO - Screening and scoping application for proposed sand and gravel quarry – Closed 20/5/2016 ____________________________________________________________________________

(D) CONSULTATIONS:

Scottish Environment Protection Agency (SEPA) – Responses dated 8/12/2016, 28/6/2017, 19/7/2017, SEPA initially objected due to concerns over flood risk. They confirm that they are now in a position to remove their objection and provide the following technical comments:

 The FRA indicates a localised increase (less than a 400m reach) in flooding will occur upstream of the proposed development with a maximum flood depth of approximately 0.36m possible. It is suggested that additional flood storage will be provided as a result of the proposed development works however we would confirm that a localised increase in flooding will still occur.

 In these circumstances SEPA would normally request that further management measures are considered to ensure at least a neutral effect on flooding, as per the requirements of Scottish Planning Policy, however in this instance we would note that the effect of increased flood is localised and only impacts on an area of forestry which is sited within the ownership of the same landowner.

 Furthermore the proposed development is a water compatible use and the working life of the quarry is also acknowledged as being of a temporary nature.

Based on these considerations we are now satisfied that the proposal should not represent a significant increase in flood risk

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
02911 Plan, 14/08/2017 Pre-Agenda Briefing of the Planning, Protective Services and Licensing CommitteeAgenda 310 KB Download
PDF
02911 RoH FINAL Salmon EPSReport 603 KB DownloadRead as text
PDF
02911 RoH SR 1 v3Report 133 KB Download
PDF
A AND L MCCRAE LTD: DEVELOPMENT OF A QUARRY ALLOWING FOR THE EXTRACTION AND PROCESSING OF SAND AND GRAVEL AND THE FINAL RESTORATION OF THE LAND: GLASDRUM, FASNACLOICH, APPIN (REF: 16/02911/MIN)Report 103 KB Download

At this meeting

Whole meeting
3MINUTESOn the agenda
4A AND L MCCRAE LTD: DEVELOPMENT OF A QUARRY ALLOWING FOR THE EXTRACTION AND PROCESSING OF SAND AND GRAVEL AND THE FINAL RESTORATION OF THE LAND: GLASDRUM, FASNACLOICH, APPIN (REF: 16/02911/MIN)This decision
5MR AND MRS BARRIE ADAMSON: ALTERATIONS, EXTENSION AND CHANGE OF USE OF EXISTING COOK SCHOOL TO FORM DWELLINGHOUSE AND CHANGE OF USE OF EXISTING BED AND BREAKFAST ACCOMMODATION TO FORM DWELLINGHOUSE: CORRIE HOUSE, CRAOBH HAVEN, LOCHGILPHEAD, PA31 8UA (REF: 17/00016/PP)Agreed 6TORR GORM DEVELOPMENTS LTD: MASTERPLAN IN RESPECT OF POTENTIAL DEVELOPMENT AREA PDA 6/23 OF THE ARGYLL AND BUTE LOCAL DEVELOPMENT PLAN 2015 RELATING TO MIXED USE DEVELOPMENT (RECREATION/TOURISM AND COMMERCIAL USE): LAND SOUTH OF SALEN PIERAgreed 7TORR GORM DEVELOPMENTS LTD: FORMATION OF 40 PITCH CAMPSITE INCLUDING HUB BUILDINGS AND ASSOCIATED ACCESS AND DRAINAGE WORKS: LAND SOUTH OF PIER COTTAGE, SALEN, ISLE OF MULL (REF: 17/00714/PP)Agreed 8CELTIC SEA LTD: SITING OF TRESTLES FOR OYSTER FARMING: FISH FARM, AIRD FHADA, LOCH SCRIDAIN, ISLE OF MULL (REF: 17/01490/MFF)Agreed 9STEVEN SHAW LIMITED: VARIATION OF CONDITION 2 RELATIVE TO PLANNING PERMISSION 15/03442/PP (CONSOLIDATION OF SITE LEVELS FOLLOWING DEMOLITION OF MCCOLLS HOTEL) - EXTENSION TO TIME PERIOD: FORMER MCCOLL'S HOTEL SITE, 1 TOM-A-MHOID ROAD, DUNOON (REF: 17/01636/PP)Agreed 10CONSULTATION ON AMENDMENTS TO PERMITTED DEVELOPMENT RIGHTS FOR FIN FISH AND SHELL FISH DEVELOPMENTSAgreed 11PROTOCOL FOR THE ROLE OF COUNCILLORS IN PRE-APPLICATION PROCEDURESAgreed 12PLANNING PERFORMANCE FRAMEWORK 2016/17Agreed 13UPDATE ON RECENT SCOTTISH GOVERNMENT PLANNING APPEAL DECISIONSNoted 18The Council resolved in terms of Section 50(A)(4) of theOn the agenda 14ENFORCEMENT REPORT - REFERENCE 16/00076/ENAMEN AND 17/00046/ENAMENPrivate

Who was there

13 of 15 attended
GB
Councillor Gordon BlairMember, present
RC
Councillor Rory ColvilleVice-Chair, present
RC
Councillor Robin CurrieMember, present
MD
Councillor Mary-Jean DevonMember, present
LD
Councillor Lorna DouglasMember, present
AF
Councillor Audrey ForrestMember, present
GF
Councillor George FreemanMember, apologies
GA
Councillor Graham Archibald HardieMember, apologies
DK
Councillor David KinniburghChair, present
DM
Councillor Donald MacMillanMember, present
RM
Councillor Roderick McCuishMember, present
JM
Councillor Jean MoffatMember, present

All 15 on the meeting page

More from Argyll and Bute Planning, Protective Services and Licensing Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Beaufort wind limited: erection of 7 turbines (up to 149.9m to tip) and ancillary development and decommissioning of existing beinn ghlas wind farm: existing beinn ghlas wind farm, taynuilt (ref: 25/01240/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. PP - A... Agreed Open
15 Sep 2026 Mr tony coogan: alterations to guesthouse to facilitate lawful use of existing roof space as ancillary guest house owner's accommodation: greencourt, benvoullin road, oban (26/00434/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Mrs faulkes: proposed alterations and erection of extension: 30 the green, craobh haven (ref: 26/01009/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Decision The Committee agreed that the Scottish Government’s Marine Directorate should be notified that Argyll and Bu... Agreed Open
15 Sep 2026 Development management performance update - fq1 2026/27Decision The Committee reviewed and agreed the content of the report. (Reference: Report by Executive Director with r... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies