ARGYLL AND BUTE COUNCIL SINGLE HARBOUR ORDER

Agreed Committee 1 paper

Argyll and Bute Harbour Board agreed this item on Tuesday 23 January 2018. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision Members agreed to instruct the Executive Director, Development and Infrastructure Services to persue the promotion of a single harbour order for all of Argyll and Bute Council’s 39 piers, harbours and slips. (Reference: Report by Executive Director, Development and Infrastructure Services dated 21 December 2017, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Argyll and Bute Harbour Board

Executive summary

1.1This report outlines the intention of the Marine Operations Service to seek a consolidation of the multiple harbour orders that currently exist across the piers and harbours which Argyll and Bute Council has a responsibility for. The proposal is to promote a single harbour order to cover all of the Council’s marine assets.

1.2It is recommended that Members instruct the Director of Development and Infrastructure to pursue the introduction of a single harbour order for all of Argyll and Bute Council’s 39 piers, harbours and slips.

1.3This is an issue which has been highlighted by our Designated Person (DP) in audits. The introduction of a single order will allow antiquated orders to be updated and ratify the position in relation to piers and harbours currently operating on the basis of historic custom and practice. This will provide improved clarity for harbour staff and users; and enable a more consistent approach to be taken to the management of the council’s facilities.

1.4The pre-application and application process to progress the introduction of a new harbour order is outlined in the annexe to this report. The process will involve wide consultation with a number of interested parties including local communities. The timescale for getting a single Harbour Order in place will be dependant on consultation feedback but is expected to take at least a year and possibly much longer should representation be received requiring negotiation; the main tasks will be as follows:-

 Plan will be prepared identifying each of the Council’s 39 piers and harbours.  A draft order will be prepared by Legal Services.  Discussions will take place with Transport Scotland regarding the Council’s proposals.  An important aspect of the process will be to determine if any Environmental Statements and/or Environmental Impact Assessments are required to be provided.  Consultation with communities and interested parties will take place.  Finally, the consolidation order will be formally advertised.

1.5Should approval be given by Members, as recommended in this report, officers will progress the promotion of a single harbour order for all of the Council’s 39 piers and harbours. ARGYLL AND BUTE COUNCIL ARGYLL AND BUTE HARBOUR BOARD

DEVELOPMENT AND INFRASTRUCTURE SERVICES 23 JANUARY 2018

ARGYLL AND BUTE COUNCIL SINGLE HARBOUR ORDER

2.0INTRODUCTION

2.1This report highlights the fact that, currently, the 39 piers and harbours which Argyll and Bute Council has a responsibility are covered by multiple harbour orders which are often extremely antiquated or operate on the basis of historic custom and practice. It is proposed to promote a single harbour order to cover all of the Council’s marine assets.

Recommendations

3.1It is recommended that Members instruct the Director of Development and Infrastructure to pursue the promotion of a single harbour order for all of Argyll and Bute Council’s 39 piers, harbours and slips.

Background

4.1A Harbour Empowerment or Revision Order is a piece of local legislation governing a port; it is made as a Scottish Statutory Instrument under the 1964 Harbours’ Act by Scottish Ministers. An order can create and empower Harbour Authorities to undertake works or vary their existing harbour powers.

4.2Argyll and Bute Council is responsible for 39 piers, harbours and slips; of these 39 marine assets, only 8 of the Council’s ports have Harbour Orders in place. Some of these orders, instigated by the Council’s predecessors, date back over a century to their initial inception. Orders are currently in place for the following facilities:-

 Bruichladdich  Campbeltown  Carradale  Craignure  Dunoon  Port Askaig  Rothesay  Oban North Pier

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ARGYLL AND BUTE COUNCIL SINGLE HARBOUR ORDERReport 142 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
RM
Councillor Roderick McCuishChair, present
JA
Councillor John ArmourMember, present
JL
Councillor Jim LynchMember, present
EM
Councillor Ellen MortonVice-Chair, present
AR
Councillor Alastair RedmanMember, present
AR
Councillor Alan ReidMember, present
RT
Councillor Richard TrailMember, present
AV
Councillor Andrew VennardMember, present
HM
Hazel MacInnesSecretary, expected

On this subject at Argyll and Bute

Search all
  1. ARGYLL AND BUTE COUNCIL SINGLE HARBOUR ORDERThis decision
  2. Argyll and bute outcomes and improvement plan - priorities updateNoted
  3. Argyll and Bute Climate Action NetworkNoted
  4. Argyll and bute improvement plan - priorities updateNoted
  5. Argyll and bute improvement plan - priorities updateNoted
  6. Argyll and bute harbour board workplanNoted

More from Argyll and Bute Argyll and Bute Harbour Board

All decisions
MeetingDecisionOutcome
9 Oct 2026 Piers and harbours marine asset management plan - works updateDecision The Argyll and Bute Harbour Board noted the updates on capital works currently being progressed within the M... Noted Open
9 Oct 2026 Piers and harbours - performance reportingDecision The Argyll and Bute Harbour Board – 1. agreed the proposed approach and structure to annual performance repo... Agreed Open
9 Oct 2026 Carradale harbourDecision The Argyll and Bute Harbour Board noted the content of the report. (Reference: Report by Executive Director ... Noted Open
9 Oct 2026 Piers and harbours marine asset management plan fees and charges 2027 / 2028Decision The Argyll and Bute Harbour Board – 1. noted that officers were of the view that a review is required to con... Noted Open
9 Oct 2026 Argyll and bute harbour board workplanDecision The Argyll and Bute Harbour Board noted the content of the workplan. (Reference: Argyll and Bute Harbour Boa... Noted Open