Argyll and Bute Council
Mid Argyll, Kintyre & the Islands Area Committee, Wednesday 7 March 2018 at 10.30am

Report by Senior Planning Development Officer

Agreed Committee 1 paper

Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 7 March 2018. Below is the council's own wording, with the papers it was decided on.

Item12a

Resolved

Decision The Area Committee:- Agreed to recommend to the Policy and Resources Committee that: (a) The full business case is approved and the grant funding of up to £125,000 is confirmed from the Tarbert and Lochgilphead Regeneration Fund. Release of this funding would be on the basis that expenditure can be evidenced and would be subject to a grant agreement between Argyll and Bute Council and Tarbert Harbour Authority. (b) Delegated authority be afforded to the Executive Director of Development and Infrastructure Services to confirm the details of the grant agreement. (Ref: Report by Senior Planning Development Officer dated 21 st February 2018, submitted).
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Mid Argyll, Kintyre & the Islands Area Committee

Executive summary

1.1This report provides an update on the proposals for the Tarbert Harbour Authority Shore Side Facilities and consideration of the full business case following the approval of an allocation of up to £125,000 by Committee in September and October 2017.

1.2To assess this project, Tarbert Harbour Authority have provided a full business case for the capital project together with their Business Development Plan 2016-21, accounts etc. A copy of the assessment is contained at Appendix 1 and has been informed by the business case with input from Strategic Finance.

1.3Following this assessment, it is considered that overall the impacts of the project and the organisation’s governance, financial planning and project planning are sufficient to enable the Council’s funding to be confirmed, subject to Committee approval. If the Committee agree the funding allocation of £125,000, a grant agreement will be prepared in relation to the funding which will set out the conditions associated with the grant including a requirement for expenditure to be evidenced. A summary of the key points of the assessment is shown at 4.5.

Recommendations 1.4 Members of the Mid Argyll, Kintyre and the Islands Area Committee are asked to: 1. Recommend to Policy and Resources Committee that: a. The full business case is approved and the grant funding of up to £125,000 is confirmed from the Tarbert and Lochgilphead Regeneration Fund. Release of this funding would be on the basis that expenditure can be evidenced and would be subject to a grant agreement between Argyll and Bute Council and Tarbert Harbour Authority. b. Delegated authority be afforded to the Executive Director of Development and Infrastructure Services to confirm the details of the grant agreement. ARGYLL AND BUTE COUNCIL Mid Argyll, Kintyre and the Islands Area Committee

Development and Infrastructure 7 March 2018

Tarbert and Lochgilphead Regeneration Fund – Tarbert Harbour Authority Shore Side Facilities Full Business Case

2.0INTRODUCTION

2.1This report provides an update on the proposals for the Tarbert Harbour Authority Shore Side Facilities and consideration of the full business case.

2.2On 6 September 2017, the Mid Argyll, Kintyre and the Islands Area Committee agreed the six projects which should proceed to full business case through the Tarbert and Lochgilphead Regeneration Fund. This decision was ratified by Policy and Resources Committee on 19 October 2017.

2.3It was noted in the previous report that full business cases for each of the projects will be submitted for consideration by committee as they become available given that each of the projects will develop at a different pace. The agreed projects included an allocation of up to £125,000 for the shore side harbour facilities at Tarbert Harbour. This was the first element of works to be funded at Tarbert Harbour, the second was focused on improving car parking. The full business case for the shore side facilities has now been provided.

Recommendations

3.1Members of the Mid Argyll, Kintyre and the Islands Area Committee are asked to:

1. Recommend to Policy and Resources Committee that: a. The full business case is approved and the grant funding of up to £125,000 is confirmed from the Tarbert and Lochgilphead Regeneration Fund. Release of this funding would be on the basis that expenditure can be evidenced and would be subject to a grant agreement between Argyll and Bute Council and Tarbert Harbour Authority. b. Delegated authority be afforded to the Executive Director of Development and Infrastructure Services to confirm the details of the grant agreement.

4.0DETAIL

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report by Senior Planning Development OfficerReport 114 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 11 attended
JA
Councillor John ArmourMember, present
SC
Stewart ClarkCouncil Staff, present
RC
Councillor Rory ColvilleMember, present
RC
Councillor Robin CurrieChair, present
AH
Councillor Anne HornMember, present
LI
Lynsey InnisSecretary, expected
DK
Councillor Donald KellyMember, present
DM
Councillor Donald MacMillanVice-Chair, present
DP
Councillor Douglas PhilandMember, present
AR
Councillor Alastair RedmanMember, present
ST
Councillor Sandy TaylorMember, apologies

On this subject at Argyll and Bute

Search all
  1. Report by Senior Planning Development OfficerThis decision
  2. Report by Senior Planning Officer in regard to Druimavuic Roadside Cairns, Loch Creran, by ObanApproved

More from Argyll and Bute Mid Argyll, Kintyre & the Islands Area Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... Noted Open
2 Sep 2026 Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... Agreed Open
2 Sep 2026 Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... Noted Open
2 Sep 2026 Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... Noted Open
2 Sep 2026 Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... Noted Open