CONSULTATION ON AMENDMENTS TO FEE REGIME FOR APPLICATIONS IN RESPECT OF S36 AND S37 OF THE ELECTRICITY ACT 1989
AgreedPlanning2 papers
Planning, Protective Services and Licensing Committee agreed this item on Wednesday 18 April 2018. Below is the council's own wording, with the papers it was decided on.
Decision The Committee agreed to endorse the terms of the response to the Scottish Government as detailed in Appendix A attached to the Executive Director’s report. (Reference: Report by Executive Director – Development and Infrastructure Services dated 20 March 2018, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Planning, Protective Services and Licensing Committee
ARGYLL & BUTE COUNCIL Planning, Protective Services and Licensing Committee DEVELOPMENT AND 18 April 2018 INFRASTRUCTURE SERVICES
CONSULTATION ON AMENDMENTS TO FEE REGIME FOR APPLICATIONS IN RESPECT OF S36 AND S37 OF THE ELECTRICITY ACT 1989
1. INTRODUCTION
The purpose of this report is to advise Members of the Planning Service’s suggested response in relation to a Scottish Government Consultation on potential amendments to the existing fee regime in respect of S36 and S37 applications of the Electricity Act 1989.
For general information, Scottish Ministers are responsible for determining applications for consent for electricity generating stations with installed capacity exceeding 1MW (offshore) and 50 MW (onshore) and overhead power lines in Scotland under sections 36 and 37 of the Electricity Act 1989 respectively. The Electricity (Applications for Consent) Regulations 1990 and Electricity Works (Environmental Impact Assessment) (Scotland) Regulations 2017 apply to such applications, which are processed on behalf of Scottish Ministers by the Scottish Government’s Energy Consents Unit (ECU) (onshore) and Marine Scotland (offshore).
The Scottish Government now adopts the principle as set out in the Scottish Public Finance Manual that :
“there should be full cost recovery for all public services which cannot be sustained, as it is standing in the way of the Government's vision where "our public services are high quality, continually improving, efficient and responsive to local people's needs".
It is the view set out in the consultation document that there has been a shortfall in cost recovery for a number of years, which is now impeding the ability to resource these consenting functions in the manner which is required.
It is also clarified in the consultation documentation that:
“Having developed a detailed understanding of costs that we would seek to recover through our fees, we have balanced the desire for cost recovery against impacts on industry. We have considered the extent to which Scottish Ministers can continue to bear the shortfall in costs experienced to date, having regard to the standard approach to setting charges for public services as set out in the Scottish Public Finance Manual which is full cost recovery. We have undertaken a comparative assessment of our fees against other consenting authorities and jurisdictions to arrive at proposed fee increases which we consider to be reasonable in the context of current market conditions. The assessment of application costs is not an exact science, but we have given careful consideration to the fee levels proposed in the consultation paper. On balance, we consider that the proposed fee increases are necessary and proportionate.”
The Consultation takes the form of a number of questions to which a response is sought. The questions and suggested responses are set out at Appendix A of this report. The existing and proposed fee regime, are included as Appendix B to this report (at annex 1), as is general commentary on the reasoning and justification behind the proposed changes to the fee regime.
Members are requested to note that no increase in the fees currently paid to the Planning Authority are proposed as part of this consultation, nor any “up front” payments to cover officer time required to undertake screening and scoping work associated with S36 and S37 applications. It is clarified in the consultation that:
The proposed fee increases outlined in this paper reflect costs to Scottish Ministers and assume planning authorities will not receive any additional money following the implementation of the revised fees. Ministers intend to maintain the existing voluntary payments at current absolute values and they will cease to be the equivalent of two- thirds of the increased application fees Ministers plan to introduce.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Protective Services and Licensing Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.