CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Oban Lorn & The Isles Area Committee, Wednesday 12 June 2019 at 10.30am

CRAIGNURE PIER - STAG REPORT

Agreed Committee 1 paper

Oban Lorn & The Isles Area Committee agreed this item on Wednesday 12 June 2019. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

Decision The Oban, Lorn and the Isles Area Committee agreed:- 1. Officers engage with the local community and partners (Transport Scotland, CMAL and Calmac ) to discuss the findings of the STAG report. 2. Officers make arrangements to move the process onto the next stage i.e to produce the outline business case for both interim and long-term options. 3. All related decisions of the Area Committee be considered by the Harbour Board and; 4. To write to CMal in support of the Communities wish to commission smaller vessels and the introduction a more frequent sailings timetable which would better support existing infrastructure both in Oban and Mull. (Ref: Report by Executive Director of Development and Infrastructure dated 27 May 2019, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Oban Lorn & The Isles Area Committee

Executive summary

1.1The STAG report, which considers the future of Craignure Pier, has now been completed by the consultant Mott MacDonald. This update report provides Members of the Oban, Lorn and the Isles Area Committee with an overview of the STAG report findings; it also asks Members to consider information provided within this report and duly make recommendations to the Harbour Board.

1.2The STAG does not identify a preferred option but establishes the pros and cons of each option. As part of the STAG process, public and stakeholder consultation was carried out; the information gathered was used as the basis of setting objectives and developing and appraising options. In order to seek views on interim and long-term options developed, secondary engagement was undertaken in late 2018. Feedback from the consultation process is provided in Appendix A.

1.3Interim Options: the following ‘Interim Options’ were considered:-

 Do Minimum – Continue monitoring and maintain the existing infrastructure.  Option 1 - Maintenance and Improvements – Demolition of pier building; extend vehicle marshalling area; road realignment.  Option 2 - Pier Extension – Construct new pier extension.  Option 3 - South berth improvements – New fendering piles; sheet piling; dredging at the south berth.

Likely costs for the above options are provided in Appendix B.

1.4Choice of interim options is complex due to the nature of the works i.e. overall costs and their limited life-span. Transport Scotland’s Vessel Replacement and Deployment Plan (VRDP) indicates that the MV Hebrides is scheduled to operate on the Oban to Craignure route. Notwithstanding Transport Scotland’s aspirations to re-deploy the MV Hebrides onto the Oban to Craignure Route (The MV Hebrides is 99 metres in length and carries 98 vehicles, whilst the MV Isle of Mull which currently operates on the route is 90 metres in length and carries 66 vehicles), it is worthy of note that, from the consultation with the local community, the majority of responders would prefer not to have a vessel of this size, but rather two, or possibly three smaller vessels i.e. smaller vessels operating at a higher frequency, as opposed to larger vessels as is currently planned. 1.5 Long-term Options: a number of options were considered for replacement of the existing infrastructure:-

 Option 1A - Rebuild on existing footprint  Option 1B – Rebuild close to existing footprint  Option 2A - Rebuild south – finger pier  Option 2B – Rebuild south – nested berth  Option 3A – Rebuild north – finger pier  Option 3B - Rebuild north – nested berth

Likely costs for the above options are provided in Appendix B. Locations are shown in Appendix C.

1.6Options recommended for future consideration will be 1B, 2A and 3A.

1.7It is recommended that Members consider this report and make the following recommendations to the Harbour Board:-

 That officers engage with the local community and partners (Transport Scotland, CMAL and Calmac) to discuss the findings of the STAG report;

 That officers make arrangements to move the process onto the next stage i.e. to produce an Outline Business Case for both interim options and long-term options.

 That all related decisions of the Area Committee be considered by the Harbour Board. ARGYLL AND BUTE COUNCIL OBAN, LORN AND THE ISLES AREA COMMITTEE

DEVELOPMENT AND 12 JUNE 2019 INFRASTRUCTURE SERVICES

CRAIGNURE PIER – STAG REPORT

2.0INTRODUCTION

2.1The STAG report, which considers the future of Craignure Pier, has now been completed by the consultant Mott MacDonald. This update report provides Members of the Oban, Lorn and the Isles Area Committee with an overview of the STAG report findings; it also asks Members to consider information provided within this report and duly make recommendations to the Harbour Board.

Recommendations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CRAIGNURE PIER: STAG REPORTReport 1.1 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
MD
Councillor Mary-Jean DevonMember, present
KG
Councillor Kieron GreenMember, present
JL
Councillor Jim LynchMember, present
RM
Councillor Roderick McCuishMember, apologies
SJ
Councillor Sir Jamie McGrigorVice-Chair, present
JM
Councillor Julie McKenzieMember, present
ER
Councillor Elaine RobertsonChair, present
AV
Councillor Andrew VennardMember, present

On this subject at Argyll and Bute

Search all
  1. CRAIGNURE PIER - STAG REPORTThis decision
  2. Argyll and bute council: extension to existing car marshalling area and formation of vehicular access: land north west of the pier, craignure, isle of mull (ref: 20/00940/pp)Agreed

More from Argyll and Bute Oban Lorn & The Isles Area Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... Agreed Open
9 Sep 2026 CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... Noted Open
9 Sep 2026 Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... Noted Open
9 Sep 2026 Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... Noted Open
9 Sep 2026 Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies