Resolved
The Audit and Scrutiny Committee agreed to endorse the updated , as outlined at Appendix 1 of the report. (Reference: Report by Chief Executive, dated 18 June 2019, submitted.)
Audit and Scrutiny Committee agreed this item on Tuesday 18 June 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
The Audit and Scrutiny Committee agreed to endorse the updated , as outlined at Appendix 1 of the report. (Reference: Report by Chief Executive, dated 18 June 2019, submitted.)
STRATEGIC RISK REGISTER NEXT REVIEW DATE 14/10/2019
No Risk Corporate Outcome Consequences Gross Risk Current Mitigation Residual Risk Approach Key Actions and Deadlines Last Reviewed Risk Owner Imp Lik Sc Imp Lik Sc Population and Economic Our Economy is Population decline reduces available funding 1. Local outcome improvement plan targets population 1.Deliver Rural Growth Deal (Initial SMT 27 May 2019 Exec Director Decline diverse and thriving impacting on Councils capacity to deliver and economic recovery Phase March 2020) Dev & Infra services. 2. Economic Forum 2.Lobbying activity in pursuit of Failure to identify relevant 3. Maximise external funding opportunities regional immigration policies and factors contributing to the A circle of decline with reduced employment, 4. Strategic economic development action plan related strategies decline and failure to lower earning and failing businesses and poor 5. Strategic infrastructure plan develop strategies and perception of the area. 6. Area economic development action plans 1 actions targeting these 5 4 20 7.Promote and Market Argyll and Bute 4 4 16 Treat factors. Combined population and economic decline 8. Maximise social-eco benefits via effective partnership may increase the need for and cost of services. working
Insufficient people of working age with appropriate skills and experience to fill vacancies across CPP
Condition and suitability Our Infrastructure Infrastructure and asset base does not support 1.Asset management board 1. One Council Property Approach SMT 27 May 2019 Executive of Infrastructure & Asset supports sustainable or is not aligned to business outcomes and 2.Robust capital planning and monitoring 2. Consider implementation of new Directors of D Base growth does not aid effective service delivery. 3. Asset management work plan 2018/2019 capital prioritisation process for & I and CS 4. Business case modelling including sustainability, 2020/21 budget (September 2019) Infrastructure and asset Infrastructure and asset base is allowed to development and strategic change base does not meet deteriorate resulting in cost, lost opportunities 5. Intelligence and best practice sharing via Heads of current and future and wasted resource. Property Group. 2 requirements and is not 4 4 16 6.New schools programme 4 3 12 Treat being used or managed 7.Smarter Places efficiently and effectively. 8. Community Empowerment and Community Asset Transfer – Arrangements in place to evaluate and determine requests. 9. Roads Asset Management Plan 10. Status and Options Report 11. R&A Services control hub and joint operations team
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 8 -App1-ABC Strategic Risk Register for ASC 18 JuneReport | 77 KB | DownloadRead as text |
PDF |
Strategic Risk RegisterReport | 59 KB | Download |
Follow Audit and Scrutiny Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | Internal Audit and Counter Fraud Summary of ActivitiesDecision The Audit and Scrutiny Committee reviewed and endorsed the Summary of Activities report. (Reference: Report ... | Decided | Open |
| 3 Sep 2026 | Internal and External Audit Report Follow Up 2026-27Decision The Audit and Scrutiny Committee endorsed the contents of the report. (Reference: Report by Chief Internal A... | Decided | Open |
| 3 Sep 2026 | Internal Audit Reports to Audit and Scrutiny Committee 2026/2027Decision The Audit and Scrutiny Committee reviewed and endorsed the summary report and detail within each individual ... | Decided | Open |
| 3 Sep 2026 | External Audit Progress UpdateDecision The Audit and Scrutiny Committee agreed to note the information provided. | Agreed | Open |
| 3 Sep 2026 | Verbal Update by Chair(s) of Scrutiny PanelDecision The Audit and Scrutiny Committee noted the information provided. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.