Audit and Scrutiny Committee, Thursday 3 September 2026 at 10.30am

Internal and External Audit Report Follow Up 2026-27

Decided Finance 1 paper

AI summaryArgyll and Bute's Audit and Scrutiny Committee endorsed the Internal and External Audit Report Follow Up 2026-27, noting satisfactory progress on 66 open audit actions across council services and the HSCP.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecided19 actions due by 30 June 2026, 47 due after
Money£143kOutstanding Piers and Harbours debt at end June
What happens nextOversight continuesAppendices detail delayed actions and School Trips work
Who it affectsCouncil services and HSCPIncludes Education, Roads, Finance, Social Care

What was decided

The Committee endorsed the contents of the follow up report, accepting the Chief Internal Auditor's update on progress with open audit actions. Report 2.1, 4.1

Why

Satisfactory progress continues to be made implementing audit actions, according to the conclusion in the officer report. Report 4.1

All implications under policy, financial, legal, HR, risk, equalities and climate change were recorded as none. Report 5.1

What happens next

Several audit actions have been rescheduled or delayed; the appendices set out revised dates and progress updates for services including Development and Economic Growth, HSCP Strategic Planning, Roads and Infrastructure, and Children and Families. Report 3.3, P25, P26, P40, P47, P48

Education Performance and Improvement has completed all agreed actions on the Process for School Residential Trips, with updated EMCs and appendices received in August 2026. Report 3.4, P58, P60, P63, P65, P68

The money

  • £143k Outstanding debt owed to the Council at end of June for Piers and Harbours Report P56

Options considered

  • Chosen: Endorse the contents of the report. Committee accepted satisfactory progress against open audit actions Report 2.1, 4.1

Implications

  • Other: Policy, Financial, Legal, HR, Customer Service, Risk, Climate Change, Islands, Fairer Scotland Duty, Equalities, Consumer Duty, and Children's Rights implications all recorded as none. Report 5.1

Who and where

  • Council services across Development and Economic Growth, Education, Roads and Infrastructure, Financial Services, Customer Support, Commercial Services, Legal and Regulatory Support, and LiveArgyll Report P10, P11, P14, P15, P16, P17
  • Argyll and Bute Health and Social Care Partnership, including Adult Services, Children and Families and Justice, and Strategic Planning, Performance and Technology Report P10, P11, P14, P15, P16, P17
  • Oban Airport fuelling operations staff and managers Report P25
  • Piers and Harbours users, including CalMac and fish farming businesses Report P47, P48, P49

Timeline

  • 31/03/2024 to 30/09/2025: Original and revised target dates across various open actions Report P25, P26, P37
  • 30 June 2026: Cut-off for first table of audit actions, with 19 actions tracked Report 3.1, P11
  • 25 August 2026: Updated EMC 3.25 and appendices received for School Residential Trips Report P58, P63, P68
  • 26 August 2026: Updated EMC 3.14 and appendix received; School Trips Procedure Manual received Report P60, P65
  • 31 August 2026: Original target completion date for School Residential Trips working group actions Report P57, P59, P61, P63, P65, P67
  • 31 Dec 2026: Revised target dates for several rescheduled actions including Piers and Harbours and IJB training Report P25, P26, P28, P29, P30, P32, P33, P34, P35, P47, P48, P49, P51, P52, P53, P54, P55
  • 31 Mar 2027: Revised target date for Capital Governance Arrangements and Children and Families external placements work Report P40, P43, P45

Plain English for the jargon

  • HSCP: Health and Social Care Partnership, covering both Argyll and Bute Council and NHS Highland services
  • IJB: Integration Joint Board, the body that directs integrated health and social care functions
  • EMC: Education Memorandum Circular, an internal council education policy document
  • EVOLVE: Online system used for managing and recording school educational visits and trips
  • SPB: Strategic Policy Board, an Argyll and Bute HSCP governance group
  • SMT/DMT: Senior/Departmental Management Team within council services
  • PCCMT: Procurement and Commercial Contract Management Team
  • KF/DH: Officer initials denoting the lead councillor or senior officer group responsible for the service area
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

Decision The Audit and Scrutiny Committee endorsed the contents of the report. (Reference: Report by Chief Internal Auditor, dated 3 September 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Audit and Scrutiny Committee

Recommendations

2.1To endorse the contents of the report.

3.0DETAIL

3.1The two tables below provide a numerical summary of open audit actions with a split between actions due by and due after 30 June 2026.

3.2Appendix 1 provides a visual representation of progress in addressing agreed actions.

3.3Appendix 2 provides further detail on actions that have been delayed and rescheduled.

3.4Appendix 3 provides details of steps taken to complete all agreed actions in respect of the Process for School Residential Trips. Table 1 - Actions Due by 30 June 2026

SLT/Service

Rescheduled

Superseded Complete

Delayed/

Total KF – Development & Economic Growth 1 1 0 2 KF – Financial Services 2 0 0 2 H&SCP (SW) – Adult Services (Hospital & Community 0 1 0 1 Services) H&SCP (SW) – Adult Services (Complex Care & 0 1 0 1 Registered Services H&SCP (SW) – Children and Families and Justice 2 2 0 4 H&SCP (IJB) – Strategic Planning, Performance & 1 7 1 9 Technology TOTAL 6 12 1 19

Table 2 - Actions due after 30 June 2026

SLT/Service

Rescheduled

On Course Complete

Delayed/

Total DH – Commercial Services 0 0 2 2 DH – Education Performance & Improvement 6 0 0 6 DH – Education Wellbeing, Inclusion & Achievement 0 0 5 5 DH – Legal & Regulatory Support 0 0 2 2 KF – Financial Services 0 2 5 7 KF – Roads & Infrastructure Services 2 5 6 13 KF – Customer Support Services 0 0 2 2 KF – Development & Economic Growth 1 0 2 3 H&SCP (IJB) – Adult Services (Hospital & Community 0 0 2 2 Services) H&SCP (IJB) – Strategic Planning, Performance & 0 0 2 2 Technology H&SCP (SW) – Adult Services (Hospital & Community 0 0 2 2 Services) LiveArgyll 0 0 1 1 TOTAL 9 7 31 47

4.0CONCLUSION

4.1Satisfactory progress continues to be made implementing audit actions. 5.0 IMPLICATIONS

5.1Policy – None 5.2 Financial – None 5.3 Legal – None 5.4 HR – None 5.5 Customer Service – None 5.6 Risk – None 5.7 Climate Change – None 5.8 Islands – None 5.9 Fairer Scotland Duty – None 5.10 Equalities – None 5.11 Consumer Duty – None 5.12 Children’s Rights and Wellbeing – None

Paul MacAskill Chief Internal Auditor 3 September 2026

For further information contact: Paul MacAskill, 01546 604108 [email protected]

APPENDICES Appendix 1 – Visual representations of progress in addressing agreed actions Appendix 2 – Action Plan Points Delayed & Rescheduled and Superseded Appendix 3 – Steps taken to complete all agreed Process for School Residential Trips Actions Appendix 1 – Visual Representations of Progress in Addressing Agreed Actions Appendix 2 - Action Plan Points Delayed & Rescheduled or Superseded

Action Plan Points due by 30 June 2026

Service, Report, Plan no. & finding Agreed Action Original and Comment Responsible Officer Revised Dates DEVELOPMENT & ECONOMIC GROWTH Management will implement a 31/03/2026 Presentation in progress - to be Oban Airport Station formal training and competency 30/06/2026 added onto training programme Manager FUEL - OBAN AIRPORT framework for fuelling 30 Sep 2026 on Redkite. Training Records operations, including Training records for fuelling operations are documented induction, Delayed and Rescheduled LOW

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal and External Audit Report Follow Up 2026-27Report 537 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 9 attended
JW
Janice Wason HallChair, present
DH
Councillor Daniel HampseyMember, apologies
GH
Councillor Graham HardieMember, apologies
FH
Councillor Fiona HowardMember, apologies
LI
Lynsey InnisSecretary, expected
RK
Councillor Reeni Kennedy-BoyleMember, present
KM
Katie McKenzieSecretary, expected
GM
Councillor Gary MulvaneyVice-Chair, present
AV
Councillor Andrew VennardMember, present

On this subject at Argyll and Bute

Search all
  1. Internal and External Audit Report Follow Up 2026-27This decision
  2. Internal and External Audit Report Follow Up 2025-26Decided
  3. Internal and External Audit Report Follow Up 2025-26Decided
  4. Internal and External Audit Report Follow Up 2025-26Decided
  5. Internal and External Audit Report Follow Up 2025-26Decided
  6. Internal and external audit report follow up report 2024-2025Agreed

More from Argyll and Bute Audit and Scrutiny Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Internal Audit and Counter Fraud Summary of ActivitiesDecision The Audit and Scrutiny Committee reviewed and endorsed the Summary of Activities report. (Reference: Report ... Decided Open
3 Sep 2026 Internal Audit Reports to Audit and Scrutiny Committee 2026/2027Decision The Audit and Scrutiny Committee reviewed and endorsed the summary report and detail within each individual ... Decided Open
3 Sep 2026 External Audit Progress UpdateDecision The Audit and Scrutiny Committee agreed to note the information provided. Agreed Open
3 Sep 2026 Verbal Update by Chair(s) of Scrutiny PanelDecision The Audit and Scrutiny Committee noted the information provided. Noted Open
3 Sep 2026 Treasury Management Update - Quarter Ended 30 June 2026Decision The Audit and Scrutiny Committee noted the contents of the report and the treasury activity during the perio... Noted Open