Resolved
Decision The Committee noted the contents of the report. (Reference: Report by Head of Development and Economic Development, submitted)
Planning, Protective Services and Licensing Committee noted this item on Wednesday 22 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee noted the contents of the report. (Reference: Report by Head of Development and Economic Development, submitted)
Argyll and Bute Council Development and Economic Growth
PLANNING, PROTECTIVE SERVICES AND LICENSING COMMITTEE – 22nd January 2020 ____________________________________________________________________________
UPDATE ON RECENT SCOTTISH GOVERNMENT PLANNING APPEAL DECISIONS ____________________________________________________________________________
A) INTRODUCTION
This report summarises the outcome of recent appeal decisions by the Planning and Environmental Appeals Division (DPEA) for the conjoined Killean & Clachaig Glen Public Local Inquiry held in January 2019. The outcome for each of the individual cases are set out below.
B) RECOMMENDATION
Members are asked to note the contents of the report.
C) DETAILS OF APPEAL DECISIONS
Planning Authority: Argyll & Bute Council (Section 36 Consultation) Planning application ref: 16/03400/S36 Planning appeal ref: WIN-130-3 Proposal: S36 Consultation for proposed Killean Wind Farm Location: Killean Wind Farm, Tayinloan, Argyll and Bute
Date of decision: 18th December 2019
The Planning Authority objected to this application on the 18th October 2017. The Planning Committee agreed with the planning officer’s recommendation to object to the proposal as the proposed development would be contrary to local development plan policies, supplementary guidance, landscape capacity study and Scottish Planning Policy on the basis that the development would be unacceptable due to the adverse landscape and visual impacts which would occur.
In accordance with the terms of paragraph 2(2) of Schedule 8 to the Act, the Scottish Ministers caused a Public Local Inquiry to be held. The Killean wind farm application was considered by the Reporters alongside an appeal relating to a nearby proposed wind farm at Clachaig Glen (PPA-130-2064), which was recalled by Scottish Ministers to enable the cumulative impacts of both Killean and Clachaig Glen wind farm proposals to be considered. The conjoined Public Inquiry and Hearing Sessions took place in January 2019.
Reporters’ conclusions
The Reporters’ concluded that:
With regard to Schedule 9 of the Electricity Act, the Company has minimised impacts where possible within the parameters of the chosen site and submitted design. The scale of the harmful visual effects on the proposed development would outweigh the benefits of the project. Notwithstanding national energy policy support, both the Scottish Planning Policy and Policy LDP 6 of the local development plan require Ministers to give consideration to visual impacts. It is considered that the proposal is contrary to local development plan policy LDP 6. The proposal does not benefit from the Scottish Planning Policy presumption in favour of sustainable development because of the substantial adverse visual impacts, both individually and cumulatively.
Reporters’ Recommendation
For the above reasons, and after taking account of the advice of Scottish Natural Heritage, the Reporters’ agree with the Council and Community Councils that the consent should be refused. The visual impacts are unacceptable due to the siting and size of the turbines.
The Scottish Ministers’ Decision
The Scottish Ministers refused the application for consent under Section 36 of the Electricty Act 1989 for the construction and operation of the proposed development on the 18th December 2019. The Scottish Ministers decision is final, subject to the right of any aggrieved person to apply to the Court of Session for judicial review. Judicial review is the mechanism by which the Court of Session supervises the exercise of administrative functions, including how the Scottish Ministers exercise their statutory function to determine applications of consent.
Full details of the appeal decision can be viewed on the DPEA website: https://www.dpea.scotland.gov.uk/CaseDetails.aspx?ID=118391
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
UPDATE ON RECENT SCOTTISH GOVERNMENT PLANNING APPEAL DECISIONSDecisions | 76 KB | DownloadRead as text |
Follow Planning, Protective Services and Licensing Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.