Decision The Community Services Committee - 1. Noted the contents of the report. 2. Agreed that the condition survey, scheduled for 2021/22, was brought forward to this year. (Reference: Report by Executive Director with responsibility for Education, dated 3 March 2020, submitted.)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report sets out the current position in respect of Dalintober Primary School, in response to concerns that have been raised in respect of the condition and safety of the building.
1.2Members are asked to:-
1.2.1 Note the contents of the report; and
1.2.2 Agree that the condition survey, currently scheduled for 2021/22, is brought forward to this year. ARGYLL AND BUTE COUNCIL COMMUNITY SERVICES COMMITTEE CUSTOMER SERVICES 12 MARCH 2020
DALINTOBER PRIMARY SCHOOL
2.0INTRODUCTION
2.1This report sets out the current position in respect of Dalintober Primary School, in response to concerns that have been raised in respect of the condition and safety of the building.
Recommendations
Members are asked to:-
3.1Note the contents of the report; and
3.2Agree that the condition survey, currently scheduled for 2021/22, is brought forward to this year.
4.0DETAIL
4.1Dalintober Primary School is situated in the former royal burgh of Campbeltown. The oldest part of the building was built in 1889. Dalintober currently has a primary school roll of 255 and provides Early Learning and Childcare (ELC) for 54 children. 4.2 In recent weeks there has been public comment in the local press in respect of the condition of the building. This has been in response to two separate incidents, which took place during the weekend of 25th/26th January, and on 24th February 2020, where internal ceiling plaster/wall plaster have failed. There were no injuries associated with either incident. Initial assessments indicate than both incidents were consider to be caused by water ingress. 4.3 In respect of the initial incident at the end of January 2020, a decision was taken to relocate P5-7 pupils to Campbeltown Grammar School from 29th January until 7th February, and to move ELC – P4 to the senior end of the school during this period to ensure the safety of all pupils and to allow assessment/remedial works to be undertaken as quickly as possible. The management of this, with clear and timely communications to parents/carers, ensured that this was a smooth process for all involved. The second incident at the end of February 2020 was not related to the initial incident or any repair works undertaken. Immediate action was taken by Property Services to make safe and arrange the necessary repair. There was no pupil displacement required due to the second incident. 4.4 Since 30th January 2020 inspections have been undertaken by the Council Property Officers and the Council’s Term Contractor, both at the time of the initial incident and follow up at the second incident, with circa £50K having been spent on ceiling remedial works. The following works are also planned:- Quotes currently being obtained for an upgrade of roof leadwork. 12 new windows will be installed at Easter, subject to delivery periods £20k programmed and budgeted for internal upgrade in 2020/21 A new condition survey was planned for 20/21 which will be carried out using the updated Scottish Government core facts template. In order to minimise any potential disruption to the School, the service will now bring forward the scheduled condition survey to this year with anticipated completion by Easter 2020 In the event that there are deemed to be any structural issues identified in the condition survey a structural engineer will be used to undertake a structural survey of the areas of concern.
4.5The Policy Lead for Education and the Executive Director with responsibility for Education visited the premises on 19th February 2020, as part of a wider programme of Kintyre School visits, and found the school to be thriving with a committed Head Teacher and staff group. No major concerns were raised by staff during this visit and the support put in place to date has been valued by the school.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.