CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Audit and Scrutiny Committee, Tuesday 17 March 2020 at 11.15am

Scrutiny of Business Case Review (Rothesay Pavilion)

Agreed Finance 1 paper

Audit and Scrutiny Committee agreed this item on Tuesday 17 March 2020. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

The Audit and Scrutiny Committee: 1. considered the indicative scope and objectives of a scrutiny review of the process followed to assess the Rothesay Pavilion business case; 2. considered the factors highlighted which may reduce the capacity of the scrutiny process to be robust and well evidenced; 3. considered an alternative area of focus relating to guidance on the award of external funding and review of future business cases; 4. agreed that a review should be conducted on the pre-decision scrutiny of a business case with reference to the newly updated Following the Public Pound guidance and the work being carried out by the Asset Management Board, using as context the knowledge of what happened in Rothesay Pavilion; and 5. agreed that this be included within the scope of the 2020/21 Scrutiny Plan. (Ref: Report by Chief Internal Auditor, dated 17 March 2020, submitted.)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Audit and Scrutiny Committee

Summary

1.1The 24 January 2020 Audit and Scrutiny Committee meeting asked the Chief Internal Auditor (CIA) to carry out initial scoping for a possible scrutiny topic relating to Rothesay Pavilion and bring a report to the next meeting.

1.2The report provides background information, presents an outline of an indicative scope and sets out some further factors for consideration.

1.3Reports on the Rothesay Pavilion taken to various Council committee meetings have contained commercially sensitive information so have been tabled as exempt items. Commercially sensitive information has not been replicated in this report to avoid the need for it to be treated as an exempt item. The information contained in this report is information which is already publically available.

1.4Should the Audit and Scrutiny Committee determine that a scrutiny review focused on the Rothesay Pavilion business case should be conducted then care will need to be taken in terms of what information is made available in any publically available report.

Recommendations

2.1The Audit and Scrutiny Committee is asked to:

2.1.1 Consider the indicative scope and objectives of a scrutiny review of the process followed to assess the Rothesay Pavilion business case.

2.1.2 Consider the factors highlighted which may reduce the capacity of the scrutiny process to be robust and well evidenced.

2.1.3 Consider an alternative area of focus relating to guidance on the award of external funding and review of future business cases.

2.1.4 Determine whether they wish to conduct a review and, if so, the focus of the review, how they wish to proceed and the scale of the review to be conducted.

3. DETAIL

Background

3.1In 2007, the Council decided to take each of the town centre and waterfront projects as part of the larger CHORD programme to Outline Business Case (OBC) stage and that these would be subject to independent scrutiny. It was agreed that one consultancy firm be appointed to prepare the OBC for all town centre and waterfront projects and a separate firm appointed to score them against revised scoring criteria agreed by the Council in 2008.

3.2Project boards of key stakeholders were established for each project comprising of relevant Councillors, officials and local stakeholders to work with the consultants and sign off their OBC.

3.3The process for taking forward the CHORD Programme was endorsed in December 2008 by the Executive Committee. Each Project Board was tasked to prepare a Project Initiation Document (PID). In June 2011 a report detailing each PID associated with the CHORD Programme was presented to the Programme Management Board for consideration. The PID for Rothesay Pavilion was approved at this meeting.

3.4In July 2011 consideration was given to a report advising on the next steps to be taken by the Rothesay Project Team following completion of the interim full Business Case (FBC) for Rothesay Pavilion.

3.5Full Council considered the FBC at their meeting on 23 April 2015 and agreed the recommendations contained within. This was an exempt item as there was commercial information contained within the report.

3.6Full funding for the project was achieved in September 2017 and a construction contract of £10.7 million was awarded to Messrs CBC on 29 November 2017 with a contract completion date of 31 July 2019.

3.7Capital funding for the project is being provided by the Council and a number of external funders, including Heritage Lottery Fund, Highlands and Islands Enterprise, European Regional Development Fund amongst others.

3.8On completion the building will be managed by Rothesay Pavilion Charity (RPC) who will lease the building from the Council for a term of 25 years.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Scrutiny of Business Case Review (Rothesay Pavilion)Report 101 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
MC
Martin CaldwellChair, present
JF
Councillor Jim FindlayMember, present
GF
Councillor George FreemanMember, present
LI
Lynsey InnisSecretary, expected
SJ
Councillor Sir Jamie McGrigorMember, present
AR
Councillor Alan ReidMember, present
ST
Councillor Sandy TaylorVice-Chair, present
RT
Councillor Richard TrailMember, present
AV
Councillor Andrew VennardMember, present

More from Argyll and Bute Audit and Scrutiny Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Internal Audit and Counter Fraud Summary of ActivitiesDecision The Audit and Scrutiny Committee reviewed and endorsed the Summary of Activities report. (Reference: Report ... Decided Open
3 Sep 2026 Internal and External Audit Report Follow Up 2026-27Decision The Audit and Scrutiny Committee endorsed the contents of the report. (Reference: Report by Chief Internal A... Decided Open
3 Sep 2026 Internal Audit Reports to Audit and Scrutiny Committee 2026/2027Decision The Audit and Scrutiny Committee reviewed and endorsed the summary report and detail within each individual ... Decided Open
3 Sep 2026 External Audit Progress UpdateDecision The Audit and Scrutiny Committee agreed to note the information provided. Agreed Open
3 Sep 2026 Verbal Update by Chair(s) of Scrutiny PanelDecision The Audit and Scrutiny Committee noted the information provided. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies