The Audit and Scrutiny Committee: 1. considered the indicative scope and objectives of a scrutiny review of the process followed to assess the Rothesay Pavilion business case; 2. considered the factors highlighted which may reduce the capacity of the scrutiny process to be robust and well evidenced; 3. considered an alternative area of focus relating to guidance on the award of external funding and review of future business cases; 4. agreed that a review should be conducted on the pre-decision scrutiny of a business case with reference to the newly updated Following the Public Pound guidance and the work being carried out by the Asset Management Board, using as context the knowledge of what happened in Rothesay Pavilion; and 5. agreed that this be included within the scope of the 2020/21 Scrutiny Plan. (Ref: Report by Chief Internal Auditor, dated 17 March 2020, submitted.)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The 24 January 2020 Audit and Scrutiny Committee meeting asked the Chief Internal Auditor (CIA) to carry out initial scoping for a possible scrutiny topic relating to Rothesay Pavilion and bring a report to the next meeting.
1.2The report provides background information, presents an outline of an indicative scope and sets out some further factors for consideration.
1.3Reports on the Rothesay Pavilion taken to various Council committee meetings have contained commercially sensitive information so have been tabled as exempt items. Commercially sensitive information has not been replicated in this report to avoid the need for it to be treated as an exempt item. The information contained in this report is information which is already publically available.
1.4Should the Audit and Scrutiny Committee determine that a scrutiny review focused on the Rothesay Pavilion business case should be conducted then care will need to be taken in terms of what information is made available in any publically available report.
Recommendations
2.1The Audit and Scrutiny Committee is asked to:
2.1.1 Consider the indicative scope and objectives of a scrutiny review of the process followed to assess the Rothesay Pavilion business case.
2.1.2 Consider the factors highlighted which may reduce the capacity of the scrutiny process to be robust and well evidenced.
2.1.3 Consider an alternative area of focus relating to guidance on the award of external funding and review of future business cases.
2.1.4 Determine whether they wish to conduct a review and, if so, the focus of the review, how they wish to proceed and the scale of the review to be conducted.
3. DETAIL
Background
3.1In 2007, the Council decided to take each of the town centre and waterfront projects as part of the larger CHORD programme to Outline Business Case (OBC) stage and that these would be subject to independent scrutiny. It was agreed that one consultancy firm be appointed to prepare the OBC for all town centre and waterfront projects and a separate firm appointed to score them against revised scoring criteria agreed by the Council in 2008.
3.2Project boards of key stakeholders were established for each project comprising of relevant Councillors, officials and local stakeholders to work with the consultants and sign off their OBC.
3.3The process for taking forward the CHORD Programme was endorsed in December 2008 by the Executive Committee. Each Project Board was tasked to prepare a Project Initiation Document (PID). In June 2011 a report detailing each PID associated with the CHORD Programme was presented to the Programme Management Board for consideration. The PID for Rothesay Pavilion was approved at this meeting.
3.4In July 2011 consideration was given to a report advising on the next steps to be taken by the Rothesay Project Team following completion of the interim full Business Case (FBC) for Rothesay Pavilion.
3.5Full Council considered the FBC at their meeting on 23 April 2015 and agreed the recommendations contained within. This was an exempt item as there was commercial information contained within the report.
3.6Full funding for the project was achieved in September 2017 and a construction contract of £10.7 million was awarded to Messrs CBC on 29 November 2017 with a contract completion date of 31 July 2019.
3.7Capital funding for the project is being provided by the Council and a number of external funders, including Heritage Lottery Fund, Highlands and Islands Enterprise, European Regional Development Fund amongst others.
3.8On completion the building will be managed by Rothesay Pavilion Charity (RPC) who will lease the building from the Council for a term of 25 years.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.