ARGYLL AND BUTE COUNCIL HELENSBURGH & LOMOND AREA COMMITTEE (PROJECT BOARD) CUSTOMER SERVICES 24 JUNE 2020
HELENSBURGH WATERFRONT DEVELOPMENT (HWD) – CONTRACT AWARD AND FULL BUSINESS CASE
1.0INTRODUCTION 1.1. This report aims to summarise the proposed contract award and full business case of the Helensburgh Waterfront Development (HWD) Project. 1.2. As part of the Councils Approval process Helensburgh Waterfront Development Contract Award and Full Business Case Report is first being considered by the Helensburgh and Lomond Area Committee (Project Board) at a Special Meeting on the 24th June 2020, before being considered for approval at the Business Continuity Meeting of the 25th June 2020. These reports are restricted due to the Commercial Sensitivities of the information contained within and by virtue of Paragraphs 8, 9 of Schedule 7A of the Local Government (Scotland) Act 1973 it is recommended that both of these reports are considered as exempt from the Public. 1.3. The following sections provides members and the public, with a summary of: the background to the project; the procurement exercise for the Public Works Contract; and the development of the Full Business Case, which is developed in more detail with the full report. 1.4. Business Continuity Committee approval of the Full Business Case, Capital Budget allocation and Contract Award is now required to enable this essential piece of infrastructure to be delivered. 2.0 RECOMMENDATIONS 2.1. The full report includes the following recommendations to members, and provides them with the detail necessary for them to make an informed decision: 2.1.1. Business Continuity Committee are invited to note the outcome of the Tender Evaluation and the determination of the tenderer having submitted the Most Economically Advantageous Tender, as detailed in the full report. 2.1.2. Business Continuity Committee are invited to note that the commercial outcome of the evaluation has been incorporated into the anticipated final costs for the project, which have informed the development of the Full Business Case, and in particular the economic and financial cases.
Page 1 2.1.3. Business Continuity Committee are invited to approve the Full Business Case, Capital Budget allocation, and the award of the Public Works Contract.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.