Decision The Committee noted the background report and that the recommendations as outlined in the public report would be given full consideration at Item 12 (c) of this Minute. (Ref: Report by Executive Director for Commercial Services dated 25 June 2020, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL BUSINESS CONTINUITY COMMITTEE CUSTOMER SERVICES 25 JUNE 2020
HELENSBURGH WATERFRONT DEVELOPMENT (HWD) – CONTRACT AWARD AND FULL BUSINESS CASE
1.0INTRODUCTION 1.1. The main purpose of the full report to the Business Continuity Committee is to seek members’ approval of the Full Business Case, Capital Budget allocation, and the recommendation for the award of a Publics Works Contract for the Helensburgh Waterfront Flood Defence, Amenities & Leisure Services Improvements. 1.2. The following sections provides members and the public, with a summary of: the background to the project; the procurement exercise for the Public Works Contract; and the development of the Full Business Case, which is developed in more detail with the full report. 1.3. The Helensburgh and Lomond Area Committee considered a similar report at its meeting on the 24 June 2020 1.4. Business Continuity Committee approval of the Full Business Case, Capital Budget allocation and Contract Award is now required to enable this essential piece of infrastructure to be delivered. 2.0 RECOMMENDATIONS 2.1. The full report includes the following recommendations to members, and provides them with the detail necessary for them to make an informed decision: 2.1.1. Business Continuity Committee are invited to note the outcome of the Tender Evaluation and the determination of the tenderer having submitted the Most Economically Advantageous Tender, as detailed in the full report. 2.1.2. Business Continuity Committee are invited to note that the commercial outcome of the evaluation has been incorporated into the anticipated final costs for the project, which have informed the development of the Full Business Case, and in particular the economic and financial cases. 2.1.3. Business Continuity Committee are invited to approve the Full Business Case, Capital Budget allocation, and the award of the Public Works Contract.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2021-22 to 2025-26Decision The Committee noted the current estimated budget outlook position for the period 2021-22 to 2025-26. (Ref: R...
Budget planning 2021-22 and beyondDecision The Committee:- 1. Agreed to the overall budget approach for 2021-22 and the themed reviews as identified in...
Public conveniences remobilisationDecision The Committee:- 1. Agreed to Option 2, that is to keep the current 35 public conveniences open until the end...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.