Resolved
Decision 1. With reference to page 18 of the agenda pack circulated for the first calling of the LRB, which detailed the reason for refusal, the LRB noted that the reason for refusal referred to the installation of 108 solar photovoltaic roof mounted panels covering an area of 176.m², each panel measuring 1698mm by 1004mm and pitched at a 10 degree angle facing with a specific design. 2. The LRB further noted the information submitted by the Applicant’s Agent in answer to the LRB’s request (page 7 of Agenda pack for 2 nd calling). The Agent indicates that they had proposed 108 panels as part of the pre-application process but when it got to the full application stage they had revised that down to 94 panels which reduced the area of 155.8m² with an alternative design. 3. The LRB also noted that on page 12 of the Agenda pack for the 1 st calling, it showed a plan marked as refused but it looked like the plan for the 94 plan proposal. 4. With reference to points 1 – 3 above, the Argyll and Bute LRB agreed to request the following further written information from the Planning Officer: a) Clarity on whether the decision to refuse the application was based on the 108 panel proposal discussed at the pre-application stage, or based on the revised 94 panel proposal with alternative design submitted by the Applicant at full application stage; b) If the proposal was refused on the basis of 108 panels, the LRB requested the Planning Officer review the 94 panel proposal including the alternative design to see if their determination would be any different to that of the 108 proposal; c) To ask the Planning Officer to seek clarity from the Design and Conservation Officer on whether or not the 94 panel proposal would be contrary to policy LDP ENV 16 ... view the full minutes text for item 3.