Decision The Policy and Resources Committee – 1. Noted the Revenue Budget Monitoring Report as at 31 December 2020 and noted the comments in respect of the Health and Social Care Partnership. 2. Noted the progress with the Policy Savings Options as at 31 December 2020. 3. Noted the Financial Risks for 2020-21. 4. Noted the Capital Plan Monitoring Report as at 31 December 2020. 5. Noted the Treasury Monitoring Report as at 31 December 2020. 6. Noted the Reserves and Balances Report as at 31 December 2020. 7. Agreed to recommend to Council that the revenue virements over £0.200m during November and December be approved. (Reference: Report by Section 95 Officer dated 8 February 2021, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITEE
FINANCIAL SERVICES 18 FEBRUARY 2021
FINANCIAL REPORTS MONITORING PACK – 31 DECEMBER 2020
1. INTRODUCTION
1.1This report provides a summary of the financial monitoring reports as at the end of December 2020. There are six detailed reports summarised in this Executive Summary:
• Revenue Budget Monitoring Report as at 31 December 2020 • Monitoring of Policy Savings Options as at 31 December 2020 • Monitoring of Financial Risks as at 31 December 2020 • Capital Plan Monitoring Report as at 31 December 2020 • Treasury Monitoring Report as at 31 December 2020 • Reserves and Balances as at 31 December 2020
2. DETAIL
2.1Revenue Budget Monitoring Report
2.1.1 This report provides a summary of the current revenue budget monitoring position to ensure net expenditure is contained within budget. It provides corporate and departmental information with comparisons on a forecast outturn and a year to date basis.
2.1.2 There is a forecast overspend of £5.124m as at the end of December 2020. There are two main factors contributing to this forecast: - The additional pressures forecast in relation to COVID-19 as detailed in Appendix 1 of the Financial Reports Monitoring Pack Report. Officers have identified a number of options to bring current year spending back in line with budget including the funds made available via the national lost income scheme, use of financial flexibilities and the identification of in year savings. - The estimated overspend within Social Work which is due to a combination of forecast slippage on the delivery of agreed savings and a high demand for services. The HSCP has contributed to a local mobilisation plan on a regular basis and it has now been confirmed that the Scottish Government will make funding available for the undelivered savings and as a result Social Work will no longer be overspent.
2.1.3 The impact of COVID is detailed in Appendix 1 however can be summarised as new additional costs of £11.142m for which £9.038m of Scottish Government Funding has been provided with an additional £0.616m of flexibility around existing funding and £0.875m of identified underspends, the use of reserves and loans fund investment income. This leaves an estimated shortfall of £0.613m.
2.1.4 There is a year to date overspend of £0.397m. More focus is on the forecast outturn position, hence why sometimes the year to date position is not updated. The year to date variances mainly relate to the timing of income and expenditure, recharging of costs to capital and the impact of COVID-19.
Health and Social Care Partnership (HSCP) – Financial Update
2.1.5 The forecast outturn position at the end of December is an estimated overspend of £1.662m for 2020-21 (£1.879m overspend for Social Work and £0.217m underspend Health).
2.1.6 The Social Work overspend does not include any additional costs incurred as a result of COVID-19, due to there being an expectation that these will be covered by Scottish Government. The HSCP has contributed to a local mobilisation plan on a regular basis and it has now been confirmed that the Scottish Government will make funding available for the undelivered savings and as a result Social Work will no longer be overspent.
2.2Monitoring of Policy Savings Options
2.2.1 The purpose of this report is to provide Members with an update on the implementation and delivery of the Service Package Policy Options:
- agreed by Council in February 2020 - agreed in February 2019 that were either not delivered in 2019-20 or have further increases in value in 2020-21 onwards - agreed in February 2018 with further increases in value in 2020-21 onwards.
2.2.2 The savings options will be reported as being delivered, on track to be delivered, still to be implemented, being developed, potential shortfall or delayed.
2.2.3 Of the 66 savings options, 55 have already been delivered, 1 is on track to be delivered as per their timescale, 4 have a potential shortfall and 6 are delayed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.