Noted Committee 1 paper

AI summaryArgyll and Bute Policy and Resources Committee noted an update on Iran conflict financial impact, with 2026-27 pressure estimated at up to £0.330m and a £2m contingency already in place.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted update on financial impact of Iran conflict
MoneyUp to £0.330mEstimated financial pressure on 2026-27 budget
What happens nextMonitor and use contingencyELT to authorise drawdowns from £2m contingency as needed
Who it affectsCouncil budget, staff, residentsService demand expected to rise as living costs increase

What was decided

The committee noted the contents of the report, which sets out the latest estimated financial impact of the Iran conflict on the council's 2026-27 revenue and capital budgets. Report 1.4, 3.1

Why

Financial Services reviewed the potential impact of the conflict on revenue and capital budgets, though quantification has been challenging and the figures should be treated with caution. Report 1.1, 1.2, 2.1, 2.2

Cost increases in business mileage, vehicle fuel, and food are emerging, with further pressures possible later, including construction, borrowing, and pay award costs. Report 4.2, 4.3, P14, P16

What happens next

Continue tracking the conflict and reflect any financial impact in routine financial monitoring reports.

Should costs materialise, drawdowns from the £2m contingency will be authorised by the Executive Leadership Team in consultation with the Leader, Deputy Leaders and relevant Policy Lead, with virements reported retrospectively. Report 4.5, 5.3

The money

  • £0.330m Total estimated financial pressure on 2026-27 budget excluding construction, borrowing and pay award impacts Report 1.3
  • 120 Estimated annual cost increase for business mileage following HMRC rate rise from 45p to 55p for first 10,000 miles Report P14
  • Up to 90 Estimated 2026-27 impact on utilities and vehicle fuel costs, based on CPI forecasts Report P14
  • Up to 120 Estimated 2026-27 impact on food costs, based on CPI forecasts Report P14
  • £1.3m to £3.5m Possible range of construction cost impact in 2027-28, based on Ukraine conflict experience of 3%-8% material inflation Report 4.3, P16
  • £2.2m Cost to the council of every 1% increase in the pay award Report 4.3, P16
  • £900k Capital budget already set aside from unallocated Roads Reconstruction funds to cover material inflation Report 4.4
  • £2m Contingency created from 2025-26 underspend to address any conflict-related pressures, approved by Council on 24 June 2026 Report 4.5, 5.3

Options considered

  • Chosen: Note the report as recommended. Recommended by the Section 95 Officer so the committee could consider the latest estimated impact Report 1.4, 3.1

Implications

  • Financial: The conflict represents a material and multi-year risk to the council's financial position, with construction, borrowing and pay award impacts not yet quantified. Report 5.1
  • Staffing: The escalating cost of living may influence pay negotiations for the 2027/28 settlement.
  • Risk: Ongoing conflict poses significant financial and service delivery risks to the council and communities throughout Argyll and Bute.
  • Equalities: Rising prices and transport costs are expected to disproportionately affect island communities, and rising living costs are anticipated to negatively affect children's wellbeing and increase demand for support such as free school meals.
  • Other: Rising living expenses are expected to increase demand for assistance from the council, central government and the wider public sector.

Who and where

  • Argyll and Bute Council's 2026-27 revenue and capital budgets Report 1.3, 4.1
  • Council staff subject to future pay award negotiations Report 4.3
  • Island communities in Argyll and Bute
  • Children and families potentially needing increased support, including free school meals
  • Roads Reconstruction schemes, where £900k has been ring-fenced against material inflation Report 4.4

Timeline

  • 21 May 2026: Initial report on potential Iran conflict impact presented to Policy and Resources Committee Report 1.1, 2.1
  • 24 June 2026: Council approved creation of £2m contingency from 2025-26 underspend, with ELT delegated authority to authorise drawdowns Report 4.5
  • 17 July 2026: Update report dated by the Section 95 Officer Report P24
  • 20 August 2026: Policy and Resources Committee considered the update and noted its contents Report P5
  • 2026-27: Current financial year for which estimated pressures of up to £0.330m are identified, excluding construction, borrowing and pay award impacts Report 1.3, 4.1
  • 2027-28: Earliest year when construction cost impact of between £1.3m and £3.5m is anticipated Report 1.3, 4.3

Plain English for the jargon

  • ELT: Executive Leadership Team, which has delegated authority to authorise contingency expenditure in consultation with the Leader, Deputy Leaders and relevant Policy Lead
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

Decision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section 95 Officer dated 17 July 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy and Resources Committee

Executive summary

1.1A report was presented to Policy and Resources Committee on 21 May 2026 highlighting to Members the potential impact of the conflict in Iran and the broader Arabian Gulf region. This report provides an update on the estimated financial impact of the conflict and gives consideration to the Council’s revenue and capital budgets during 2026-27.

1.2Quantification of the financial estimations contained within this report has been challenging and therefore caution should be applied when placing any reliance on them.

1.3The potential financial pressure currently identified for 2026-27 is estimated to be up to £0.330m excluding construction costs and borrowing costs which are unlikely to cause an impact until 2027-28. It also does not take into consideration any potential impact on pay award negotiations. It is expected that further costs will transpire as the year progresses, however at this early stage in the financial year those noted within this report outline the current estimated impact for 2026- 27.

1.4It is recommended that Policy and Resources Committee consider the contents of the report. ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE

FINANCIAL SERVICES 20 AUGUST 2026

POTENTIAL IMPACT OF IRAN CONFLICT - UPDATE

2. INTRODUCTION

2.1A report was presented to Policy and Resources Committee on 21 May 2026 highlighting to Members the potential impact of the conflict in Iran and the broader Arabian Gulf region. This report provides an update on the estimated financial impact of the conflict.

2.2Financial Services have reviewed the potential financial impact, however quantifying the estimations has been challenging and therefore caution should be applied when placing any reliance on them.

Recommendations

3.1It is recommended that Policy and Resources Committee consider the contents of the report.

4. DETAIL

4.1This report considers the estimated financial impact of the conflict in Iran for the current year 2026-27.

4.2Assessing both the scale of cost increases and how long they are likely to last has been challenging, however estimates of the costs currently emerging in 2026-27 are noted within the table below. It is expected that further costs will transpire as the year progresses, however at this early stage in the financial year those noted below outline the current estimated impact for 2026-27.

Estimated Financial Description Impact 2026-27 £000 Business mileage costs – HMRC have increased the mileage 120 rate from 45p to 55p for the first 10,000 miles. Estimate based on 2025/26 costs and likely to be recurring in nature. Utilities/Vehicle Fuel – costs fluctuate on a regular basis Up to 90 regardless so difficult to quantify what is as a result of the conflict. Based on CPI forecasts. Food costs - costs fluctuate on a regular basis regardless so Up to 120 difficult to quantify what is as a result of the conflict. Based on CPI forecasts. 2026-27 Total Up to 330

4.3In addition to the above, there are further areas of uncertainty including:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
POTENTIAL IMPACT OF IRAN CONFLICT: UPDATEAgenda 205 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 18 attended
KM
Katie McKenzieSecretary, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairMember, present
MC
Councillor Math Campbell-SturgessMember, apologies
KG
Councillor Kieron GreenMember, present
AH
Councillor Amanda HampseyMember, present
AK
Councillor Andrew KainMember, absent
RK
Councillor Reeni Kennedy-BoyleMember, present
JL
Councillor Jim LynchChair, present
LM
Councillor Luna MartinMember, present

All 18 on the meeting page

On this subject at Argyll and Bute

Search all
  1. POTENTIAL IMPACT OF IRAN CONFLICT - UPDATEThis decision
  2. Potential impact of iran conflictNoted
  3. Potential impact of the implementation of frs 25 & 26 and fred 33Noted
  4. Impact of land allowance scheme (scotland) regulations 2005 and potential strategic waste fund support for long term waste management projectsApproved

More from Argyll and Bute Policy and Resources Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... Agreed Open
20 Aug 2026 Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... Noted Open
20 Aug 2026 Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... Agreed Open
20 Aug 2026 Scottish languages act 2025 - areas of linguistic significanceDecision The Policy and Resources Committee – 1. noted the progress being made to ensure that the Council meets its s... Noted Open
20 Aug 2026 Community regeneration partnership fund - programme updateDecision The Policy and Resources Committee – 1. noted progress with delivery of the Community Regeneration Partnersh... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies