CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Planning, Protective Services and Licensing Committee, Wednesday 17 March 2021 at 11.00am

MR PETER DAALMAN: ERECTION OF RETAINING WALL TO INCLUDE RECESS FOR BIN AND SOLID FUEL STORAGE AREAS AND INSTALLATION OF FLUSH KERBS: 38 ELLENABEICH, ISLE OF SEIL (REF: 20/01847/PP)

Agreed Planning 2 papers

Planning, Protective Services and Licensing Committee agreed this item on Wednesday 17 March 2021. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. The development shall be implemented in accordance with the details specified on the application form dated 30/09/20 ; supporting information and, the approved drawings listed in the table below unless the prior written approval of the Planning Authority is obtained for an amendment to the approved details under Section 64 of the Town and Country Planning (Scotland) Act 1997. Plan Title. Plan Ref. No. Version Date Received Location Plan 2023 01 09/11/20 Site Plan As Existing 2023 02 09/11/20 Site Plan As Proposed 2023 03 A External Wall As Proposed 2023 04 A Retaining Wall As Existing 2023 05 09/11/20 Reason: For the purpose of clarity, to ensure that the development is implemented in accordance with the approved details. 2. Before any works commence on site, full details of the materials to be used for the slate wall copings and the flush kerbing shall be submitted to and approved in writing by the planning authority. The required materials shall include the submission of samples where such submission is considered necessary by the planning authority. Thereafter, the development shall be implemented using the materials as agreed. Reason: In order to ensure that the materials to be used in the development are appropriate to their setting within the conservation area and in respect of any impact upon the setting of the adjacent listed building. (Reference: Report by Head of Development and Economic Growth dated 2 March 2021, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Planning, Protective Services and Licensing Committee
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
2001847 planReport 617 KB Download
PDF
MR PETER DAALMAN: ERECTION OF RETAINING WALL TO INCLUDE RECESS FOR BIN AND SOLID FUEL STORAGE AREAS AND INSTALLATION OF FLUSH KERBS: 38 ELLENABEICH, ISLE OF SEIL (REF: 20/01847/PP)Report 489 KB Download

At this meeting

Whole meeting

Who was there

11 of 15 attended
GB
Councillor Gordon BlairMember, present
RC
Councillor Rory ColvilleVice-Chair, present
MD
Councillor Mary-Jean DevonMember, present
LD
Councillor Lorna DouglasMember, apologies
AF
Councillor Audrey ForrestMember, present
GF
Councillor George FreemanMember, apologies
KG
Councillor Kieron GreenMember, present
GH
Councillor Graham HardieMember, present
DK
Councillor David KinniburghChair, present
DM
Councillor Donald MacMillan BEMMember, present
RM
Councillor Roderick McCuishMember, apologies
JM
Councillor Jean MoffatMember, apologies

All 15 on the meeting page

More from Argyll and Bute Planning, Protective Services and Licensing Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Beaufort wind limited: erection of 7 turbines (up to 149.9m to tip) and ancillary development and decommissioning of existing beinn ghlas wind farm: existing beinn ghlas wind farm, taynuilt (ref: 25/01240/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. PP - A... Agreed Open
15 Sep 2026 Mr tony coogan: alterations to guesthouse to facilitate lawful use of existing roof space as ancillary guest house owner's accommodation: greencourt, benvoullin road, oban (26/00434/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Mrs faulkes: proposed alterations and erection of extension: 30 the green, craobh haven (ref: 26/01009/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Decision The Committee agreed that the Scottish Government’s Marine Directorate should be notified that Argyll and Bu... Agreed Open
15 Sep 2026 Development management performance update - fq1 2026/27Decision The Committee reviewed and agreed the content of the report. (Reference: Report by Executive Director with r... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies