Argyll and Bute HSCP Integration Joint Board (IJB) approved this item on Wednesday 31 March 2021. Below is the council's own wording, with the papers it was decided on.
Decision The Integration Joint Board – 1. Approved the Programme Management Approach to progressing the Care Home and Housing Transformation work. 2. Approved the work stream approach and the short and longer term priorities set out at 3.3 of the submitted report. 3. Recognised the importance of engagement as outlined at 3.6 of the submitted report. 4. Approved the options appraisal scoring framework set out at 3.10 to 3.12 of the submitted report. 5. Agreed to delegate authority to the Finance & Policy Committee to approve the outcome of the options appraisal. 6. Agreed the approach to the financial implications set out at 3.13 of the submitted report. 7. Noted the progress of the Care Home and Housing Programme Board detailed within the report. (Reference: Report by Head of Older Adults and Community Hospitals dated 31 March 2021, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Argyll and Bute HSCP Integration Joint Board (IJB)
Executive summary
1.1This report summarises the progress to date of the care home and housing programme board. It provides context in the work previously undertaken and gives details of the approach going forward.
2. INTRODUCTION
2.1Care homes and housing is a key transformation area which is an integral part of the HSCP Strategic Plan. Care homes for older adults plays a central part of the range of services for older people. These are registered services with the Care Inspectorate but ultimately an older person’s home.
2.2The care homes and housing programme and its projects all link clearly with the HSCP strategic priorities and aims to establish future need and provide a multi-agency platform for planning how our future care homes and specialist housing requirements are met.
2.3Significant progress towards this priority was carried out in 2018-19 through the Care Homes & Housing Steering Group.
1 However, it was paused due to resourcing difficulties and the planned re-start in January 2020 was put on hold due to the Covid-19 response.
2.4The Senior Leadership Team made a decision to re-commence this work by the establishment of a new Care Home and Housing Programme Board. The focus of this board is to build on the previous work, to identify short and longer term options which includes local authority care homes in Oban and Dunoon. The new terms of reference of the board are detailed in Appendix One.
3. DETAIL OF REPORT
3.1A scoping meeting was held on 12th February. This was well represented by a number of key stakeholders including the Chief Officer, Head of Service Older Adults, Scottish Care, Union Representatives, Human Resources, Commercial Services and Argyll and Bute Senior Housing Managers.
3.2Care Homes and Housing Programme Board
It was agreed to progress with a new programme board approach. Where there is major change there will be complexity, risk, many interdependencies to manage and conflicting priorities to resolve. These challenges are managed through the board, its governance, themes and agreed principles. In addition, it will ensure that:
Relevant projects (whether short term or longer term) are coordinated, and aligned with the HSCP transformational priorities. There is a clear structure in its framework. Membership allows for a multi-agency approach. Any failure is mitigated by a risk management approach.
3.3Two definite work streams were identified; one as a short term and the other as longer term:
1. Work stream 1 : Operational Priority - Short Term (1-2 years) Deliver the operational priority to deliver care in a safe and comfortable environment. 2. Work stream 2 : Strategic Development - Longer Term (3-5 years) Deliver the strategic priority to scope and deliver a co-produced model of future care for older people with communities. The previous report along with up to date modelling and the impact of Covid-19 will be re considered.
3.4Work stream 1: Operational Priority 1. 1. Eadar Glinn - Oban Eadar Glinn will be the first care home to explore alternative opportunities for care home accommodation for their residents in 2021- 22.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Argyll and Bute HSCP Integration Joint Board (IJB) at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.