CARE HOMES STRATEGIC DEVELOPMENT - STAKEHOLDER ENGAGEMENT

Noted Committee 1 paper

AI summaryArgyll and Bute councillors noted the HSCP care homes strategic review is progressing, with public engagement to start in July 2026. Engagement cost is estimated at £63k plus up to £28k.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThree points on review, engagement, governance
Money£63k plus up to £28kCost of public engagement process
What happens nextEngagement July to September 2026Reporting due in October 2026
Who it affectsOlder adults, residents, island communitiesBute, Islay, Tiree, Mull mentioned

What was decided

The committee noted that the HSCP is progressing its Care Homes Strategic Review in partnership with HUB North. Report 1.4, 3.1

The committee noted that public engagement is expected to commence in July 2026. Report 1.4, 3.1

The committee noted that governance is complex and the strategic review requires to be progressed with support from Argyll and Bute Council. Report 1.4, 3.1

Why

The strategic work has been ongoing for some time. Stages 1 and 2 are complete, the Strategic Assessment found dilapidation across the care home estate and a mismatch between demand and capacity, and demand has been modelled through to the 2040's. Report 1.1, 4.1, 4.2, P16, P18

An externally facilitated public engagement was agreed as the most appropriate way forward, to be consistent with Planning with People and advice from Health Improvement Scotland, and to engage the independent sector. Report 1.2, P22, P23, P24

Governance is complex because the HSCP is responsible for service planning while Argyll and Bute Council owns the estate, approves capital investment and borrowing, and decides on asset disposal and property closure. Report 1.3, P28, P34, P35, P36

What happens next

Public engagement will run from July to September 2026, with reporting in October 2026, including in person events on Islay, Mull and Bute. Report 1.3, P25

Once engagement outcomes are known, they will be combined with Stage 1 and Stage 2 work to develop firm proposals. Further formal consultation may be required. Report P39

A full risk register and a full Equality Impact Assessment will need to be developed and maintained as the programme progresses. Report 6.6, 6.9, P51

The money

  • £63k Estimated cost of the public engagement process Report P26
  • up to a further £28k Additional cost if external contractors attend all in person events Report P26

Options considered

  • Chosen: Externally facilitated public engagement process. Agreed as the most appropriate way to take the project forward and to ensure objectivity, with HUB commissioned to facilitate Report 1.2, P22

Implications

  • Financial: The programme has significant revenue and capital resource implications, and some public sector capital investment is likely to be required over and above normal Council allocations to support the care home estate. Report P13
  • Risk: There are substantial risks, including failure of facilities if investment is not made, modelling overstating or understating future demand, independent sector capacity reductions, optimistic cost modelling, staffing shortages, funding unavailability, and reputational damage from engagement. Report 6.6, P51, P52
  • Other: Significant implications for Health and Social Care services, with further implications for Housing and Economic Development policy areas. Report P45, 6.1
  • Equalities: A full Equality Impact Assessment will be required as the programme progresses, and residential care services primarily serve older people. Report 6.9
  • Staffing: None at present, but the programme may result in significant service change in the medium term which is expected to have HR implications. Report 6.4
  • Climate: Reducing the carbon reduction footprint of existing and any potential new facilities is one of the objectives of the programme. Report 6.7
  • Legal: None at present, with the report setting out the governance arrangements between the Council, the HSCP and the Integration Joint Board. Report 6.3, P28, P29

Who and where

  • Older adults needing residential and wider care in Argyll and Bute Report 1.1, 4.1
  • Current and future residents of HSCP operated care homes on Bute, Islay, Tiree and the enhanced care facility on Mull
  • Independent sector care home providers and housing sector providers Report 4.1, P23
  • Argyll and Bute Council, the Health and Social Care Partnership, and the Integration Joint Board as decision makers Report 1.3, P28, P29, P30, P36
  • Communities that may make strong representations requiring substantial capital investment Report P37

Timeline

  • July 2026: Public engagement expected to commence Report 1.4, 3.1
  • July to September 2026: Engagement period, including in person events on Islay, Mull and Bute Report P25
  • October 2026: Engagement reporting due Report 1.3, P25, P39
  • 2040's: Demand for care home places modelled through to this period in the Stage 1 Report Report P18

Plain English for the jargon

  • HSCP: Health and Social Care Partnership, the body responsible for service planning, quality and commissioning of social care services in the area
  • HUB North: External organisation commissioned to facilitate public engagement and support the strategic development work, also referred to as the HUB team
  • IJB: Integration Joint Board, the body that sets the strategic plan, commissioning strategy and Older Adult Strategy, but cannot approve capital expenditure or commit Council capital funding
  • HIS: Health Improvement Scotland, which is supporting the HSCP in major engagement activities
  • SA: Strategic Assessment, a review of the physical condition of the care home estate and engagement with staff, service users and stakeholders
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

Decision The Policy and Resources Committee noted – 1. that the HSCP was progressing its Care Homes Strategic Review in partnership with HUB North; 2. that Public Engagement was expected to commence in July 2026; and 3. that governance was complex, and the strategic review required to be progressed with support from Argyll and Bute Council. (Reference: Report by Chief Officer, Health and Social Care Partnership dated 28 April 2026, submitted) *
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy and Resources Committee

Executive summary

1.1The Strategic Development project in respect of Care Homes has been on- going for some time. Stages 1 and 2 have been completed and reported within the Health and Social Care Partnership’s (HSCP) governance structure, and to the Council Executive Leadership Team. The purpose of this report is to provide a summary of the programme, outline the next stage, and summarise the governance framework. The main drivers for longer term planning include demographic change and the current condition and capacity of care homes.

1.2It has been agreed that an externally facilitated public engagement process was the most appropriate way to take forward the project. The objectives are to engage with a broad range of stakeholders in respect of the population and capacity modelling data and the long list of options that have been identified. The process will seek to gather views and further options from stakeholders and will engage with the independent sector. This engagement is consistent with Planning with People and with advice from Health Improvement Scotland (HIS) in respect of the development of service change options. It is not a formal consultation in respect of any specific service.

1.3The timeline for the proposed engagement is July to September 2026, with reporting due in October 2026. It is intended that the HSCP, in partnership with HUB North, will also continue to progress development in respect of what the future service model and infrastructure might look like in respect of a potential investment in a new care facility. The governance arrangements are complex, as Argyll and Bute Council, and not the HSCP, has responsibility for capital investment. The HSCP has responsibility for service planning and operation of services and therefore a joint approach is required. This paper seeks to ensure that elected members are aware of the programme, the intended commencement of the stakeholder engagement, and of the governance arrangements which apply to residential care home provision.

1.4It is recommended that the Policy and Resources Committee consider and note: • that the HSCP is progressing its Care Homes Strategic Review in partnership with HUB North. • that Public Engagement is expected to commence in July 2026. • that governance is complex, and the strategic review requires to be progressed with support from Argyll and Bute Council. ARGYLL AND BUTE COUNCIL Policy and Resources Committee Health and Social Care Partnership 21 May 2026

Care Homes Strategic Development – Stakeholder Engagement

2.0INTRODUCTION

2.1The purpose of this report is to summarise the strategic development work being undertaken by the HSCP, supported by Hub North, and Argyll and Bute Council. The report also summarises the complex governance arrangements to ensure that these are understood prior to the commencement of the next stage of the work which is the Stakeholder Engagement process.

Recommendations

3.1It is recommended that the Policy and Resources Committee consider and note:

• that the HSCP is progressing its Care Homes Strategic Review in partnership with HUB North. • that Public Engagement is expected to commence in July 2026. • that governance is complex, and the strategic review requires to be progressed with support from Argyll and Bute Council.

4.0DETAIL

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CARE HOMES STRATEGIC DEVELOPMENT: STAKEHOLDER ENGAGEMENTReport 151 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 19 attended
KM
Katie McKenzieSecretary, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairMember, present
MC
Councillor Math Campbell-SturgessMember, present
AF
Councillor Audrey ForrestMember, present
KG
Councillor Kieron GreenMember, present
AH
Councillor Amanda HampseyMember, present
RK
Councillor Reeni Kennedy-BoyleMember, present
JL
Councillor Jim LynchChair, present
LM
Councillor Luna MartinMember, present

All 19 on the meeting page

On this subject at Argyll and Bute

Search all
  1. CARE HOMES STRATEGIC DEVELOPMENT - STAKEHOLDER ENGAGEMENTThis decision
  2. Care inspectorate grades: care homes for older people in argyll and buteNoted
  3. Church of scotland care homesNoted
  4. The future for care homes in scotlandNoted

More from Argyll and Bute Policy and Resources Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... Agreed Open
20 Aug 2026 Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... Noted Open
20 Aug 2026 Potential impact of iran conflict - updateDecision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section ... Noted Open
20 Aug 2026 Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... Agreed Open
20 Aug 2026 Scottish languages act 2025 - areas of linguistic significanceDecision The Policy and Resources Committee – 1. noted the progress being made to ensure that the Council meets its s... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies