CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Policy and Resources Committee, Thursday 12 August 2021 at 10.30am

FINANCIAL REPORTS MONITORING PACK - 30 JUNE 2021

Noted Committee 1 paper

Policy and Resources Committee noted this item on Thursday 12 August 2021. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

Decision The Policy and Resources Committee – 1. Noted the revenue budget monitoring report as at 30 June 2021 and noted the comments in respect of the Health and Social Care Partnership. 2. Noted the progress with the policy savings options as at 30 June 2021. 3. Noted the financial risks for 2021-22. 4. Noted the capital plan monitoring report as at 30 June 2021. 5. Noted the treasury monitoring report as at 30 June 2021. 6. Recommended to Council the approval of the following amendments to the Annual Treasury Management Strategy: i. Increase the investment limit for term deposits with UK banks from £15m to £20m. ii. Increase the investment limit for term deposits with all other banks from £10m to £15m. 7. Noted the reserves and balances report as at 30 June 2021. 8. Recommended to Council that the revenue virements over £0.200m during April to June 2021 are approved. (Reference: Report by Section 95 Officer dated 9 July 2021, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy and Resources Committee

ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITEE

FINANCIAL SERVICES 12 AUGUST 2021

FINANCIAL REPORTS MONITORING PACK – 30 JUNE 2021

1. INTRODUCTION

1.1This report provides a summary of the financial monitoring reports as at the end of June 2021. There are six detailed reports, setting out the position as at 30 June 2021, which are summarised in this Executive Summary:

 Revenue Budget Monitoring Report  Monitoring of Policy Savings Options  Monitoring of Financial Risks  Capital Plan Monitoring Report  Treasury Monitoring Report  Reserves and Balances

2. DETAIL

2.1Revenue Budget Monitoring Report

2.1.1 This report provides a summary of the current revenue budget monitoring position to ensure net expenditure is contained within budget. It provides corporate and departmental information with comparisons on a forecast outturn and a year to date basis.

2.1.2 There is a forecast overspend of £1.369m as at the end of June 2021. This projection results from Social Work and is due to a combination of a high demand for services and some forecast slippage on the delivery of agreed savings.

2.1.3 There is a year to date underspend of £0.404m. More focus is on the forecast outturn position, hence why sometimes the year to date position is not updated. The year to date variances mainly relate to the timing of income and expenditure, recharging of costs to capital and the impact of COVID-19.

2.1.4 With regard to the ongoing financial impact of COVID-19, a report will be presented to the Policy and Resources Committee in October which will provide an update on the latest projections and the extent to which the monies put aside when setting the 2021/22 budget have been/are expected to be utilised.

Health and Social Care Partnership (HSCP) – Financial Update 2.1.5 The forecast outturn position at the end of June is an estimated overspend of £1.569m for 2021-22 (£1.369m overspend for Social Work and £0.200m overspend Health). The new Chief Financial Officer of the IJB commences in post on 9 August 2021 and we will schedule a meeting with him to discuss the need for a recovery plan to be developed and presented to the IJB Board in September 2021.

2.2Monitoring of Policy Savings Options

2.2.1 The purpose of this report is to provide Members with an update on the implementation and delivery of the Service Package Policy Options agreed by Council in February 2021 or agreed by Council in previous years which have either not been delivered yet or have increases in value in 2021-22 onwards.

2.2.2 One saving in relation to Procurement has been removed as it is no longer deemed deliverable. This saving was dependent on the number and type of contracts being tendered for which have the potential to achieve revenue savings through the procurement process. The target was agreed in 2019- 20 by the Council however it has proved harder to achieve than was first anticipated and this is likely to be exacerbated by the impact of COVID-19 with tenders not expected to come in below budget.

A £0.250m cost pressure has been added to the budget outlook to reflect this.

2.2.3 The savings options are reported as being delivered, on track to be delivered, still to be implemented, being developed, potential shortfall or delayed.

2.2.4 The table below outlines the progress as at 30 June 2021 for the new policy savings options agreed in February 2021.

Category No of 2020-21 2021-22 2022-23 Options £000 £000 £000 Delivered 10 180.4 194.4 202.4 On Track to be Delivered 7 214.0 324.0 324.0 Still to be Implemented 2 87.1 294.7 414.3 Being Developed 1 76.0 76.0 76.0 Potential Shortfall 0 0.0 0.0 0.0 Delayed 0 0.0 0.0 0.0 Total 20 557.5 889.1 1,016.7 2.2.5 For savings options agreed in February 2018, 2019 and 2020, we are reporting on an exception basis. Those that are already delivered are not included in the analysis below.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FINANCIAL REPORTS MONITORING PACK: 30 JUNE 2021Report 7.2 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 18 attended
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
RC
Councillor Rory ColvilleMember, present
RC
Councillor Robin CurrieChair, present
MD
Councillor Mary-Jean DevonMember, present
BG
Councillor Bobby GoodMember, apologies
KG
Councillor Kieron GreenMember, present
JF
Councillor Jim FindlayMember, present
AF
Councillor Audrey ForrestMember, present
JL
Councillor Jim LynchMember, present
DK
Councillor David KinniburghMember, present
YM
Councillor Yvonne McNeillyMember, present

All 18 on the meeting page

On this subject at Argyll and Bute

Search all
  1. FINANCIAL REPORTS MONITORING PACK - 30 JUNE 2021This decision
  2. Financial reports monitoring pack - 31 december 2024Agreed
  3. Financial reports monitoring pack - 31 october 2024Agreed
  4. Financial reports monitoring pack - 31 august 2024Noted
  5. Financial reports monitoring pack - 30 june 2024Noted
  6. Financial reports monitoring pack - 31 december 2023Noted

More from Argyll and Bute Policy and Resources Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... Agreed Open
20 Aug 2026 Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... Noted Open
20 Aug 2026 Potential impact of iran conflict - updateDecision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section ... Noted Open
20 Aug 2026 Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... Agreed Open
20 Aug 2026 Scottish languages act 2025 - areas of linguistic significanceDecision The Policy and Resources Committee – 1. noted the progress being made to ensure that the Council meets its s... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies