Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report and information provided. (Reference: Report by Regional Communities Manager - West, Scottish Water, dated February 2022, submitted)
Mid Argyll, Kintyre & the Islands Area Committee noted this item on Wednesday 2 March 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report and information provided. (Reference: Report by Regional Communities Manager - West, Scottish Water, dated February 2022, submitted)
Scottish Water Update February 2022 Scottish Water has had a busy period of investment in the Mid Argyll, Kintyre, and the Islands area, with many projects completed and others in the pipeline.
I have presented some highlights below, looking back over the past year, and looking forward, with upcoming projects at various stages of planning and delivery. This is by no means an exhaustive list.
Ongoing Investment Low & High Askomil
An £800K mains rehabilitation project to install 1.5 miles of new pipes commenced in August. The works, being delivered by local firm McFadyens, were affected by a Covid 19 outbreak which caused a short delay. It is due for completion by the end of February. This project was delivered following the successful delivery of a £950K upgrade to the water network in Machrihanish.
Islay
A number of projects were completed, with further works ongoing, as part of a multi-million water and waste water investment on Islay.
Bowmore
A £3m project to upgrade the water network in the town commenced in October 2021. The work is expected to last 18 months.
As part of our community engagement, we trialled our virtual platform to improve the way we communicate with customers during lockdown. This has proved a hugely successful way of communicating with our more remote communities, while reducing our carbon footprint. You can access the platform here and unique registration is with an email address. We were also pleased to take part in a radio podcast for This is Islay to discuss the project. You can access the podcast at www.thisisislay.co.uk . Torra TTU
This £2.5m investment is now onstream after a marathon journey across land and sea and months of on-site testing. The Transportable Treatment Unit – TTU – is now connected to the network supplying nearly 2000 customers in the Bowmore and Port Ellen areas.
The new unit is supplying an additional 70,000 litres of clear, fresh drinking water a day.
This work is just part of our ongoing programme of works for Islay to provide capacity for future housing developments but also resilience and improvements to the existing network.
More information can be found here
SW Public General The following projects on Islay were also completed in 2021, delivered by local contractor McFadyens: School Street, Port Ellen; Emerivale & Shore Street, Port Ellen; Daal Terrace, Port Charlotte.
Isle of Luing
A £1.2m investment to upgrade the water network on the Isle of Luing, started in October 2021.
We are replacing 2.8km of water main in the village of Cullipool, to improve the resilience of water supplies, following a history of bursts in this location. Our team are staying on the island, and this has enabled good communications with local residents on the ground, around required interruptions to water supply, to enable the works. More information can be found here
Planned Investment Tayvallich
An approx. £850K investment to upgrade the water network in Tayvallich was due to commence last year.
However, it has been discovered that the mains is in a challenging position which would require a full road closure. Given the restrictions this would put on the local community for a period of around six months, we are now in active discussions with roads authority to establish the best way to proceed to allow us to deliver the work, while minimising the impact on residents.
We have recently learned lessons, working with a community on a project in a similar location of Innellan.
Ballygrant, Islay
We are at the early stages of planning for a project to replace a stretch of water main in the woods adjacent to Port Askaig. It is expected to be carried out later this year. No further details are available at present. Bengullion Road WWPS, Campbeltown
We are in the early stages of planning for the refurbishment of the existing pumping station on Bengullion Road. There are no timescales for this at present.
Campbeltown WWTW
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Scottish Water Annual UpdateReport | 405 KB | DownloadRead as text |
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... | Noted | Open |
| 2 Sep 2026 | Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... | Agreed | Open |
| 2 Sep 2026 | Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... | Noted | Open |
| 2 Sep 2026 | Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... | Noted | Open |
| 2 Sep 2026 | Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.