OBAN HARBOUR UPDATE

Agreed Committee 1 paper

Oban Lorn & The Isles Area Committee agreed this item on Wednesday 9 March 2022. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

Decision The Oban, Lorn and the Isles Area Committee agreed to note the update presented to, and the decision of, the Council’s Harbour Board on 3 March 2022. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services, dated February 2022, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Oban Lorn & The Isles Area Committee

Recommendation

The Oban, Lorn and the Isles Area Committee are asked to note the update presented to, and the decision of, the Council’s Harbour Board on 3 rd March 2022, and to consider the detail provided.

Argyll and Bute Harbour Board - 3 March 2022 ARGYLL AND BUTE COUNCIL OBAN, LORN AND THE ISLES AREA COMMITTEE

ROADS AND INFRASTRUCTURE 9 MARCH 2022 SERVICES

OBAN BAY UPDATE

Executive summary

2.1This report provides an update following the Special Harbour Board Meeting, which took place in December 2021, on progress since the Special Meeting and the next steps which officers require to undertake.

Recommendations

3.1The Oban, Lorn and the Isles Area Committee are asked to note the update presented to, and the decision of, the Council’s Harbour Board on 3rd March 2022, and to consider the detail provided.

Argyll and Bute Harbour Board - 3 March 2022

4.0DETAIL

SPECIAL HARBOUR BOARD, DECEMBER 2021

4.1The Harbour Board made the following decision at its Special Meeting in December 2021:

The Argyll and Bute Harbour Board:

1. Thanked Caledonian Economics for their work on the Options Appraisal;

2. Agreed that the Council would not at this time proceed with a transfer of assets on the basis that there were too many uncertainties around the proposal;

3. Noted that Options 4 or 5 (Argyll and Bute Council or Caledonian Maritime Assets Limited (CMAL) becoming the Harbour Authority for the unmanaged section of Oban Bay) provides a quicker route to addressing the current safety concerns and are therefore the best options available at this time; 4. Agreed that either Options 4 or 5 should move forward and request that Officers engage with CMAL, through the OBMG, on the basis that the Council’s preference would be option 5 and that the Council was prepared to be the Harbour Authority for the unmanaged section of Oban Bay, to begin the process of application for a Harbour Revision Order covering the unmanaged section of Oban Bay and to expedite the process for such an order and to report back to members on that process;

5. Noted that there was no inherent reason why a Trust Port would not be a good future option; and

6. Agreed that once Options 4 or 5 were delivered there would be a period of bedding in to monitor the new arrangement and, after that time, there would be a further report to members on the potential for and exploration of the future development of a Trust Port.

PROGRESS SINCE DECEMBER

4.2Since the instruction from the Harbour Board to progress matters, Officers have held several sessions with key external bodies including CMAL, CalMac, Transport Scotland and Northern Lighthouse Board with additional support and assistance from the Council’s external Marine Designated Person.

4.3CMAL have agreement from their Board that Argyll and Bute Council will progress becoming Municipal Port Authority for the unmanaged areas of Oban Bay.

4.4These initial discussions were critical to determining how matters should progress. It was agreed with the various parties that the Council would begin the process of developing the process of applying for a Harbour Revision Order (HRO) covering the unmanaged sections of Oban Bay.

4.5A high level project timeline is in draft format and has been shared with the above noted key stakeholders for their input.

4.6At the Oban Bay Management Group meeting on 11 January the majority of the members of the group endorsed the proposal by the Council to become a Municipal Harbour Authority for the unmanaged waters within Oban Bay.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
OBAN HARBOUR UPDATEReport 222 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
MD
Councillor Mary-Jean DevonMember, present
KG
Councillor Kieron GreenMember, present
JL
Councillor Jim LynchMember, present
RM
Councillor Roderick McCuishMember, present
SJ
Councillor Sir Jamie McGrigorVice-Chair, present
JM
Councillor Julie McKenzieMember, present
AP
Adele Price-WilliamsSecretary, expected
ER
Councillor Elaine RobertsonChair, present
TC
Tiree CC SecretaryPublic, expected
AV
Councillor Andrew VennardMember, present

On this subject at Argyll and Bute

Search all
  1. OBAN HARBOUR UPDATEThis decision
  2. Oban harbour revision order - clarification for notingNoted
  3. Oban harbour revision order updateNoted
  4. Piers and harbours - oban harbour - costs and conservancyAgreed
  5. Oban harbour revision order - clarification for notingNoted
  6. Oban harbour updateNoted

More from Argyll and Bute Oban Lorn & The Isles Area Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... Agreed Open
9 Sep 2026 CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... Noted Open
9 Sep 2026 Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... Noted Open
9 Sep 2026 Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... Noted Open
9 Sep 2026 Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... Decided Open