CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Argyll and Bute Council, Thursday 19 May 2022 at 11.00am

UK LEVELLING UP FUND

Approved Committee 1 paper

Argyll and Bute Council approved this item on Thursday 19 May 2022. Below is the council's own wording, with the papers it was decided on.

Item24

Resolved

Decision The Council approved:- 1. The removal of the Active Travel Route for Helensburgh to Dumbarton Cyclepath due to the inability to meet Levelling Up Fund delivery deadlines, but note that officers continue to pursue this option via other funding opportunities. 2. The removal of the Active Travel Route from Kennacraig to Tarbert, due to the inability to meet Levelling Up Fund delivery deadlines, but note that officers continue to pursue this option via other funding opportunities. (Ref: Report by Executive Director with responsibility for Development and Infrastructure dated 10 May 2022, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Argyll and Bute Council

Executive summary

1.1The purpose of this report is to seek agreement from Elected Members to adjust the Levelling Up Fund Bids, following on from the update provided in February 2022, and the Members Seminar in March 2022.

1.2The Council has determined to submit 2 bids to the next round of the Levelling Up Fund, by the deadline of 6th July 2022. One bid will be for an area regeneration town centre project, maximum £20m and the second a Transport Bid, up to £50m.

Recommendations

It is recommended that the Council:

a) Approve the removal of the Active Travel Route for Helensburgh to Dumbarton Cyclepath due to the inability to meet Levelling Up Fund delivery deadlines, but note that officers continue to pursue this option via other funding opportunities; b) Approve the removal of the Active Travel Route from Kennacraig to Tarbert, due to the inability to meet Levelling Up Fund delivery deadlines, but note that officers continue to pursue this option via other funding opportunities ARGYLL AND BUTE COUNCIL COUNCIL

DEVELOPMENT AND INFRASTRUCTURE 19 MAY 2022

UK LEVELLING UP FUND – UPDATE

2.0INTRODUCTION

2.1This report provides an update on the progress of elements within the bids, which now require to be adjusted, to ensure that the bids are deliverable within the timescale set by the UK Government.

3.1It is recommended that the Council:

a) Approve the removal of the Active Travel Route for Helensburgh to Dumbarton Cyclepath due to the inability to meet Levelling Up Fund delivery deadlines, but note that officers continue to pursue this option via other funding opportunities; b) Approve the removal of the Active Travel Route from Kennacraig to Tarbert, due to the inability to meet Levelling Up Fund delivery deadlines, but note that officers continue to pursue this option via other funding opportunities

4.0DETAIL

4.1The Levelling Up Bids are currently being prepared, taking account of the UK Government Business Case guidance which was issued on the 13 th April 2022, which requires a considerable amount of supporting information. It is a highly competitive fund and there is no guarantee of a successful Bid or Bids.

4.2The Bids subject to feasibility consideration are included in two separate programmes:-  The Regeneration Bid up to £20m – Argyll and Bute Western Seaboard Marine Gateways Initiative – Rothesay and Dunoon.  The Transport Bid up to £50m – Connected Argyll and Bute – Whisky Islands; Helensburgh and Lorn Economic Growth Zone.

4.3The UK Government’s Guidance on bids is clear in regard to the timescale of projects and their deliverability. Projects included with the bid must be delivered by 2025 and those which are not anticipated to be delivered by that timeframe will negatively impact the overall application and this is deemed to lower the chances of a successful bid. Should the bid(s) be unsuccessful, the Council will not be able to deliver on any of the projects within the bid(s) and will require to look at alternative funding options. 4.4 There are two elements within the Connected Argyll Bid which officers have reviewed and are proposing should be removed. It should be noted that the Active Travel options will still be pursued outwith the Levelling Up Fund, via other sources of funding such as Sustrans.

4.4.1 Active Travel Route – Cardross – Helensburgh to Dumbarton Cyclepath

This is a long running project designed to provide an off-road walking and cycling path linking Helensburgh, Cardross and Dumbarton. Due to the long history of the project with the landowners between Helensburgh – Cardross, it is considered unlikely that it will be possible to secure a voluntary agreement with any of these landowners within the timescale of the Levelling Up Fund.

4.4.2 Active Travel Route – Tarbert to Kennacraig

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
UK LEVELLING UP FUNDReport 233 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

35 of 39 attended
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairMember, present
RC
Councillor Robin CurrieMember, present
AF
Councillor Audrey ForrestMember, present
GH
Councillor Graham HardieMember, present
KG
Councillor Kieron GreenMember, present
DK
Councillor Donald KellyMember, present
JL
Councillor Jim LynchMember, present
LM
Councillor Liz McCabeMember, present
JM
Councillor Julie McKenzieMember, apologies
YM
Councillor Yvonne McNeillyMember, present
GM
Councillor Gary MulvaneyMember, present

All 39 on the meeting page

On this subject at Argyll and Bute

Search all
  1. UK LEVELLING UP FUNDThis decision
  2. Levelling up fund - business case and bid submission updateAgreed
  3. Uk levelling up fund - progress updateNoted
  4. Uk levelling up fund - potential bids for fundingAgreed
  5. Uk levelling up fundNoted

More from Argyll and Bute Argyll and Bute Council

All decisions
MeetingDecisionOutcome
23 Sep 2026 Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro... Decided Open
23 Sep 2026 Nhs highland director of public health annual report 2025Decision The Council – 1. noted the Director of Public Health Annual Report 2025; and 2. supported the recommendation... Noted Open
23 Sep 2026 Leader's reportDecision The Council – 1. noted the contents of the submitted report; and 2. noted that any reports, briefings or cop... Noted Open
23 Sep 2026 Policy leads reportDecision The Council noted the content of the submitted report. (Reference: Report by Policy Lead Councillors dated 1... Noted Open
23 Sep 2026 Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex... Decided Open