Decision The Policy and Resources Committee – 1. Noted the content of the report and agreed that the Council claim the £125,000 funding to be used to develop two quality bids for a future call for applications. 2. Instructed Officers to bring back a report to Policy and Resources Committee once ideas for future bids have been developed to a stage that require political oversight. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 4 May 2021, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
2.1Members of the Policy and Resources Committee are asked to:
Note the content of this report and agree that the Council claim the £125,000 funding to be used to develop two quality bids for a future call for applications. Instruct Officers to bring back a report to Policy and Resources Committee once ideas for future bids have been developed to a stage that require political oversight.
3.0DETAIL
3.1The UK Levelling Up Fund (UKLUF) was announced on 3rd March 2021 as part of the UK Budget process, and the UK Government Levelling Up agenda. It was one of three new UK wide funds launched using the powers conferred to the UK Government through Sections 50 and 51 of the UK Internal Market Act 2020.
3.2It is a UK wide £4.8 billion capital fund which will support investment projects with up to £20 million of funding, although there is scope for investment in larger high value transport projects up to £50m. The fund will run for four years until 2024/2025 with potential for projects to be delivered until 2026.
3.3The closing date for the first round of funding is 18 June 2021 and will focus on three themes:
o smaller transport projects that make a genuine difference to local areas (or larger transport schemes such as road network investments); o town centre and high street regeneration; and o support for maintaining and expanding the UK’s world-leading portfolio of cultural and heritage assets.
3.4A sum of at least £800 million will be allocated to Scotland, Wales and Northern Ireland over the lifetime of the fund. For the first round of funding, at least 9% of total UK allocations will be set aside for Scotland. 1 Bids in Scotland can be submitted by any local authority, with the number of bids being dependent on the number of MPs in each area. An additional bid can be submitted for a transport bid.
3.5Bids and constituent projects should have the support of local stakeholders and partners. They should be consulted and bids should be developed with their inclusion.
3.6Bids should also have local MP support and decisions on successful bids will be made by the UK Government.
3.7There is a system of geographical prioritisation whereby the UK Government has devised an index that puts each local authority into one of three categories of need. The indicators used relate to:
o economic recovery and growth; o improved transport connectivity; and o regeneration.
3.8Argyll and Bute has been placed in the second priority category.
3.9During a meeting which took place between Argyll and Bute Council officers and civil servants involved in the UK Levelling Up Fund, it was confirmed that the criteria for the current call for applications could potentially change in subsequent rounds of funding. This is due to the current guidelines being kept under review, and to reflect operational feedback.
3.10The expectation from the UK Government is that projects applying for the first round of funding are advanced in their development and ‘shovel ready’. There are many authorities that will not be able to submit a bid in the first round as projects are not sufficiently developed, which is the case for Argyll and Bute.
3.11Each Local Authority in Scotland can claim £125,000 to develop quality bids. The £125,000 offered to develop quality bids will be claimed as soon as possible in order that we can progress being ready for a future round of funding. It is extremely important that we have a competent bid as we currently understand we only get one chance and if the bid is not robust enough then it may not be approved.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.