Decision The Argyll and Bute Harbour Board – 1. noted the update on the major programmes currently being addressed within Argyll and Bute Council’s Marine Asset Management Plan; 2. noted that £6.5 million worth of capital works are programmed for the financial year 2023/2024; and 3. noted that there was a potential spend of c.£110 million over the next 5 years, the majority of which would support the new CMAL and CFL / CalMac fleet renewal. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated February 2023, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
2.1Members of the Harbour Board are asked to:- 2.1.1 Consider the update on the major programmes currently being addressed within the Argyll and Bute Council’s Marine Asset Management Plan. 2.1.2 Note that £6.5 million worth of capital works are programmed for the financial year 2023 2024. 2.1.3 Note that there is a potential spend of c.£110 million over the next 5 years, the majority of which will support the new CMAL and CFL / CalMac fleet renewal.
Background
3.1Argyll and Bute Council continue to work closely with Transport Scotland, CMAL and CFL / CalMac to support Island and rural communities with marine links to the mainland, Central Belt resources and tourist revenue. 3.2 Lifeline ferry services are prioritised and the CMAL vessel replacement programme for Islay, Mull, Iona and Gigha all require infrastructure upgrades to meet the new vessel’s requirements. 3.3 Dunoon and Kilcreggan also have vessel replacement programmes underway which will see an improvement in the service reliability and resilience for commuters and visitors. 3.4 Shore power upgrades for overnight charging of vessels and the associated infrastructure requirements are being completed in Craignure for the Loch Frisa; and preparation work is also underway for Fionnphort and Gigha. 3.5 Crew and passenger’s safe boarding and access will be improved with our programmes at Fionnphort, Feolin, Dunoon and Kilcreggan, while studies will be completed for the Council’s own ferry services infrastructure.
4.0DETAIL
4.1The latest version of the Marine Asset Management Plan is attached as annex A and planned expenditure is summarised in table 1 in appendix 1. It includes the following significant works: 4.1.1 Iona & Fionnphort
CMAL’s Small Vessel Replacement Programme (SVRP) vessel no3 of 7, expected Q4 2026 / Q1 2027. A very successful meeting and presentation took place in January with the residents and users of Iona slipway. The EIA has now been received and we are very pleased that there are now no ‘Red Flag’ issues outstanding and that mitigation measures will be agreed to allow the project to continue. We will now proceed with the Marine licences, planning etc. and hope to have works commencing next year. Alongside this is the preparation is progressing with Fionnphort to ensure: Overnight berth
Safe access for crew
Sheltered berthing
Charging and supply facilities
Traffic survey to enhance the passenger road user interface at the terminal area. A public engagement visit, drop in day and presentation at Fionnphort will take place on 25th April this year and is expected to be well attended.
4.1.2 Craignure
New Ferry Terminal A well-attended meeting was held in Craignure in December where we agreed to proceed with Ground Investigations (GI) at the proposed location close by the existing pier. GI planning and tender compilation is now underway. Next phase works include completion of the Outline Business Case (OBC), detailed design and Financial Business Case.
Power supply for Loch Frisa Officers have worked closely with CMAL to provide the shore power supply for the Loch Frisa and we continue to progress the remaining enabling works. A new power substation is now online from 5th February providing improved capacity for both present demand and a ‘Phase 1’ for the new terminal requirements. 4.1.3 Port Askaig
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Argyll and bute harbour board workplanDecision The Argyll and Bute Harbour Board noted the content of the workplan. (Reference: Argyll and Bute Harbour Boa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.