PIERS & HARBOURS - MARINE ASSET MANAGEMENT PLAN

Noted Committee 1 paper

Argyll and Bute Harbour Board noted this item on Thursday 31 August 2023. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Decision The Argyll and Bute Harbour Board – 1. noted the update on the major programmes currently being addressed within the Argyll and Bute Council’s Marine Asset Management Plan; 2. noted that £9.2 million worth of capital works were underway for the financial year 2023/2024; and 3. noted that there was a potential spend of c.£110 million over the next 5 years, the majority of which would support the new CMAL & CFL ( Calmac Ferries Ltd) / CalMac fleet renewal. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated August 2023, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Argyll and Bute Harbour Board

Recommendations

2.1Members are asked to: 2.1.1 Consider the update on the major programmes currently being addressed within the Argyll and Bute Council’s Marine Asset Management Plan. 2.1.2 Note that £9.2 million worth of capital works are underway for the financial year 2023 2024. 2.1.3 Note that there is a potential spend of c.£110 million over the next 5 years, the majority of which will support the new CMAL & CFL / CalMac fleet renewal.

Background

3.1Argyll and Bute Council continue to work closely with Transport Scotland, CMAL and CFL / CalMac to support Island and rural communities with marine links to the mainland, Central Belt resources and tourist revenue. 3.2 Lifeline ferry services are prioritised and the CMAL vessel replacement programme for Islay, Mull, Iona and Gigha all require infrastructure upgrades to meet the new vessel’s requirements. 3.3 Shore power upgrades for overnight charging of vessels and the associated infrastructure requirements have been completed in Craignure for the Loch Frisa; and preparation work is now underway for Fionnphort and Gigha. 3.4 Crew and passenger’s safe boarding and access will be improved with our programmes at Fionnphort, Feolin, Dunoon and Kilcreggan, while studies will be completed for the Council’s own ferry services infrastructure. 4.0 DETAIL

4.1The Marine Asset Management Plan is an adaptable plan fed into by changing priorities and circumstances. It also relies on steady and predictable income from those ferry services utilising Argyll & Bute Council infrastructure. In recent years the COVID-19 pandemic and the UK’s withdrawal from the European Union has made some of the variables less predictable and our ability to engage contractors and consultants more difficult. Costs are best estimated and closely watched for best value. Rising prices and availability of resources are risks which will need to be monitored in each of the projects and forecasts adjusted accordingly.

4.2The latest version of the Marine Asset Management Plan is attached as annex A and planned expenditure is included in the updates. It includes the following significant works: 4.2.1 Iona & Fionnphort

CMAL’s Small Vessel Replacement Programme (SVRP) vessel no 3 of 7 is expected Q3 2027. Presently, we are uploading the planning application with a view to tender this year, contractor award and start of works in the spring / summer of 2024 and a completion summer 2025. The present forecast of 1 year construction may be subject to the contractor work scope and supply chains, particularly rock for armour. Expected expenditure this year is £500k. Alongside this is the preparation is progressing with Fionnphort to ensure:  Overnight berth

 Safe access for crew

 Sheltered berthing

 Charging and supply facilities  Traffic survey to enhance the passenger road user interface at the terminal area. An Environmental Impact Assessment (EIA) is in process including the socioeconomic assessment. Design colleagues have addressed all potential issues with CalMac Marine regarding swept paths and approaches. When Marine Scotland approve the EIA we will continue with the marine licences and other preparations with a view to tender in the summer of 2024 approx. Expected expenditure this year is £100K Public engagement visits with drop in day and presentation at Fionnphort and Iona took place in April this year and were well attended.

4.2.2 Craignure

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PIERS & HARBOURS: MARINE ASSET MANAGEMENT PLANReport 158 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
JA
Councillor John ArmourMember, present
GC
Councillor Garret CornerMember, present
AH
Councillor Amanda HampseyMember, present
AK
Councillor Andrew KainChair, present
JL
Councillor Jim LynchMember, present
IM
Councillor Ian MacQuireMember, apologies
RM
Councillor Ross MorelandVice-Chair, present
AV
Councillor Andrew VennardMember, present
HM
Hazel MacInnesSecretary, expected

On this subject at Argyll and Bute

Search all
  1. PIERS & HARBOURS - MARINE ASSET MANAGEMENT PLANThis decision
  2. Piers and Harbours - Marine Works UpdateNoted
  3. Piers and harbours marine asset management plan - works updateNoted
  4. Piers and harbours - performance reportingAgreed
  5. Piers and harbours marine asset management plan fees and charges 2027 / 2028Noted
  6. Piers and Harbours - Marine Works UpdateAgreed

More from Argyll and Bute Argyll and Bute Harbour Board

All decisions
MeetingDecisionOutcome
9 Oct 2026 Piers and harbours marine asset management plan - works updateDecision The Argyll and Bute Harbour Board noted the updates on capital works currently being progressed within the M... Noted Open
9 Oct 2026 Piers and harbours - performance reportingDecision The Argyll and Bute Harbour Board – 1. agreed the proposed approach and structure to annual performance repo... Agreed Open
9 Oct 2026 Carradale harbourDecision The Argyll and Bute Harbour Board noted the content of the report. (Reference: Report by Executive Director ... Noted Open
9 Oct 2026 Piers and harbours marine asset management plan fees and charges 2027 / 2028Decision The Argyll and Bute Harbour Board – 1. noted that officers were of the view that a review is required to con... Noted Open
9 Oct 2026 Argyll and bute harbour board workplanDecision The Argyll and Bute Harbour Board noted the content of the workplan. (Reference: Argyll and Bute Harbour Boa... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies