What the committee will consider, in order, with every paper attached to its item. Helensburgh Waterfront Development (Commercial area) - Update & shortlisting of offers is the main business; one item may be taken in private.
noted the commitments of those in attendance, the Chair agreed to vary the order of business. This Minute reflects the order in which discussions took place.
Report by Executive Director with responsibility for Roads and Infrastructure Services
Decision: Decision The Helensburgh and Lomond Area Committee: 1. noted the breakdown of engagement and consultation responses in each area with the majority of responses focussing on new/replacement equipment; and 2. agreed that officers make arrangements for a Business Day to discuss how the funding would be spent in Helensburgh and Lomond. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services, dated August 2023, submitted) Decision page
Update from Sergant Eddie McGunnigal , Police Scotland
Decision: Decision The Helensburgh and Lomond Area Committee considered and noted the information provided in the report. (Reference: Report by Sergeant Eddie McGunnigal , Police Scotland, submitted) Decision page
Report by Executive Director with responsibility for Customer Support Services
Decision: Decision The Helensburgh and Lomond Area Committee: 1. noted and considered the performance and supporting commentary as presented; 2. noted that upon receipt of the Quarterly Performance Report the Area Committee should contact either the Responsible Named Officer or Sonya Thomas with any queries; and 3. noted that work was ongoing and to respond to Sonya Thomas with requests or comments regarding the layout and format of the Performance Report and Scorecard. (Reference: Report by Executive... Decision page
Report by Executive Director with responsibility for Roads and Infrastructure Services
Decision: Decision The Helensburgh and Lomond Area Committee noted and considered the details as outlined in the report and the national policy drivers that would likely impact over the coming years . (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services, submitted) Decision page
Report by Executive Director with Responsibility for Commercial Services and Executive Director with responsibility for Economy & Rural Growth
Decision: Decision The Helensburgh and Lomond Area Committee: 1. noted that the reinstatement of the temporary skatepark facilities would be completed in autumn 2023 meeting the conditions of the leisure centre planning consent; 1. agreed that the waterfront site is not considered to be a suitable long term location for an expanded skatepark if a commercial development is selected as the preferred option for the site but for the avoidance of doubt the previously existing skatepark area extending to... Decision page
Report by Executive Director with Responsibility for Development and Economic Growth
Decision: Decision The Helensburgh and Lomond Area Committee: 1. noted that the Parks for People National Lottery Heritage Fund project was now complete and the project officer post had come to an end; 2. noted the End of Project Report and the Evaluation Report and all that had been achieved through the project; 3. noted the Council’s continuing legal obligations; and 4. noted the risk to the Council in relation to the final drawdown of £100,000 grant from National Lottery Heritage Fund . (Reference... Decision page
Report by Chief Executive
Decision: Decision The Helensburgh and Lomond Area Committee: 1. noted the positive contribution of the Supporting Communities Fund detailed in section 4 and the table within the report; and 2. noted that a total of £5,150 had been returned and that £1,800 would be included in the distribution of the Supporting Communities Fund for 2024/25 with the other funds included and redistributed in previous years. (Reference: Report by Chief Executive, dated 17 August 2023, submitted) Decision page
Decision: Decision The Helensburgh and Lomond Area Committee noted the contents of the workplan . (Reference: Helensburgh and Lomond Area Committee Workplan , dated 12 September 2023) Decision page
Decision: Decision The Helensburgh and Lomond Area Committee: 1. noted the outcomes of the public engagement exercise undertaken by Ryder Architecture contained at Appendix A and that this report would be made available to the public; 2. noted the varied interest in the site and the summary of the nine proposals received as outlined paragraph 3.4 and in Appendix B within the report; 3. noted the Property Development Working Group had met in August 2023 to score and assess the 9 proposals with 7 being... Decision page
of Section 50(A)(4) of the Local Government (Scotland) Act 1973, relating to the following item of business would require the exclusion of the press and public should Members wish to discuss the content of appendix 2 on the grounds that it would likely involve the disclosure of exempt information as defined in Paragraph 9 of Part 1 of Schedule 7A to the Local Government (Scotland) Act 1973.
Decision: Decision The Helensburgh and Lomond Area Committee: 1. welcomed the award of contract to Civic Engineers for £99,333.00 for the identification of a route linking Morrisons Supermarket/Hermitage Academy to Helensburgh Town Centre/Waterfront, and development of this to Concept Design stage; 2. noted the agreement of one (1) change requests from WSP at an additional cost of £5,285.53, taking the total cost of WSPs work to £265,913.00. This additional cost is covered by externally secured funding... Decision page
Item 13 is where most of this meeting's papers sit: 2 papers, about 7.6 MB.
This committee has dealt with the subject before.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 15 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 13 June 2023. 9 of its items lead into this meeting; 4 items are new. Point at any item to follow a thread. Procedural items are left out.
HERMITAGE ACADEMY ATTAINMENT REPORT, CEMETERY MAINTENANCE AND ROADS ACCESS FUND, HSCP ANNUAL PERFORMANCE REPORT 2022-2023, REQUEST FOR FINANCIAL ASSISTANCE FROM HELENSBURGH AND DISTRICT TWINNING ASSOCIATION and 1 more do not return this time.
See the 13 June meetingEvery Helensburgh & Lomond Area Committee meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Argyll and Bute, Helensburgh & Lomond Area Committee
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Helensburgh & Lomond Area Committee, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.