Helensburgh & Lomond Area Committee noted this item on Tuesday 12 September 2023. Below is the council's own wording, with the papers it was decided on.
Decision The Helensburgh and Lomond Area Committee: 1. welcomed the award of contract to Civic Engineers for £99,333.00 for the identification of a route linking Morrisons Supermarket/Hermitage Academy to Helensburgh Town Centre/Waterfront, and development of this to Concept Design stage; 2. noted the agreement of one (1) change requests from WSP at an additional cost of £5,285.53, taking the total cost of WSPs work to £265,913.00. This additional cost is covered by externally secured funding; 3. n oted the continued efforts by WSP and Officers to engage with landowners; 4. noted the high-level options for land acquisition laid out in this report; 5. approved Officers to contact colleagues in Highland Council to understand their experience of Land Reform (Scotland) Act 2003 Section 22 Orders; 6. approved Officers to engage with Scottish Government civil servants to identify the current requirements for a Compulsory Purchase Order. For clarity, this exploratory engagement would not include submission of any Compulsory Purchase Order, which would require approval of full Council and/or the appropriate Committee prior to submission; 7. gave consideration to the need to secure 30% match funding of the cost of construction from non-Transport Scotland sources; and 8. gave consideration to identifying how future maintenance of the path would be funded and undertaken, given the current situation where no path specific maintenance funding is provided to the Council; and 9. agreed that officers would bring forward a report to the next Area Committee outlining progress made and suggested next steps. (Reference: Report by Executive Director with responsibility for Development and Economic Growth, dated 28 August 2023, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report updates Members on the progress made since the previous report to the Helensburgh and Lomond Area Committee on 13 June 2023 in relation to the delivery of a dedicated, high quality walking and cycle path linking Helensburgh, Cardross and Dumbarton. The delivery of this path is a stated Council Priority.
1.2Officers have approved one (1) change request from WSP, resulting in a cost increase of £5,285.53 taking the total cost of WSPs work to £265,913.00. This additional cost can be accommodated within the secured external funding from Transport Scotland’s Places for Everyone (PFE) Programme, administered by Sustrans, and Strathclyde Partnership for Transport’s (SPT) Capital Programme.
1.3WSP continue to work on securing landowner agreement to enable environmental survey access and on continued engagement with other key stakeholders to secure support for the designs. Since the previous update, Officers have secured agreement to the surveys with one landowner, Officers and WSP have met on-site with one landowner and Officers have been in dialogue with the land agents for two other landowners.
1.4A contract has been awarded to Civic Engineers for £99,333.00 to identify the preferred route linking the existing cyclepath at Morrisons Supermarket / Hermitage Academy to Helensburgh Town Centre and the new section of segregated cycleway under construction at Helensburgh Waterfront, and to develop the preferred route to concept design stage. The outline programme for this work forecasts completion of design stages 0-2 (Feasibility, Route Alignment and Concept Design) by the end of 2023/24. This work is being funded via successful competitive applications to SPT’s Capital Programme and Transport Scotland’s PFE Programme.
1.5While funding has been secured to complete the design stages of the project; based on current funding models, to pay for construction of the route further competitive applications will be required to a range of programmes including the SPT Capital Programme and the Transport Scotland PFE Programme. The PFE Programme requires a minimum of 30% of total construction costs are secured from non-Transport Scotland derived sources. The future maintenance of the route also needs to be considered as currently no specific funding is received by the Council for maintenance of walking/cycling paths. RECOMMENDATIONS
1.6It is recommended that the Helensburgh and Lomond members:
1.6.1. Welcome the award of contract to Civic Engineers for £99,333.00 for the identification of a route linking Morrisons Supermarket/Hermitage Academy to Helensburgh Town Centre/Waterfront, and development of this to Concept Design stage.
1.6.2. Note the agreement of one (1) change requests from WSP at an additional cost of £5,285.53, taking the total cost of WSPs work to £265,913.00. This additional cost is covered by externally secured funding.
1.6.3. Note the continued efforts by WSP and Officers to engage with landowners.
1.6.4. Note the high-level options for land acquisition laid out in this report.
1.6.5. Approve Officers to contact colleagues in Highland Council to understand their experience of Land Reform (Scotland) Act 2003 Section 22 Orders.
1.6.6. Approve Officers to engage with Scottish Government civil servants to identify the current requirements for a Compulsory Purchase Order. For clarity, this exploratory engagement would not include submission of any Compulsory Purchase Order, which would require approval of full Council and/or the appropriate Committee prior to submission.
1.6.7. Give consideration to the need to secure 30% match funding of the cost of construction from non-Transport Scotland sources.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.