Decision The Council agreed – 1. to fund £706k from the Capital Contract Increases Fund to contribute to the landslip works at Claonaig; 2. to fund £28k from the Capital Contract Increases Fund to contribute towards the purchase of the Road Marking Machine; and 3. that delegated authority be granted for the use of the Capital Contract Increases Fund to the Council’s Chief Executive and two Executive Directors in consultation with the Leader, Depute Leaders and Leader of the largest Opposition Group. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated April 2024, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
a. agree to fund £706k from the Capital Contract Increases Fund to contribute towards the landslip works at Claonaig;
b.agree to fund £28k from the Capital Contract Increases Fund to contribute towards the purchase of the Road Marking machine; and
c. agree that delegated authority be granted for the use of the Capital Contract Increases Fund to the Council’s Chief Executive and two Executive Directors.
3.0DETAIL
3.1Claonaig Landslip
3.1.1 At the Council’s Environment, Development and Infrastructure Committee in June 2021, Members were advised that the Auchmeanach Farm Slip, Claonaig (also known as the B8001 Claonaig) had been added to the MAKI Roads Reconstruction Programme, this was a scheme brought forward from 2020/21 Programme due to the Covid pandemic.
3.1.2 The B8001 is the only public road to both the village of Skipness, and the Claonaig Bay ferry terminal (to Arran) with no suitable alternative route. The road has sustained damage due to land movement (land-slip) affecting large areas immediately up and down hill of the road. Slope failures on the south- western embankment (lower slope) in 2020 led to substantial differential settlement and further movement of the road make-up causing significant cracking and collapse of part of the road surface adjacent to the lower embankment. The width of the road has been restricted to ensure safety of road users. There is evidence of further historic and ongoing movement across the area. The Claonaig Water river runs roughly parallel to the B8001 road in the area of the failure. Associated drainage works are required as part of the engineering works to repair the embankment.
3.1.3 The geology that caused the landslip is quite intricate and the original solution of stabilising the embankment has been amended following intrusive ground investigation work with a piling rig, detailed design work and discussions with external geotechnical engineering advisors. Design Consultants were commissioned to prepare an Options Appraisal report which considered a total of five remedial solutions utilising a range of construction techniques.
3.1.4 Within the Roads Reconstruction Budget there is £464k allocated to this and further budget funds of £430k are being vired from the wider capital budget for drainage works, however, having tested the market and progressing the project using early contractor involvement to conclude a deliverable design, the overall costs are now estimated to be around £1.6M. This creates a shortfall of funding of £706k.
3.2Road Marking Machine
3.2.1 At the Council Budget Meeting in February 2023, funding was allocated for new vehicles to support the operations of Road and Infrastructure Services.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.