Decision The Council – 1. noted the capital and revenue implications of the LEIP / Mull Campus project which were of a strategic financial nature; 2. considered the project to be affordable at this time, and agreed that up to £5m from the previously earmarked LEIP funding be used to commence the Business Case, undertake engagement exercises, commence the site selection process and establish governance arrangements; with updates being brought back to Members at appropriate gateway points; 3. noted the information provided in regard to the Economic, Community & Educational implications relative to the proposed Mull Campus as outlined in the bid and previous reports and that these would be considered further once the project proceeded to a full business case; and 4. noted that capital and revenue budget provision would require to be built into future budget estimates and approved as part of budget setting process. (Reference: Report by Executive Director with responsibility for Commercial Services and Education; and Executive Director with responsibility for Finance / Section 95 Officer dated 16 April 2024, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The purpose of this report is to update Council on the Council’s Learning Estate Investment Programme (LEIP) project to deliver a New Campus on Mull. LEIP is the Scottish Government’s flagship investment programme for Education which was a competitive bidding process, and it was confirmed in October 2023 that Mull had been successful in winning access to the fund. This has created an exciting opportunity to create a once in a generation investment in Education community infrastructure for the island, however the level of financial commitment from the Council is significant and must be carefully considered. Mull was chosen to be the Council’s sole bid to LEIP and number one priority for strategic investment in Education due to being the only secondary school in Argyll and Bute to be graded as ‘Poor’ in terms of learning suitability.
1.2This report follows on from, and should be considered in conjunction with the associated update reports, discussion and minutes on the same subject matter from Policy & Resources Committee dated 15th February and Council dated 22nd February. It is also noteworthy there was a Deputation made at the Council meeting in February by community members on Mull, including Parent Council representatives in relation to this subject matter.
1.3At the 22nd February Council meeting it was agreed that no decision, as to whether or not to proceed with the Mull Campus should be taken at that time and that officers were asked to prepare a further report with more detail regarding the financial aspects and affordability of LEIP and hold a Members Seminar. This report aims to fulfil that request and it is confirmed that a Members Seminar took place on 12th April.
1.4In the context of the additional detail contained here within, Members must now determine whether they consider the LEIP project to be affordable – or not - and require to adequately plan for capital and revenue implications of that preferred outcome. This must be done whilst being aware of the economic, community and educational implications of their decision.
1 ARGYLL AND BUTE COUNCIL COUNCIL COMMERCIAL SERVICES, EDUCATION 25TH APRIL 2024 AND FINANCIAL SERVICES
2.1This report follows on from, and should be considered in conjunction with the associated update reports, and minutes from the Policy & Resources Committee of 15th February and the Council of 22nd February 2024. Members will recall that there was a Deputation heard at the Council meeting on 22nd February by community members on Mull, including Parent Council representatives in relation to LEIP, and it was decided:-
“in the light of the update on funding, that no decision as to whether or not to proceed be taken at this time and that officers prepare a further report with more detail regarding the financial aspects and affordability of LEIP, to be the subject of a Members Seminar and then brought to the Council meeting in April 2024 for members’ consideration.”
Recommendations
3.1Council are asked to:
a) Note the capital and revenue implications of the LEIP / Mull Campus project which are of a strategic financial nature;
b) Determine in light of the financial information provided, whether they consider the project to be affordable at this time and if so, agree that up to £5m from the previously earmarked LEIP funding be used to; commence the Business Case, undertake engagement exercises, commence site selection process and establish governance arrangements with updates being brought back to Members at appropriate gateway points;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.