Decision The Policy and Resources Committee approved – 1. the continued development and implementation of the remaining elements of the iTrent project (Phase 2), in order to maximise the benefits from its investment, as outlined in the original business case; and 2. additional budget resources of £480k for 2025/26, to be funded from the partial release of an earmarked reserve balance, previously earmarked to create a general provision for future redundancy costs. (Reference: Report by Executive Director with responsibility for Customer Support Services and Financial Services dated 3 April 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The purpose of this report is to update Policy and Resources Committee on the major new HR and Payroll system implementation, to highlight what has been delivered so far and request additional funding to complete the final elements of the project. 1.2 The Policy and Resources Committee agreed to support the HR and Payroll system replacement project in 2021, with funding approved for this purpose. The previous system was about to become obsolete. MHR/iTrent were the successful bidders and a project team and project board were put in place to oversee the implementation of the new system. 1.3 This paper highlights the successes in the installation of this new system to date, along with a number of challenges that emerged post implementation, which have caused some delays to completing the final elements of system installation and realisation of the full expected outcomes. These final elements will result in greater efficiencies and accuracy in our people management processes. 1.4 The Policy and Resources Committee is requested to approve: a) The continued development and implementation of the remaining elements of the iTrent project (Phase 2), in order to maximise the benefits from its investment, as outlined in the original business case; and
b) Additional budget resources of £480k for 2025/26, to be funded from the partial release of an earmarked reserve balance, previously earmarked to create a general provision for future redundancy costs. ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE 8 MAY 2025 JOINT REPORT BY CUSTOMER SUPPORT SERVICES AND FINANCIAL SERVICES
ITRENT HR AND PAYROLL SYSTEMS REPLACEMENT PROJECT UPDATE
2.0INTRODUCTION
2.1In 2021, the council approved the replacement of its core HR & payroll software application, Resourcelink with MHR iTrent. This decision was taken following approval of the associated Business Case by SMT, the agreement to allocate funding and the selection of a preferred provider via a competitive procurement process. This resulted in the award of a 5 year contract to MHR iTrent, commencing 1 January 2023. 2.2 A multi-disciplinary project team was established to deliver the successful implementation of the replacement system. The system comprises a number of modules and phased implementation saw the first modules go live in August 2024, with the new payroll module delivering the August pay for teachers. 2.3 A number of challenges have been encountered post implementation. These predominantly relate to issues associated with the functionality of the payroll module. Unfortunately, these issues were unforeseen and therefore not provided for within the original project timescale and approved resources. 2.4 A project remediation plan for the resolution of key issues is now in place and resources have been allocated to develop and manage delivery of agreed remedial actions. A risk based approach has been taken to the deployment of resources and it has been necessary to prioritise this remedial work over the continued development and implementation of remaining modules, fundamental to delivery of the wider objectives outlined in the business case. 2.5 It will not be possible to fully deliver the iTrent project objectives within approved project resources. As such, a cost benefit analysis of potential options has been undertaken in order to inform recommended next steps. 2.6 The purpose of this report is to set out the original iTrent project objectives, provide and update on progress and challenges to date, and bring forward recommended next steps, based on an options appraisal.
Recommendations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.