Decision 1. approved the Policy on Year End Flexibility as included in Appendix 1; 2. approved the three new earmarked proposals that total £2.600m as supported by business cases as outlined within Appendix 2; 3. noted the £8.278m of earmarking that qualify for automatic carry forward in line with the Policy on Year End Flexibility as outlined within Appendix 3; and 4. noted previously approved earmarked reserves as outlined within Appendix 4 with a balance of £94.284m as at 31 March 2025. (Reference: Report by Section 95 Officer dated 16 June 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
REPORT BY EXECUTIVE DIRECTOR DOUGLAS HENDRY & 26 JUNE 2025 EXECUTIVE DIRECTOR KIRSTY FLANAGAN
PROPOSAL TO EARMARK FUNDS FROM GENERAL FUND RESERVE
STORM EOWYN
1. INTRODUCTION
1.1The purpose of this report is to request support in earmarking from unspent budget/unallocated General Fund for a specific purpose, in line with the Policy on End of Year Flexibility.
2. DETAIL
2.1Initiative/Proposal
2.1.1 It is proposed that £1.3m be earmarked from a combination of the overall revenue budget underspend and funds held within the Unallocated General Fund to fund expenditure in relation to Storm Eowyn.
2.2Business Case – Storm Eowyn
2.2.1 A separate report is on the Council agenda today in respect of Storm Eowyn. Storm Eowyn struck Argyll and Bute on 24 January 2025, bringing wind speeds of up to 100 mph and causing widespread damage. The Council’s infrastructure suffered significant damage, particularly to roads, sea walls, harbour facilities and property. Helensburgh Leisure Centre suffered extensive damage to its roof and water damage to the interior of the building and fixtures and fittings.
2.2.2 At this stage all costs in relation to Storm Eowyn are not known and figures may be subject to change. However, at the present time it is estimated that the total expenditure amounts to £3.952m. This figure does not include any shortfall in relation to Helensburgh Leisure Centre (HLC) in respect of the difference between insured works and required works.
2.2.3 For HLC, the Council’s insurers will cover like for like repairs to the building and contents. However, it is felt that it would be prudent to check that the existing design and roof covering will withstand future weather incidents of this nature. Should changes to the design be required there will be re-design, re-engineering and legal costs involved.
2.2.4 £2m has already been set aside from the roads reconstruction budget, £0.792m has been absorbed within the 2024-25 revenue outturn and £0.353m is expected from a Bellwin Claim. This leaves a gap of £0.807m. Appendix 2b 2.2.5 This gap does not include any costs for Helensburgh Leisure Centre. On the basis that the Council will require to undertake a technical assessment that will not be covered by the Insurers like for like cover and in the knowledge that not all costs incurred by the Council will ultimately be recoverable, it would be prudent to set aside some funding to cover:
a) any additional costs to ensure that the HLC is suitably reinstated for use at the earliest opportunity, and b) potential legal costs incurred by Council in court proceedings in regard to the design and construction of the Leisure Centre.
2.2.6 At the budget meeting on 27 February 2025, Council previously agreed to set aside £2.9m to boost future resilience for severe weather related costs. As the wording suggests, this was for future resilience but there is an option that Council could agree to use some of this funding towards the budget gap. However, due to the overall underspend on the revenue budget in 2024-25 and the balance in the unallocated General Fund, it is recommended that Council set aside a further £1.3m of funding towards Storm Eowyn related costs on the basis that any funding not required for such purposes be returned to the General Fund.
2.3Expenditure Profile
2.3.1 It is anticipated that the sum of £1.3m will be spent over 2025-26 and 2026-27.
DOUGLAS HENDRY & KIRSTY FLANAGAN EXECUTIVE DIRECTORS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.