Decision The Council – 1. noted the actual expenditure incurred during the financial year 2024-25 and progress on delivery of the Capital Plan as at 31 March 2025; and 2. approved the updated Capital Plan, as detailed within Appendix 1. (Reference: Report by Section 95 Officer dated 9 June 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report provides a summary of the financial position and progress on delivery of the approved 2024-27 Capital Plan as at 31 March 2025. It provides details of the actual expenditure incurred during the financial year 2024-25 and the forecast outturn across future years, in comparison to the approved Capital Plan budget for each service.
1.2A number of budget changes have been made to the Capital Plan since last reporting to reflect previous approvals. There are no further changes to previously reported reprofiling of expenditure across 2024-25 and future years, at this stage. Any 2024-25 budget over or underspends will be rolled forward and reprofiled across 2025-26 and future years, as part of the year end process.
1.3Financial Position:
• 2024-25 Actual Outturn – Actual gross capital expenditure for the financial year totals £48.553m, compared to a profiled annual revised budget of £70.588m, giving rise to an underspend for the year of £22.035m (31.2%). Project specific income totals £4.523m, resulting in project actual net expenditure of £44.030m in 2024-25. The actual borrowing required to finance capital expenditure incurred during 2024-25 is lower than originally estimated at £28.717m.
• Total Capital Plan Forecast Outturn – Forecast outturn gross expenditure on the total Capital Plan is £189.728m, compared to a budget of £189.611m, resulting in a forecast overspend of £0.117m (0.06%). Additional resources of £0.117m have been approved as part of the 2025-26 budget process to meet this forecast overspend.
1.4Capital Plan risks may impact the delivery of the plan within available resources and target timescales. The monitoring and review of specific Capital Plan risks will continue to be undertaken on an ongoing basis and reported to the Policy and Resources Committee, as part of future capital monitoring reports.
1.5It is recommended that Council:
• Note the actual expenditure incurred during the financial year 2024-25 and progress on delivery of the Capital Plan as at 31 March 2025; and
• Approve the updated Capital Plan, as detailed within Appendix 1. ARGYLL AND BUTE COUNCIL COUNCIL
FINANCIAL SERVICES 26 JUNE 2025
CAPITAL PLAN MONITORING REPORT – FOR THE YEAR ENDING 31 MARCH 2025
2.0INTRODUCTION
2.1This report provides a summary of the financial position and progress on delivery of the approved 2024-27 Capital Plan as at 31 March 2025.
2.2It provides details of the actual expenditure incurred during the financial year 2024-25 and the forecast outturn across future years, in comparison to the approved Capital Plan budget for each service.
Recommendations
3.1It is recommended that Council: • Note the actual expenditure incurred during the financial year 2024-25 and progress on delivery of the Capital Plan as at 31 March 2025; and • Approve the updated Capital Plan, as detailed within Appendix 1.
4.0BUDGET CHANGES
4.1Following the decision at Policy and Resources Committee on 9 December 2021, the Rothesay Pavilion project was put on pause, whilst potential funding options were being considered. At the budget meeting in February 2023, additional funding was allocated to this project, which will allow the project to progress towards successful delivery, by supporting completion of certain work stages. Further funding was allocated at the budget meeting in February 2024 for stages 2 and 3 to complete the project. Since last reporting, the Capital Plan has been updated to incorporate previous approvals relating to Phase 1, 2 and 3 of the Rothesay Pavilion project. Gross expenditure has been increased by £20.559m in this respect (£0.559m 2024/25, £10m 2025/26 and £10m future years), while project specific income has been increased by £11.7m (£6.7m 2025/26 and £5m future years).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.