Decision The Community Services Committee: 1. c onsidered the information contained within this report; 2. agreed to endorse officers’ actions not to commence the statutory relocation consultation exercise on 18 August 2025, given that the Judicial Review proceedings are ongoing; 3. agreed to endorse the decision of the Strategic Board, dated 4 August 2025, to pause all other work on the Project (including design work and development of the Outline Business Case) whilst the Judicial Review proceedings are ongoing; and 4. agreed that all further reports should be brought to Members whilst the ongoing Court proceedings progress. (Reference: Report by Executive Director with responsibility for Education, Legal and Regulatory Support and Commercial Services dated 1 August 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report provides an update to the Community Services Committee on recent decisions and developments in relation to the project for a new 2-18 School Campus in Tobermory. In particular, it highlights to Members the lodging of a Petition for Judicial Review in the Court of Session, which has triggered a material change in circumstances following the decision of the Special Council meeting on 7th March 2025 regarding site selection for the new Campus; as well as the subsequent decision of the Community Services Committee, dated 5th June 2025, to commence a statutory consultation exercise on a relocation proposal in terms of the Schools (Consultation) (Scotland) Act 2010.
1.2The Community Services Committee are invited to: 1.2.1 Consider the information contained within this report; 1.2.2 Agree to endorse officers’ actions not to commence the statutory relocation consultation exercise on 18th August 2025, given that the Judicial Review proceedings are ongoing; 1.2.3 Agree to endorse the decision of the Strategic Board, dated 4th August 2025, to pause all other work on the Project (including design work and development of the Outline Business Case) whilst the Judicial Review proceedings are ongoing; and 1.2.4 Agree that further reports shall be brought to Members as appropriate whilst the ongoing Court proceedings progress.
1 ARGYLL AND BUTE COUNCIL COMMUNITY SERVICES COMMITTEE EDUCATION AND COMMERCIAL SERVICES 28TH AUGUST 2025
TOBERMORY 2-18 CAMPUS – UPDATE AND NEXT STEPS
2.0INTRODUCTION
2.1Following the decision of the Special Council on 7th March 2025, regarding the site selection for a new 2-18 School Campus on the Isle of Mull, a Petition for Judicial Review was lodged in June 2025 in the Court of Session, challenging that decision. 2.2 As a result, and given that those proceedings are ongoing, this report provides an update to Members on the progress of the project thus far, and makes recommendations in terms of next steps, assessed by officers as appropriate in light of the ongoing court proceedings.
Recommendations
3.1The Community Services Committee are invited to: 3.1.1 Consider the information contained within this report; 3.1.2 Agree to endorse officers’ actions not to commence the statutory relocation consultation exercise on 18th August 2025, given that the Judicial Review proceedings are ongoing; 3.1.3 Agree to endorse the decision of the Strategic Board, dated 4th August 2025, to pause all other work on the Project (including design work and development of the Outline Business Case) whilst the Judicial Review proceedings are ongoing; and 3.1.4 Agree that further reports shall be brought to Members as appropriate whilst the ongoing Court proceedings progress.
4.0DETAIL
4.1On 25th April 2024, the Council considered the terms of a report providing an update on the Council’s Learning Estate Investment Programme (LEIP) to deliver a new Campus on Mull. This report followed previous updates to the
2 Policy and Resources Committee on 15th February 2024, and the Council meeting of 22nd February 2024.
4.2After considering the terms of that report, the Council, amongst other things, decided to note the capital and revenue implications of the LEIP/Mull Campus project which were of a strategic financial nature; and considered the project to be affordable at that time, and agreed that up to £5m from the previously earmarked LEIP funding be used to commence the Business Case, undertake engagement exercises, commence the site selection process and establish governance arrangements; with updates being brought back to Members at appropriate gateway points.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.