PIERS AND HARBOURS - MARINE ASSET MANAGEMENT PLAN - WORKS UPDATE

Noted Committee 2 papers

AI summaryArgyll and Bute Harbour Board noted an update on capital works in the Marine Asset Management Plan, representing nearly £22 million of investment in 2025/26 across multiple piers and harbours.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAcross piers and harbours in Argyll and Bute
Moneynearly £22 millionInvestment in marine infrastructure in 2025/26
What happens nextSeveral projects in planning or underwayIncluding Oban, Craignure, Iona, Fionnphort
Who it affectsMarine users, island communities, businessesFerry passengers, fishermen, importers, exporters

What was decided

The Harbour Board noted the update on capital works being progressed in the Marine Asset Management Plan. Report 3.1

The plan is now structured as a 5-year look ahead to support long-term financial planning. Report 1.3

Funding is primarily through Prudential Borrowing, repaid via fees from major ports, with additional grants pursued from Crown Estate Scotland and Transport Scotland.

Why

To update Members on programmed capital works developing and upgrading the Council's marine infrastructure. Report 1.1, 2.1

A significant number of projects focus on renewing or adapting infrastructure to support CalMac ferry services ahead of new vessels. Report 4.1

The streamlined 5-year plan allows officers to give a clearer picture of upcoming projects and supports long-term financial planning. Report 1.3

What happens next

The Management and Development Consultant tender for Craignure closes at the end of January 2026, with the appointee advancing the project to Final Business Case.

An Environmental Impact Assessment is underway for the Fionnphort overnight berthing facility, with construction and dredging consent applications to follow.

Officers will undertake a staged approach to Carradale Harbour defects, starting with a diver survey once the Marine Framework becomes active in early 2026.

The money

  • nearly £22 million Investment in marine infrastructure in 2025/26 Report 1.2
  • £3.1m Campbeltown spend in 2025/26
  • £9.1m Iona breakwater spend in 2025/26
  • £16.4m Iona current financial plan estimate
  • £25.5m Fionnphort current financial plan figure
  • £47.9m Craignure current financial plan figure
  • £12.5m Gigha and Tayinloan current financial plan figure
  • approximately £4.9 million Proposed partial funding grant for SVRP ports

Options considered

  • Rejected: Oban Harbour Revision Order. Submission to Cabinet Secretary still being completed by Transport Scotland; awaiting update Report 4.4
  • Chosen: Rothesay East Roundhead options. Officers progressing options to select a suitable option for the harbour's future needs
  • Chosen: Carradale Harbour repair approach. Staged approach starting with diver survey of ICCP anodes and submerged elements

Implications

  • Financial: Increases to fees and charges are required to ensure future income is sufficient to maintain and develop marine assets, with alternative funding routes also to be explored.
  • Risk: Above inflation increases may have a detrimental economic impact on fishermen, bulk importers, timber exporters, wind farm developers and cruise companies, and may reduce usage and customers. Report P14
  • Risk: External influences such as vessel breakdowns, environmental issues and potential changes in RET may impact ferry usage and income from ferry fees and charges. Report P15
  • Other: Funding raised from increased fees and charges will support future projects and enhance service reliability and community connectivity for island communities.
  • Other: Completed works will support improved accessibility and service reliability benefiting children's access to schools and wider activities.
  • Climate: There are no direct climate change impacts from this report, but due regard will be given to climate change to minimise impacts as and when they arise. Report 6.7

Who and where

  • CalMac Ferry Limited services and passengers Report 4.1
  • Local fishing and leisure users at Carradale
  • Campbeltown Harbour commercial users
  • Businesses using facilities including fishermen, bulk importers, timber exporters, wind farm developers and cruise companies Report P14
  • Island communities, including Iona, Gigha, Fionnphort, Jura and Islay
  • Children accessing schools and activities on islands
  • Oban users and Transport Scotland Report 4.4

Timeline

  • January 2025: General inspection of Carradale Harbour carried out
  • 20 March 2025: Harbour Board approved completion of Craignure Outline Business Case and continuation to Final Business Case pre-construction
  • Monday 3rd November 2025: Campbeltown Wall A works completed and area re-opened to the public
  • End of January 2026: Craignure Management and Development Consultant tender returns due
  • Early 2026: Carradale diver survey expected once Marine Framework becomes active
  • 2026/27: Planned £3m Craignure spend
  • 2029 onwards: New Small Vessel Replacement Programme vessels scheduled to begin service

Plain English for the jargon

  • MAMP: Marine Asset Management Plan
  • CFL: CalMac Ferry Limited
  • HRO: Harbour Revision Order
  • OBC: Outline Business Case
  • FBC: Final Business Case
  • MDC: Management and Development Consultant
  • SVRP: Small Vessel Replacement Programme
  • ICCP: Impressed Current Cathodic Protection
  • EIA: Environmental Impact Assessment
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item3

Resolved

Decision The Argyll and Bute Harbour Board noted the update on capital works currently being progressed within the Marine Asset Management Plan. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure, dated December 2025, submitted) *
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Argyll and Bute Harbour Board

Executive summary

1.1This report is to update Members on the latest programmed Capital Works being carried out to develop and upgrade the Council’s marine infrastructure.

1.2It includes details on projects which are either in the planning stages or well underway across the area and represents an investment of nearly £22 million in 2025/26.

1.3This year the plan has been streamlined into a 5-year look ahead. This allows officers to provide a clearer picture of key upcoming projects and supports long- term financial planning. ARGYLL AND BUTE COUNCIL ARGYLL AND BUTE HARBOUR BOARD ROADS AND INFRASTRUCTURE SERVICES 29 JANUARY 2026

PIERS AND HARBOURS MARINE ASSET MANAGEMENT PLAN – WORKS UPDATE

2.0INTRODUCTION

2.1This report provides Harbour Board Members with a review of the marine infrastructure works contained within the Marine Asset Management Plan (MAMP). It includes significant and major programmes currently planned as well as those underway.

Recommendations

3.1Members are asked to consider and note the updates on capital works currently being progressed within the Marine Asset Management Plan.

4.0DETAIL

4.1The Marine Asset Management Plan (MAMP) outlines the Council’s programmed capital works to develop and upgrade marine infrastructure across Argyll and Bute. The plan provides cost estimates for the next five years while remaining flexible to respond to changing priorities, design developments, construction methods, and market conditions. A significant number of projects focus on renewing or adapting infrastructure to support CalMac Ferry Limited (CFL) services ahead of the arrival of new vessels. 4.2 Funding is primarily sourced through Prudential Borrowing, repaid via fees from major ports, with additional grants actively pursued from organisations such as Crown Estate Scotland and Transport Scotland. All projects undergo competitive tendering to secure value for money and high quality delivery. They are regularly monitored and re-forecast to manage risk, maintain progress, and ensure budgets are adjusted appropriately. 4.3 Alongside our maintenance, servicing and conservancy works, Marine Operations are presently engaged in several long, and shorter-term projects across Argyll & Bute which include:

• Oban - Harbour Revision Order; • Craignure –New Ferry Terminal; • Iona breakwater – protection of ferry berthing slip; • Fionnphort overnight berthing facility; • Port Askaig – Enabling works for new CalMac vessel; • Campbeltown and Carradale Harbours; • Rothesay Harbour; • Feolin – Jura passenger only service access; and • Gigha / Tayinloan – SVRP upgrades including overnight / charging at Gigha.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MAMP 25 vDecAppendix 1 93 KB Download
PDF
PIERS AND HARBOURS: MARINE ASSET MANAGEMENT PLAN: WORKS UPDATEReport 186 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 11 attended
JS
Julieann SmallSecretary, expected
KM
Katie McKenzieSecretary, expected
JA
Councillor John ArmourVice-Chair, present
GB
Councillor Gordon BlairMember, present
MC
Councillor Maurice CorryMember, present
AK
Councillor Andrew KainMember, present
LM
Councillor Liz McCabeMember, expected
DM
Councillor Dougie McFadzeanMember, present
RM
Councillor Ross MorelandChair, present
AV
Councillor Andrew VennardMember, present
HM
Hazel MacInnesSecretary, expected

On this subject at Argyll and Bute

Search all
  1. PIERS AND HARBOURS - MARINE ASSET MANAGEMENT PLAN - WORKS UPDATEThis decision
  2. Piers and Harbours - Marine Works UpdateNoted
  3. Piers and harbours marine asset management plan - works updateNoted
  4. Piers and harbours - performance reportingAgreed
  5. Piers and harbours marine asset management plan fees and charges 2027 / 2028Noted
  6. Piers and Harbours - Marine Works UpdateAgreed

More from Argyll and Bute Argyll and Bute Harbour Board

All decisions
MeetingDecisionOutcome
9 Oct 2026 Piers and harbours marine asset management plan - works updateDecision The Argyll and Bute Harbour Board noted the updates on capital works currently being progressed within the M... Noted Open
9 Oct 2026 Piers and harbours - performance reportingDecision The Argyll and Bute Harbour Board – 1. agreed the proposed approach and structure to annual performance repo... Agreed Open
9 Oct 2026 Carradale harbourDecision The Argyll and Bute Harbour Board noted the content of the report. (Reference: Report by Executive Director ... Noted Open
9 Oct 2026 Piers and harbours marine asset management plan fees and charges 2027 / 2028Decision The Argyll and Bute Harbour Board – 1. noted that officers were of the view that a review is required to con... Noted Open
9 Oct 2026 Argyll and bute harbour board workplanDecision The Argyll and Bute Harbour Board noted the content of the workplan. (Reference: Argyll and Bute Harbour Boa... Noted Open