Argyll and Bute Council

Transport Scotland

Noted Planning 2 papers

AI summaryMid Argyll planning group notes Transport Scotland A83 works programme running to September 2026, with temporary traffic signals through most of the period.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedGroup noted the information provided by Transport Scotland.
MoneyNot stated
What happens nextWorks continue to September 2026Programme is indicative and subject to revision.
Who it affectsA83 road usersTemporary traffic signals on the A83 for most works.

What was decided

The group noted the Transport Scotland update on upcoming A83 works. Report P7

Why

Transport Scotland set out a programme of hillside, slope and drainage repairs on the A83, including remedial works after a landslip on 1st September 2025. Report P4, P5, P6

What happens next

Pre-Christmas barrier and drainage repairs will use temporary traffic signals on the A83 for one week, then pause for two weeks over the festive period. Report P1, P2

From January to September 2026 further barrier, slope, drainage and boulder removal works are planned, including at Butterbridge, Glen Kinglas and Loch Restil. Report P3, P4, P5, P6

The programme is indicative and may change due to hillside movements, weather or further landslip assessments. Report P7

Options considered

  • Chosen: Note the Transport Scotland update. Standard information item presented to the group.

Implications

  • Other: Drivers on the A83 should expect temporary traffic signals from now until around September 2026, with a break over Christmas and New Year. Report P1, P2, P3, P4, P5, P6

Who and where

  • Road users on the A83 in Mid Argyll, Kintyre and the Islands Report P1, P2, P3, P4, P5, P6
  • Residents and businesses near the A83 works sites, including the Rest and Be Thankful, Butterbridge, Glen Kinglas and Loch Restil areas Report P4, P5, P6

Timeline

  • Now to pre-Christmas: Hillside barrier repairs, crash cushion repairs, drainage emergency works, 1 week of temporary signals on A83. Report P1
  • Christmas to New Year: Two week pause in site works; traffic management removed. Report P2
  • First week after the break: Further hillside barrier repairs, 1 week; traffic management removed. Report P3
  • January to March 2026: Hillside barrier repairs, slope remedial works, routine maintenance, boulder removal, and A83 Rest and Be Thankful remedial works after the 1 September 2025 landslip. Temporary traffic signals on A83. Report P4
  • April to June 2026: Slope remedial works and routine drainage maintenance, plus works at Butterbridge and Glen Kinglas after the 1 September 2025 landslip. Temporary traffic signals on A83. Report P5
  • July to September 2026: Works at Loch Restil (Easn Dubh); exact period to be defined. Temporary traffic signals on A83. Report P6

Plain English for the jargon

  • A83: The A83 trunk road, including the Rest and Be Thankful (RaBT) section in Argyll.
  • RaBT: Rest and Be Thankful, a well known stretch of the A83 prone to landslips.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11f

Resolved

Decision The Mid Argyll, Kintyre and the Islands Area Community Planning Group noted the information provided. (Reference: Report by , submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Mid Argyll, Kintyre and the Islands Area Community Planning Group

Periods Activity Duration Traffic Management Now – Pre Hillside protection barriers repairs 1 week Temporary Traffic Signals on A83 Christmas Roadside crash cushion repairs on A83 Drainage emergency repairs

Christmas – No site works 2 weeks Traffic management removed New Year

First week after Hillside protection barriers repairs 1 week Traffic management removed the Christmas and New Year break

January – Hillside protection barriers repairs 3 months Temporary Traffic Signals on A83 March 2026 Slope remedial works Routine barriers and drainage maintenance works Hillside boulder removal Remedial works at A83 RaBT following landslip on 1st Sep 2025

April – June Slope remedial works 3 months Temporary Traffic Signals on A83 2026 Routine drainage maintenance works Remedial works at Butterbridge and Glen Kinglas following landslip on 1st Sep 2025

July – Works at Loch Restil (Easn Dubh). Exact period to be Temporary Traffic Signals on A83 September defined 2026

Note: This is an indicative programme and is subject to revision, for example due to unpredictable hillside movements, adverse weather conditions, assessment findings for remedial works of landslip events.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transport Scotland 2Report 207 KB DownloadRead as text
PDF
Transport ScotlandReport 71 KB Download

At this meeting

Whole meeting

Who was there

0 of 5 attended
IC
Iona CampbellSecretary, expected
KC
Karen CampbellSecretary, expected
AH
Councillor Anne HornChair, expected
CM
Caitlin McNeillVice-Chair, expected
JS
Julieann SmallSecretary, expected

On this subject at Argyll and Bute

Search all
  1. Transport ScotlandThis decision
  2. Transport Scotland UpdateNoted
  3. Transport ScotlandNoted
  4. Transport ScotlandNoted
  5. Transport ScotlandNoted
  6. Transport scotlandNoted

More from Argyll and Bute Mid Argyll, Kintyre and the Islands Area Community Planning Group

All decisions
MeetingDecisionOutcome
4 Nov 2026 Medieval Kintyre ProjectDecision The Mid Argyll, Kintyre and the Islands Area Community Planning Group noted the information provided. (Refer... Noted Open
4 Nov 2026 Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Community Planning Group noted the content of the report and th... Noted Open
4 Nov 2026 Scottish ambulance service updateDecision The Mid Argyll, Kintyre and the Islands Area Community Planning Group noted the information provided. (Refer... Noted Open
4 Nov 2026 Community planning partnership management committee meeting highlightsDecision The Mid Argyll, Kintyre and the Islands Area Community Planning Group noted the contents of the report. (Ref... Noted Open
4 Nov 2026 Argyll and bute improvement plan - priorities updateDecision The Mid Argyll, Kintyre and the Islands Area Community Planning Group noted the information provided. (Refer... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies