HOUSING SERVICES ACTIVITY UPDATE - STRATEGIC HOUSING INVESTMENT PLAN (SHIP) - ANNUAL UPDATE

Noted Committee 1 paper

AI summaryOban, Lorn and the Isles Area Committee noted a housing services activity update covering 6 new affordable homes in Lorn, falling homelessness, and 22 empty homes brought back into use in 2024/25.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted the housing services update
MoneyNo new spending agreedNo financial decisions in this report
What happens nextRevised HNDA in spring 2026New Housing Need and Demand Assessment to be submitted
Who it affectsOban, Lorn and the Isles residentsPlus people on housing waiting lists and in temporary accommodation

What was decided

The Oban, Lorn and the Isles Area Committee noted the content of the housing services activity update report.

Why

The report sets out housing services activity and progress with the Local Housing Strategy in the Oban, Lorn and the Isles area, covering the housing emergency, homelessness, supply, empty homes, and energy efficiency. Report 1.1, 2.1, 4.0

Argyll and Bute was the first Scottish council to declare a housing emergency in June 2023, with around 3,300 households on social rented waiting lists and 75% of surveyed employers citing housing shortages as a barrier to recruitment. Report P12, P13, 4.2

What happens next

A revised Housing Need and Demand Assessment will be submitted to the Scottish Government in spring 2026, with new housing requirements then apportioned to each Housing Market Area. Report 5.3

After finalising the HNDA, the Council will begin work on a new Local Housing Strategy covering 2027 to 2032, with partner consultation. Report 12.1

A pipeline of affordable housing projects is planned in the SHIP through to 2031/32, including Dunbeg phase 4 (269 units) and smaller rural schemes. Report 7.2, P39, P40

The money

  • £1,310,535 Funding for WHH A Port Appin, 6 new affordable homes in Lorn in 2024/25 Report P37, 7.1
  • £138,091.96 PSHG grant value for 22 adaptations installed in OLI in 2024/25 Report P53
  • £166,143.45 Works value of the 22 PSHG adaptations in OLI in 2024/25 Report P53
  • £137,385.28 EES-ABS grants supporting 85 energy efficiency measures in 57 OLI properties in 2024/25 Report P56
  • £18.26m Resource Planning Allocation for Argyll and Bute in 2023/24 Report 4.5
  • £14m Resource Planning Allocation available mid 2025 for 2024/25 Report 4.5
  • £1.057m Strategic Housing Fund spend in both 2023/24 and 2024/25 Report 4.5

Options considered

  • Chosen: Note the content of the housing services activity update report. Recommendation from the Executive Director with responsibility for Development and Economic Growth Report P2, 3.1

Implications

  • Legal: The Council has a statutory duty to deliver statutory housing functions as the Strategic Housing Authority. Report 4.1
  • Climate: The strategy and housing service deliver positive impacts for energy efficiency and climate change. Report 11.0
  • Equalities: Positive for the Fairer Scotland Duty through delivery of affordable housing.
  • Other: Positive for Island Communities through delivery of affordable housing on the islands.
  • Other: Positive for Children's Rights and Wellbeing through affordable housing for families with children.
  • Financial: No financial implications arise from this report.

Who and where

  • Residents of Oban, Lorn and the Isles needing affordable or social rented housing Report 5.0, P18, 5.1
  • Homeless applicants in the area, with applications falling to 92 in 2024/25 from 118 Report 6.1, P26
  • Rough sleepers, with 8 cases in OLI in 2024/25 reporting rough sleeping the night before application Report 6.3, P34
  • Local employers, 75% of whom said housing shortage was a barrier to recruiting or retaining staff Report P13
  • Owners of empty homes and second homes in OLI Report 8.0, 8.2, 8.3, P44, P47
  • Registered Social Landlords operating in the area, including WHH, ACHA and LINK Report 7.1, 7.2, P37, P39, P40

Timeline

  • 2024/25: 6 new affordable homes delivered at Port Appin in Lorn via the SHIP Report 7.1, P37
  • 2024/25: 22 empty homes brought back into use in OLI, 52% of the Argyll and Bute total
  • 2024/25: 22 PSHG adaptations installed in OLI, with 85 energy efficiency measures fitted to 57 properties Report P53, P56
  • 2025/26: Strategic Housing Fund and RPA allocations recorded, with a revised HNDA being prepared Report 4.5, 5.3
  • Spring 2026: Revised Housing Need and Demand Assessment to be submitted to the Scottish Government Report 5.3
  • 2026/27: Planned SHIP starts include ACHA Bay View Gypsy/Traveller site, WHH Mull Shillinghill, and Port Appin phase 2 Report 7.2, P40
  • 2030/31: Planned completion of LINK Dunbeg phase 4 (269 affordable units) Report P39
  • 2031/32: Planned WHH Craignure development of 12 units Report P40

Plain English for the jargon

  • SHIP: Strategic Housing Investment Plan, the Council's programme for delivering affordable housing.
  • LHS: Local Housing Strategy, a five-year statutory plan setting out the Council's housing vision and priorities.
  • HNDA: Housing Need and Demand Assessment, an analysis of housing need and future demand carried out every five years.
  • RSL: Registered Social Landlord, a housing association or similar provider of social rented housing.
  • HOMEArgyll: The common housing register for Argyll and Bute, used to allocate social rented homes.
  • EES-ABS: Energy Efficient Scotland: Area Based Scheme, a Scottish Government grant programme for energy efficiency works.
  • PSHG: Private Sector Housing Grant, providing adaptations, repairs and improvements for private homes.
  • WHH / ACHA / LINK: Three Registered Social Landlords active in the area: West Highland Housing Association, Argyll Community Housing Association, and Link Group.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

Decision The Oban, Lorn and the Isles Area Committee noted the content of the report. (Reference: Report by Executive Director with responsibility for Development and Economic Growth, dated January 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Oban Lorn & The Isles Area Committee

Executive summary

1.1The main purpose of this report is to update Members of Housing Services activity and progress with the Local Housing Strategy for the Oban, Lorn and the Isles area. This report will detail the following housing activity:- • Housing Emergency • Housing Need and Demand • Homelessness • Affordable Housing Supply - Strategic Housing Investment Programme (SHIP) • Empty Homes • Private Sector Housing Grant Adaptations • Private Sector Housing Grant Repairs and Improvements • Energy Efficiency - Energy Efficiency Scotland: Area Based Scheme(EES:ABS) • Local Housing Strategy

Recommendation

Members are asked to consider and agree the content of the report. ARGYLL AND BUTE COUNCIL OBAN LORN AND THE ISLES AREA COMMITTEE

DEVELOPMENT AND ECONOMIC 11th MARCH 2026 GROWTH

HOUSING SERVICES ACTIVITY UPDATE - STRATEGIC HOUSING INVESTMENT PLAN (SHIP) – ANNUAL UPDATE

2.0INTRODUCTION

2.1The main purpose of this report is to update Members of Housing Services activity and the delivery of the Local Housing Strategy within the Oban, Lorn and the Isles area. This report will detail the following housing activity:- • Housing Emergency • Housing Need and Demand • Homelessness • Affordable Housing Supply - Strategic Housing Investment Programme • Empty Homes • Private Sector Housing Grant Adaptations • Private Sector Housing Grant Repairs and Improvements • Energy Efficiency – Energy Efficiency Programme: Area Based Scheme • Local Housing Strategy

3.1Members are asked to consider and agree the content of this report.

4.0DETAIL

4.1As the Strategic Housing Authority for this area, the Council has a series of important statutory housing functions to fulfil. A Housing Need and Demand Assessment (HNDA) is carried out every 5 years which enables Scottish Government funding to be brought into Argyll and Bute primarily to deliver affordable housing. A comprehensive revision of the local HNDA was approved as “robust and credible” by the Scottish Government’s Centre for Housing Market Analysis in December 2021. The Council also produces a Local Housing Strategy (LHS) every 5 years. The LHS 2022-27 was approved by Full Council in December 2021. It is subject to annual updates, which are published on the Housing Strategy pages of the Council website.

The LHS has been developed in accordance with Scottish Government guidance and local priorities as identified in the new HNDA. .This sets out the vision for Argyll and Bute: “Everyone in Argyll & Bute has access to a suitable, high quality home which is affordable and located within a vibrant, sustainable and connected community.” This report will detail the housing activity taking place in Oban, Lorn and the Isles.

4.2HOUSING EMERGENCY

In June 2023, Argyll and Bute Council became the first local authority to declare a housing emergency. A number of key statistics informed the emergency.

• In 2023 there were just under 3,300 people on social rented housing waiting lists, representing an increase of 8% since the previous year. • The average housing price in 2022 was £206,000 which is 7 times the average income level in Argyll and Bute. • 11% of all homes are ineffective stock, with 6% second homes and 4% empty. • 42% of the property sales are made to people living out with the Argyll and Bute area. • There were 131 private house completions in the last 5 years representing only 17% of the expected rate. • Constructions costs have seen a 22% increase in 2022 with island construction costs significantly higher. This trend is continuing currently. • 92% of residents responding to the Housing Emergency survey said that housing shortage was having an impact on their community • Of employers who responded to the workforce housing survey, 75% said a shortage of housing was a barrier to recruiting or retaining staff

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HOUSING SERVICES ACTIVITY UPDATE: STRATEGIC HOUSING INVESTMENT PLAN (SHIP): ANNUAL UPDATEReport 553 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 10 attended
KC
Karen CampbellSecretary, expected
KG
Councillor Kieron GreenChair, present
AH
Councillor Amanda HampseyMember, present
WH
Councillor Willie HumeMember, present
AK
Councillor Andrew KainVice-Chair, present
JL
Councillor Jim LynchMember, present
LM
Councillor Luna MartinMember, apologies
JM
Councillor Julie McKenzieMember, present
KM
Katie McKenzieSecretary, expected
AV
Councillor Andrew VennardMember, present

On this subject at Argyll and Bute

Search all
  1. HOUSING SERVICES ACTIVITY UPDATE - STRATEGIC HOUSING INVESTMENT PLAN (SHIP) - ANNUAL UPDATEThis decision
  2. Housing services activity update - strategic housing investment plan (ship) - annual updateNoted
  3. Housing services activity update - strategic housing investment plan (ship) - annual updateNoted
  4. Housing services activity update- strategic housing investment plan (ship) - annual updateNoted
  5. Housing Services Activity Update- Strategic Housing investment plan Update (SHIP)Noted
  6. Housing services activity update - strategic housing investment plan (ship) - annual updateNoted

More from Argyll and Bute Oban Lorn & The Isles Area Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... Agreed Open
9 Sep 2026 CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... Noted Open
9 Sep 2026 Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... Noted Open
9 Sep 2026 Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... Noted Open
9 Sep 2026 Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... Decided Open