Written from the decision and the officer reportPDF Pro
OutcomeAgreedFormalise pilot into service procedures
MoneyFees from £586.30 to £1,064.80Plus 10% admin charge, cost recovery basis
What happens nextFull Council to approve feesTrial period of 1 year, review in 12 months
Who it affectsDevelopers of brownfield sitesSubmitting land contamination reports
What was decided
The committee agreed to recommend that the full Council approve the fees and charges set out in paragraph 4.22 of the report, and to formalise the pilot into standing service procedures. Report 3.1, P10
Developers will be offered two options: pre-checking reports through a registered Suitably Qualified Person under the National Quality Mark Scheme, or paying a fee for third party peer review of unchecked reports. Report 4.21, P32, P33
Why
Poor quality land contamination reports are placing a disproportionate burden on Environmental Health resources, with capacity of 0.6 FTE long exceeded by demand, leading to delays and complaints. Report 2.3, 4.3, P22
The pilot from June 2025 showed early signs of improving report quality, cutting delays, and shifting the cost of poor reporting from the Council to developers. Report 1.5, P6, P7, P8, 4.15
What happens next
The recommendation goes to full Council for approval of the fees and charges. Report 3.1
The dual approach is proposed as a trial for one year, with a further review after 12 months. Report 4.16, 5.3
The money
£709.50 Phase I reporting fee (third party peer review) Report 4.22, P47, P100
£1,064.80 Phase II reporting fee (third party peer review) Report 4.22, P47, P100
£586.30 Teams meeting attendance fee for the first hour with Council officer and third party review consultant Report 4.22, P47, P101
Options considered
Chosen: Pre-check reports through a registered Suitably Qualified Person under the National Quality Mark Scheme (NQMS). Improves report quality and reduces resource burden on Environmental Health Report 4.17, 4.18, 4.21
Chosen: Pay a fee on submission for third party peer review of un-checked reports. Guarantees review turnaround and transfers cost of poor reporting to developers Report 4.19, 4.20, 4.21
Rejected: On-request fast-track report review (paid fee) used during the pilot. Overtaken by demand; folded into the broader peer review fee option in the new proposal Report 4.13, P31
Implications
Financial: Fee structure is on a cost recovery basis with a proposed 10% administrative charge; additional costs recovered from fee income to keep reviews within budget. Report 4.22, 6.2, P102
Risk: Fee income may be insufficient to cover service expenditure. Report 6.6
Staffing: No HR implications; the proposal provides resilience within existing Environmental Health capacity of 0.6 FTE for land contamination work. Report 2.3, 6.4
Legal: No legal implications identified. Report 6.3
Equalities: No direct equalities, Fairer Scotland Duty, island communities or children's rights implications. Report 6.8, 6.9, 6.11, 6.12
Climate: No climate change implications identified. Report 6.7
Other: Customer service expected to improve through faster response times and reduced delays in decision making, supporting sustainable brownfield development. Report 6.5
Who and where
Developers and their consultants submitting land contamination reports in Argyll and Bute Report 1.1, 1.3, 4.21
The Council's Environmental Health service within Regulatory Services Report 1.2, 2.3, 4.15
The Council's Planning service, which depends on Environmental Health input on contaminated land Report 1.3, 2.2, 6.5
Timeline
December 2023: Specialist consultancy engaged to provide third party peer review of report submissions Report 4.1
June 2025: Environmental Health pilot launched, with initial review after 4 months Report 4.9, 4.11
24/02/2026: Report dated and signed by Executive Director with responsibility for Regulatory Services Report P67
18 March 2026: Planning, Protective Services and Licensing Committee considered the report Report P11
Within 12 months: Further review of the new arrangements to be carried out Report 5.3
Plain English for the jargon
NQMS: National Quality Mark Scheme, a voluntary quality assurance scheme for land contamination reports set up by professional and industry bodies.
SQP: Suitably Qualified Person, a registered practitioner who checks and certifies reports under the NQMS.
LCRM: Land Contamination Risk Management, the current methodology for assessing and managing land contamination risks, published by the Environment Agency in 2020 and endorsed by the Scottish Government in 2025.
FTE: Full Time Equivalent, a unit measuring staff capacity; Environmental Health has 0.6 FTE for land contamination regulation.
Phase I / Phase II reports: Stages of land contamination risk assessment and ground investigation submitted by developers.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
Decision The Committee considered this report, the service’s intention to formalise the pilot into service procedures and agreed to recommend to Council approval of the associated fees and charges detailed in paragraph 4.22 of the report. (Reference: Report by Executive Director with responsibility for Regulatory Services dated 24 February 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Planning, Protective Services and Licensing Committee
Executive summary
1.1Where the redevelopment of land is proposed and previous use indicates the potential for land contamination, it is the responsibility of the developer to demonstrate that their proposal is “suitable for use”, through a phased process of risk assessment and ground investigation.
1.2Land contamination reports are reviewed by Environmental Health to support decisions in the Planning process. Many reports don’t meet the quality expected of them and are insufficient.
1.3Poor quality reporting is causing an unsustainable resource burden in Regulatory Services, increasing workload demand, and causing delays whereby applicants cannot meet the terms of their planning consent. This led to an increase in corporate complaints and frustrations for developers, agents and Council officers. Regulatory Services developed a pilot to introduce a novel approach to address these problems and the pilot has been successful. This report seeks Committee approval of the fee structure to support these changes to operational procedures.
1.4As well as a fast-track option for developers, the pilot adopted a dual approach where developers were recommended to have their reports pre-checked by a registered Suitably Qualified Person within the National Quality Mark Scheme (NQMS) prior to submission, or, requested to pay a 3rd party peer review fee on submission of their un- checked reports.
1.5An initial evaluation has found early indications that this approach has
• reduced the likelihood or length of delays for developers
• improved the quality of reports received, and
• reduced resource burden on the Service
1.6This novel service development provides necessary resilience of the Environmental Health service in its support for the Planning process in the redevelopment of land, and improvements for applicants and developers.
Recommendation: Members are asked to consider this report, the service’s intention to formalise the pilot into service procedures and recommend to Council approval of the associated fees and charges detailed in paragraph 4.22. ARGYLL AND BUTE COUNCIL Planning, Protective Services and Licensing Committee
Development and Economic Growth 18 March 2026
LAND CONTAMINATION REPORTS FOR DEVELOPMENTS IN ARGYLL AND BUTE
2.0INTRODUCTION
2.1Where the redevelopment of land is proposed and previous use indicates the potential for land contamination, it is the responsibility of the developer to demonstrate that their proposed development is “suitable for use”. This is normally done through a phased process of risk assessment and ground investigation.
2.2Land contamination risk assessment and ground investigation reports are submitted by developers and passed to Environmental Health to assess whether they meet expected standards, align with authoritative guidance, and their conclusions are evidence based.
2.3The capacity within Environmental Health staff establishment for all land contamination regulation activity (0.6 FTE), has long since been surpassed by the demand from the council’s planning service and their need for expertise relating to contaminated land issues. This resulted in a growing backlog and delay in the report review process. There is no available budget to increase the staff resource at this current time.
Recommendations
3.1Members are asked to consider this report, the service’s intention to formalise the pilot into service procedures, and recommend to Council approval of the associated fees and charges detailed in paragraph 4.22
4.0DETAIL
MEASURES TO SUPPORT CHALLANGING WORKLOAD
4.1In December 2023, a specialist consultancy was engaged to provide third party peer review of report submissions. The initial 3-month period has been extended on several occasions with the costs being covered by vacancy savings.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Protective Services and Licensing Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.