Treasury Management Annual Report 2025/26

Approved Finance 1 paper

AI summaryArgyll and Bute Council's Audit and Scrutiny Committee approved the Treasury Management Annual Report 2025/26 and referred it to full Council for noting. The council held £158.181m of debt and £23.329m of investments at year end, operating within prudential limits.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAnnual report approved, then sent to full Council
Money£158.181m total debt, £380m CFRNet debt £134.852m after investments at 31 March 2026
What happens nextReferred to full CouncilFor noting at a future Council meeting
Who it affectsCouncil borrowing and investmentsCapital programme, reserves and General Fund revenue

What was decided

The Audit and Scrutiny Committee approved the Treasury Management Annual Report 2025/26. Report P22, 1.4

The committee referred the report to full Council for noting. Report 1.4, P22

Why

The report is required under the Local Government in Scotland Act 2003 and the CIPFA Code of Practice on Treasury Management to give an annual review of activity against the approved strategy. Report 1.1, 3.1, 3.2

It demonstrates that during 2025/26 the council stayed within its prudential and treasury indicators, kept a balanced position, and recorded no liquidity difficulties. Report P13, P35, P78, 6.4

What happens next

Full Council will receive the report for noting, completing the annual reporting cycle alongside the prior strategy and mid-year review already considered by Council. Report 1.4, 3.2

The money

  • £117m Internal borrowing position at 31 March 2026 Report P5, 6.1
  • £40m New borrowing taken during 2025/26 for capital funding Report P5, 6.1
  • £1.680m PWLB loan principal repaid on a 12.5-year EIP loan Report P6, 6.2
  • £10m PWLB loan repaid early, originally due 2053 Report P7, 6.3
  • £0.485m Discount achieved on early PWLB repayment, amortised to General Fund Report P7, 6.3
  • £0.048m Annual General Fund benefit in 2025/26 from the discount amortisation
  • 4.18% Average rate of return on investments during 2025/26 Report P9, 6.5
  • 4.01% Benchmark overnight SONIA rate average for 2025/26 Report P9, 6.5
  • £16.6m Shortfall in actual borrowing requirement versus 2025/26 TMSS estimate Report P10
  • £380m Closing Capital Financing Requirement at 31 March 2026 Report P11, P53, 6.7
  • £158.181m Total debt excluding PPP and finance leases at 31 March 2026 Report P12, P61, 6.8
  • £23.329m Treasury investments at 31 March 2026 Report P12, P61, 6.8
  • £134.852m Net debt after deducting treasury investments Report P12, P61, 6.8
  • 4.47% Average interest rate payable on gross debt Report P12, P33, 6.8
  • £28.540m Actual 2025/26 borrowing requirement for capital, against revised estimate of £45.199m Report P44, 6.6
  • 4.55% Weighted average rate on new borrowing taken in year Report P30

Options considered

  • Chosen: Approve and refer Treasury Management Annual Report 2025/26 to full Council. Meets statutory duty to provide an annual review of treasury activity and outturn prudential indicators to members. Report 1.4, P22, 3.1

Implications

  • Financial: Annual report on 2025/26 treasury activity and compliance with approved treasury and prudential indicators. Report 7.0
  • Risk: Provides an overview of treasury management and investment risk, with a temporary technical breach of the limit on bank deposits noted. Report 7.0
  • Legal: Report required under the Local Government in Scotland Act 2003 and CIPFA Code; no further legal implications identified. Report 1.1, 3.1, 7.0
  • Equalities: No equalities implications identified. Report 7.0
  • Climate: No climate change implications identified. Report 7.0

Who and where

  • Argyll and Bute Council as borrowing and investing authority Report P13, P88
  • General Fund, through amortisation of the early repayment discount and reduced interest costs Report P7, P33
  • Capital programme, with slippage of £17.7m from 2025/26 into future years Report P10

Timeline

  • 27 February 2025: Council approved 2025/26 Treasury Management Strategy Report 3.2
  • 4 September 2025: Audit and Scrutiny Committee considered quarterly update to 30 June 2025 Report 3.2
  • 29 January 2026: Council approved revised Prudential Indicators at mid-year review Report 3.2, P13
  • 12 March 2026: Audit and Scrutiny Committee considered quarterly update to 31 December 2025 Report 3.2
  • 31 March 2026: Year end treasury position reported, including £380m CFR and £158.181m debt Report P11, P12, 6.8
  • 11 June 2026: Audit and Scrutiny Committee approved the Annual Report and referred it to full Council Report P15, P16, P88

Plain English for the jargon

  • CFR (Capital Financing Requirement): Total historic outstanding capital expenditure not yet paid for from revenue or capital resources; a measure of the authority's underlying borrowing need.
  • CIPFA Code: CIPFA Code of Practice on Treasury Management (revised 2021), which councils must have regard to under the Local Government in Scotland Act 2003.
  • PWLB: Public Works Loan Board, a UK government body that lends to local authorities.
  • EIP: Equal Instalments of Principal, a loan repayment method where each payment includes the same amount of principal.
  • LOBO: Lender Option Borrower Option market loan, where the lender can periodically change the interest rate and the borrower can accept or repay.
  • SONIA: Sterling Overnight Index Average, the benchmark overnight interest rate used here to compare investment returns.
  • Prudential Indicators: Statutory indicators set by members to keep capital investment plans affordable, prudent and sustainable, including limits on borrowing and the ratio of financing costs to net revenue stream.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

Decision The Audit and Scrutiny Committee: 1. approved the ; and 2. referred the report to full Council for noting. (Reference: Report by Executive Director/Section 95 Officer, dated 11 June 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Audit and Scrutiny Committee

Executive summary

1.1The Local Government in Scotland Act 2003 requires the council to have regard to the CIPFA Code of Practice in Treasury Management (revised 2021), ‘the Code’. Key reporting requirements in this respect include a Treasury Management Annual Report.

1.2This annual report, prepared in compliance with the Code, covers the following:

• 2025/26 Strategy; • Borrowing and investment activity; • 2025/26 capital expenditure and the Capital Financing Requirement (CFR); • Overall treasury position (debt and investments); and • Compliance with Prudential and Treasury Indicators.

1.3The report concludes that:

a) During 2025/26, the authority maintained an under-borrowed position. The significant level of internal reserve balances has provided an opportunity to defer new external borrowing, whilst also minimising exposure to investment risk. The level of internal borrowing as at 31 March 2026 stood at £117m. £51m of that relates to leasing, leaving internal borrowing of £66m in relation to expenditure ‘funded by borrowing’ rather than through lease arrangements. New borrowing totalling £40m was undertaken during the year, to provide an element of certainty in respect of funding the underlying borrowing requirement.

b) PWLB loan principal of £1.680m has been repaid during the year in respect of a 12.5-year PWLB loan (original principal £21m), which was taken on a fixed Equal Instalments of Principal (EIP) basis.

c) Early repayment of a £10m PWLB loan, due to mature in 2053, was secured during the year with a discount of £0.485m. The General Fund will benefit from the amortisation of this discount across future years. All other PWLB loans will be repayable on maturity. d) The authority has not borrowed more than, or in advance of, its needs purely in order to benefit from the investment of the extra sums borrowed.

e) The principles of the investment strategy have been adhered to during the year, and no liquidity difficulties were experienced. Throughout the year, investments have only been made in line with the approved limits for specific investment instruments and in accordance with the creditworthiness approach.

f) The limit of investments has reflected the level of available council reserve balances, together with provision for managing the council’s day to day cash flow requirements. The average rate of return on these investments was 4.18% compared to the benchmark overnight SONIA rate average of 4.01% over the year.

g) The actual borrowing requirement for 2025-26 was £16.6m less than estimated in the Treasury Management Strategy Statement 2025-26 (TMSS) and can be explained by rephasing of project delivery, with capital expenditure being £17.7m less than originally budgeted and capital income being £1.1m less than budgeted. It should be noted that there are technical accounting requirements for capital income recognition and that a reduction in the income recognised in the year, when compared to the budget, can represent a timing difference rather than a genuine reduction in income.

h) The 2025-26 borrowing requirement adds to the authority’s Capital Financing Requirement (CFR), the underlying need to borrow for capital purposes. The actual closing CFR as at 31 March 2026 is £380m, £16m less than the mid-year revised CFR of £396m, largely due to the reduction in capital expenditure noted above. The decrease of £16m in the movement reflects a decrease in borrowing to finance capital (£17m), higher debt charges for leasing than forecast (£1m), and lease additions (- £2m) that were not part of the original estimate.

i) As at 31 March 2026, the Council’s debt (excluding PPP and lease liabilities) totalled £158.181m, while net debt, after allowing for treasury investments of £23.329m, totalled £134.852m. The average interest rate payable on this gross debt was 4.47%, repayable over an average life of 18 years.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Treasury Management Annual Report 2025/26Report 287 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 9 attended
JW
Janice Wason HallChair, present
DH
Councillor Daniel HampseyMember, apologies
GH
Councillor Graham HardieMember, present
FH
Councillor Fiona HowardMember, apologies
LI
Lynsey InnisSecretary, expected
RK
Councillor Reeni Kennedy-BoyleMember, present
KM
Katie McKenzieSecretary, expected
GM
Councillor Gary MulvaneyVice-Chair, present
AV
Councillor Andrew VennardMember, absent

On this subject at Argyll and Bute

Search all
  1. Treasury Management Annual Report 2025/26This decision
  2. Treasury Management Update - Quarter Ended 30 June 2026Noted
  3. Treasury Management Annual Report 2025/26 and recommendation from the meeting of the Audit and Scrutiny Committee held on 11 June 2026Noted
  4. Treasury Management Update - Quarter ended 31 December 2025Noted
  5. Treasury Management Strategy and Annual Investment Strategy 2026-27Noted
  6. Treasury management strategy and annual investment strategy 2026-27Approved

More from Argyll and Bute Audit and Scrutiny Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Internal Audit and Counter Fraud Summary of ActivitiesDecision The Audit and Scrutiny Committee reviewed and endorsed the Summary of Activities report. (Reference: Report ... Decided Open
3 Sep 2026 Internal and External Audit Report Follow Up 2026-27Decision The Audit and Scrutiny Committee endorsed the contents of the report. (Reference: Report by Chief Internal A... Decided Open
3 Sep 2026 Internal Audit Reports to Audit and Scrutiny Committee 2026/2027Decision The Audit and Scrutiny Committee reviewed and endorsed the summary report and detail within each individual ... Decided Open
3 Sep 2026 External Audit Progress UpdateDecision The Audit and Scrutiny Committee agreed to note the information provided. Agreed Open
3 Sep 2026 Verbal Update by Chair(s) of Scrutiny PanelDecision The Audit and Scrutiny Committee noted the information provided. Noted Open