ISLE OF BUTE BID - RENEWAL BALLOT AND DRAFT BUSINESS PLAN
AgreedCommittee4 papers
AI summaryArgyll and Bute Council agreed to hold a 42 day postal ballot on renewing the Isle of Bute Business Improvement District, voting in favour itself and setting out its levy and admin charges.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedCouncil to vote in favour of BID renewal
Money£9,445.48 admin charge, £12,400 levyPer annum, plus potential BID income up to £158,220 yearly
What happens nextBallot runs 30 July to 10 September 2026Postal ballot, count on 11 September 2026
Who it affectsIsle of Bute levy paying businessesAnd visitors and customers of the island
What was decided
The Council endorsed the BID Renewal Ballot Proposal and the draft business plan 2026 to 2031, Live Bute, Love Bute, Visit Bute, and will instruct the Returning Officer to run a postal ballot over 42 days from 30th July to 10th September 2026. Report P6, P15, P16, 1.1, 2.1
The Executive Director with responsibility for Development and Economic Growth was authorised to cast the Council's votes in favour of the BID. Report P7, P17
If the BID is successful, the Council will charge it £9,445.48 (incl. VAT) per annum for administering the levy, will pay an estimated £12,400 per annum in levy on its own Isle of Bute properties, and will appoint two representatives to the BID Board. Report P8, P9, P10, P18, P19, P20
Why
The Isle of Bute BID has completed its first term and delivered additional projects and events beyond statutory council services, and consultation with levy payers identified priorities for a second five year term. Report 1.2
Officers from Development and Economic Growth, Legal and Governance, and Financial Services supported the BID in preparing the renewal submission. Report 1.5
The proposal is judged to support the Council's Economic Strategy and Outcomes Improvement Plan, and is identified as a budget pressure on the general unallocated fund of £12,400 per year for five years.
What happens next
The Returning Officer will conduct a postal ballot from 30th July to 10th September 2026, with papers counted on 11th September and results published within one week. Report P16
If successful, the second BID term will run from 1st October 2026 to 30th September 2031, and two Council representatives will be appointed to the BID Board. Report P10, P20
Charges for the council's levy administration will be reviewed annually with the first increase on 15th April 2027, indexed to CPI. Report P8, P18
The money
£9,445.48 (incl. VAT) per annum Council charge to BID for administering the levy Report P8, P18
£12,400 per annum Estimated council levy on its own Isle of Bute properties Report P9, P19
up to £158,220 per year Potential total levy income to the BID Report 1.3
more than £791,000 over a five year period Potential total BID levy income across the term Report 1.3
Options considered
Chosen: Endorse the BID renewal ballot and draft business plan. BID has delivered in its first term and consultation shows levy payer support for a second term Report P15
Chosen: Run a 42 day postal ballot from 30th July to 10th September 2026. Required BID ballot process, facilitated by the council Report P16
Chosen: Authorise the Executive Director to vote in favour Report P7, P17
Implications
Financial: Council will pay an estimated £12,400 per year levy on its Isle of Bute properties for five years, as a budget pressure on the general unallocated fund. Report P9
Financial: Council will charge the BID £9,445.48 (incl. VAT) per year to administer the levy, with annual increases from 15 April 2027 indexed to CPI. Report P8
Legal: Council will facilitate the ballot process, including instructing the Returning Officer. Report P16
Risk: The ballot may not be successful, in which case the potential investment to the island will be lost.
Climate: Draft business plan includes proposed environmental improvement projects such as funding for community orchards and greenspaces.
Staffing: Council officers will continue to support the BID, and one elected member plus one officer will attend BID Board meetings if the ballot succeeds. Report P10
Other: The BID is island wide and offers potential benefits to all levy paying businesses on the Isle of Bute.
Who and where
Levy paying businesses on the Isle of Bute Report 1.1, 1.2
Customers and visitors to the Isle of Bute Report 1.2
Argyll and Bute Council as a levy payer on its own Isle of Bute properties
30th July 2026: Ballot period opens (postal ballot) Report 1.3, P16
Thursday 10th September 2026: Ballot day, votes must be received by 5pm Report 1.1, 1.3, 2.1
Friday 11th September 2026: Ballot papers counted
Within one week of 11th September 2026: Ballot results published
1st October 2026: Second BID term commences if ballot successful
15th April 2027: First annual increase to council admin charge takes effect Report P8, P18
30th September 2031: End of second BID term
Plain English for the jargon
Business Improvement District (BID): A defined area where businesses pay an additional levy to fund projects that improve the local trading environment, governed by a ballot of levy payers.
Renewal ballot: A new vote of eligible businesses to decide whether an existing BID should continue for another term.
Levy: The additional charge paid by businesses in the BID area to fund its activities.
Returning Officer: The official responsible for running the ballot process and counting votes.
Rateable value: The assessed value of a property used to calculate business rates, also used to weight votes in a BID ballot.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17
Resolved
Decision The Council – 1. agreed the ballot request, the Isle of Bute Business Improvement District Renewal Ballot BID Proposal at Appendix 1 and the Isle of Bute BID Draft Business Plan 2026-2031 , Live Bute, Love Bute, Visit Bute at Appendix 2; 2. agreed to instruct the Returning Officer to conduct a ballot over 42 days in 2026 from 30 th July to Thursday 10 th September (the ballot day); 3. authorised the Executive Director with responsibility for Development and Economic Growth to cast the votes on behalf of Argyll and Bute Council in favour of the BID; 4. agreed that the Council would charge £9,445.48 (incl. VAT) per annum, to the Isle of Bute BID for administering the levy charge to businesses, with charges thereafter increased annually. The first increase would apply on 15th April 2027 and annually thereafter for the subsequent term of the BID; 5. agreed, if the Isle of Bute BID was successful in the ballot, that the Council would pay an estimated £12,400 per annum in levy contributions for council properties on the Isle of Bute; and 6. noted that if the BID was successful in the renewal ballot, two representatives from the Council would be appointed to the Isle of Bute BID Board, one elected member to serve as a Board Director and one officer to attend Board meetings as a non-voting observer. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 1 May 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The purpose of this report is to ask members to endorse the Isle of Bute Business Improvement District (BID) Renewal Ballot BID Proposal and the Draft Business Plan 2026-2031, Live Bute, Love Bute, Visit Bute (the draft business plan). The proposed renewal ballot is due to take place on Thursday 10th September 2026 (the ballot day). This will be a postal ballot, and votes must be received by 5pm on the ballot day to be considered valid and included in the count.
1.2The principal aim of the BID is to deliver projects and events to improve the trading environment for businesses, their customers, and visitors. During its first term the BID has delivered a range of initiatives and projects that are additional to statutory and non-statutory services provided by the Council. The draft business plan for term two sets out the required levy contributions and outlines the BID’s objectives, benefits, and expected outcomes over a five year period. The draft business plan also details the proposed allocation of the levy income and the anticipated return on this investment.
1.3If approved, the ballot will take place over 42 days in 2026, from 30th July to Thursday 10th September (the ballot day). If successful, the levy could potentially generate up to £158,220 a year, totalling more than £791,000 over five years. The Isle of Bute BID has therefore proposed how the income from the levy could be invested to further grow the economy of the island, building on the success of the previous term.
1.4The Isle of Bute BID Draft Business Plan 2026–2031, Live Bute, Love Bute, Visit Bute, is attached as Appendix 2. The draft business plan has been developed following consultation with the Isle of Bute’s business community and outlines proposals for use of the levy income to support the continued development of the island.
1.5Through the provision of information and advice, officers from Development and Economic Growth, Legal and Governance, and Financial Services have supported the Isle of Bute BID in their development of this renewal ballot submission.
RECOMMENDATIONS Council are asked to: a. Agree the ballot request, the Isle of Bute Business Improvement District Renewal Ballot BID Proposal (Appendix 1) and the Isle of Bute BID Draft Business Plan 2026 - 2031, Live Bute, Love Bute, Visit Bute (Appendix 2). b. Agree to instruct the Returning Officer to conduct a ballot over 42 days in 2026 from 30th July to Thursday 10th September (the ballot day).
c. Authorise the Executive Director with the responsibility for Development and Economic Growth to cast the votes on behalf of Argyll and Bute Council in favour of the BID.
d. Agree that the Council will charge £9,445.48 (incl. VAT) per annum, to the Isle of Bute BID for administering the levy charge to businesses, with charges thereafter increased annually. The first increase will apply on 15th April 2027 and annually thereafter for the subsequent term of the BID.
e. Agree, if the Isle of Bute BID is successful in the renewal ballot, that the Council will pay an estimated £12,400 per annum in levy contributions for council properties on the Isle of Bute.
f. Note that if the BID is successful in the renewal ballot, two representatives from the Council would be appointed to the Isle of Bute BID Board, one elected member to serve as a Board Director and one officer to attend Board meetings as a non voting observer. ARGYLL AND BUTE COUNCIL COUNCIL DEVELOPMENT AND ECONOMIC GROWTH 24 JUNE 2026
ISLE OF BUTE BID - RENEWAL BALLOT AND DRAFT BUSINESS PLAN
2.0INTRODUCTION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.