Capital Budget Monitoring - year ending 31 March 2026
NotedCommittee1 paper
AI summaryCouncil approved updated Capital Plan of £237.083m for 2026-29, with borrowing requirement of £170.956m. Actual 2025-26 capital spend was £54.122m, £16.544m below revised budget due to project slippage.
Written from the decision and the officer reportPDF Pro
OutcomeNotedNoted 2025-26 spend and approved updated 2026-29 plan
Money£237.083m total 2026-29 budgetBorrowing requirement £170.956m; 2025-26 underspend £16.544m
What happens nextQuarter 1 2026-27 monitoring reportProgress report on revised budget to Policy and Resources
Who it affectsCouncil-wide capital projects and servicesRoads, education, harbour, CHORD, social care, ICT
What was decided
The Council noted actual capital expenditure of £54.122m incurred during 2025-26, against a revised budget of £70.666m.
The Council approved the updated Capital Plan totalling £237.083m for 2026-29, with an underlying borrowing requirement of £170.956m. Report 3.1
Why
The 2025-26 underspend of £16.544m (23.4%) reflects project slippage into future years, particularly in Roads and Infrastructure and Strategic Change projects. Report 5.4, P29
The updated plan incorporates additional investment priorities of £41.300m approved when the 2026-27 budget was set on 25 February 2026, plus reprofiling of the 2025-26 underspend. Report 6.4
What happens next
A progress report on delivery against the revised budget will be provided as part of the quarter 1 2026-27 monitoring pack to the Policy and Resources Committee.
Ongoing monitoring and review of specific Capital Plan risks will continue and be reported to the Policy and Resources Committee as part of future capital monitoring reports. Report 1.4
The money
£54.122m Actual gross capital expenditure 2025-26
£70.666m Revised 2025-26 capital budget Report 4.2
£16.544m 2025-26 underspend (23.4%) reprofiled to 2026-27
£28.540m Borrowing requirement to finance 2025-26 capital spend
£45.199m Original 2025-26 borrowing estimate
£8.781m Project specific income 2025-26
£25.582m All financing streams excluding borrowing 2025-26
£237.083m Total Capital Plan budget 2026-29 Report 3.1, P35
£41.300m Additional investment priorities approved 25 Feb 2026
£24.278m Additional spend added to existing Capital Plan
£13.079m Final General Capital Grant 2025-26 Report 5.6
£12.159m General Capital Grant supporting 2025-26 capital plan Report 5.6
Options considered
Chosen: Approve updated Capital Plan of £237.083m for 2026-29 with £170.956m borrowing requirement. Reflects 25 Feb 2026 budget decisions, reprofiling of 2025-26 underspend, and additional investment priorities Report 3.1
Chosen: Reprofile 2025-26 underspend of £16.544m into 2026-27. Reflects project slippage, particularly Harbour Investment Programme and Roads Reconstruction Report 5.4, P29
Implications
Financial: Borrowing requirement of £28.540m in 2025-26 was £16.659m lower than the original estimate of £45.199m.
Financial: The General Capital Grant must be spent in full in the year of award and cannot be carried forward. Report 5.6
Risk: Capital Plan risks to delivery within available resources and target timescales are being monitored and will be reported regularly to the Policy and Resources Committee. Report 1.4
Climate: The Council is committed to addressing climate change via delivery of projects within the Capital Plan.
Who and where
ICT, Facility Services, Central services
Timeline
2025-26: Financial year covered by the monitoring report Report 1.1, 2.1
19 February 2026: Previous capital plan position reported to Policy and Resources Committee Report 4.1
25 February 2026: Council set 2026-27 budget and approved additional investment priorities of £41.300m Report 6.4
31 March 2026: Year end position reported Report 1.1, 2.1
2 June 2026: Report by Section 95 Officer dated Report P21
24 June 2026: Council meeting at which the decision was made Report P4
2026-27: First year of the updated £237.083m Capital Plan, budget £93.720m Report 6.2, P35
2027-28: Second year of the updated plan, budget £92.973m Report 6.2, P35
Plain English for the jargon
CFCR: Capital Financed by Current Revenue: assets funded by revenue during the year, typically of low value, recognised as capital expenditure
CHORD: Charity and Other Related Developments, a programme of major coastal town regeneration projects in Argyll
Capital Financing Requirement: The council's underlying need to borrow for capital purposes
Section 95 Officer: The council's chief finance officer, with statutory responsibility for proper administration of financial affairs
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7d
Resolved
Decision The Council – 1. noted the actual expenditure incurred during the financial year 2025-26, as detailed in Appendix 1; and 2. approved the updated Capital Plan, as detailed within Appendix 3; a total budget for 2026-29 of £237.083m with an underlying borrowing requirement of £170.956m. (Reference: Report by Section 95 Officer dated 2 June 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report provides a summary of the financial position and progress on delivery of the approved 2025-28 Capital Plan as at 31 March 2026. It provides details of the actual expenditure incurred during the financial year 2025-26 and the forecast outturn across future years, in comparison to the approved Capital Plan budget for each service. 1.2 A number of budget changes have been made to the Capital Plan since the last reporting to reflect additional funding streams recognised in the last quarter of 2025-26 and changes made during the setting of the 2026-27 capital budget. There are no further changes to previously reported reprofiling of expenditure across 2025-26 and future years at this stage. Any 2025-26 budget over or underspends will be rolled forward and reprofiled across 2025-26 and future years. 1.3 Financial Position: • 2025-26 Actual Outturn – Actual gross capital expenditure for the financial year totals £54.122m, in comparison to a profiled annual revised budget of £70.666m. This gives rise to an underspend of £16.544m (23.4%) as measured against the capital plan budget. An accounting adjustment in respect of capital creditors reduces the recognised capital expenditure to £53.240m and this is the outturn figure used for the calculation of the borrowing requirement. • Project specific income - totalled £8.781m and all financing streams (excluding borrowing) totalled £24.700m. The borrowing required to finance capital expenditure incurred during 2025-26 was £28.540m, lower than the original estimate of £45.199m. • Total Capital Plan Budget – The multi-year budget of £221.675m (2025-26 onwards) reported to Policy and Resources Committee as part of the quarter 3 position has been updated to £237.083m (2026-27 onwards) as outlined at paragraph 6.2. A progress report on delivery against the revised budget will be provided as part of the quarter 1 2026-27 monitoring pack.
1.4Capital Plan risks may impact the delivery of the plan within available resources and target timescales. The monitoring and review of specific Capital Plan risks will continue to be undertaken on an ongoing basis and reported to the Policy and Resources Committee as part of future capital monitoring reports.
1.5It is recommended that Council:
• Note the actual expenditure incurred during the financial year 2025-26, as detailed in Appendix 1; and, • Approve the updated Capital Plan, as detailed within Appendix 3; a total budget for 2026-29 of £237.083m with an underlying borrowing requirement of £170.956m. ARGYLL AND BUTE COUNCIL COUNCIL FINANCIAL SERVICES 24 JUNE 2026
CAPITAL BUDGET MONITORING –YEAR ENDING 31 MARCH 2026
2.0INTRODUCTION
2.1This report provides a summary of the financial position and progress on delivery of the approved 2025-28 Capital Plan as at 31 March 2026. 2.2 It provides details of the actual expenditure incurred during the financial year 2025-26 and the forecast outturn across future years in comparison to the approved Capital Plan budget for each service.
Recommendations
3.1It is recommended that Council: • Note the actual expenditure incurred during the financial year 2025-26, as detailed in Appendix 1; and, • Approve the updated Capital Plan, as detailed within Appendix 3; a total budget for 2026-29 of £237.083m with an underlying borrowing requirement of £170.956m.
4.02025-26 BUDGET CHANGES
4.1The approved Capital Plan expenditure budget as at 31 December 2025, presented to Policy and Resources Committee at 19 February 2026 was £221.675m, representing the budget for projects in the 3-year capital plan and excluding their prior year spend of £93.242m.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.