Resolved
Decision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Report by , dated August 2026, submitted)
AI summaryBute and Cowal area planning group noted Transport Scotland's trunk road update, covering completed A83 works at Arrochar, upcoming A82 resurfacing, and the resumption of Rest and Be Thankful maintenance from 14 September 2026.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
Decision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Report by , dated August 2026, submitted)
TS Roads Update;
We are well through our cyclic operations such as grass cutting, sign cleaning, electrical & drainage works etc. with the weekly safety inspections still ongoing;
TS/BEAR Scotland have recently completed works;
• A83 - Re-surfacing works at Arrochar
• A83 - Westport VRS construction complete
Upcoming works planned for next 3 month period;
• A82 – Re-surfacing works both North & South of Arden Roundabout, South of Luss & North of Firkin Point
RaBT update;
After a planned pause in traffic management operations at the Rest and Be Thankful, we intend to resume essential maintenance works from 14 September 2026. Initial activities will focus on the lower slopes adjacent to the A83 Trunk Road, with subsequent works including channel maintenance, debris flow barrier maintenance, and westbound drainage improvements. These critical interventions are programmed to continue through to spring 2027, helping to maintain the resilience, safety, and reliability of this key transport corridor.
Embankment stabilisation works between Loch Restil & Butterbridge will continue until mid-September using temporary traffic signals. These works are to be completed and the TM removed before we continue with the planned maintenance works at the Rest & Be Thankful.
Other Points of Interest;
• A83 - The current road safety works at Cairndow are still on hold as we are still waiting for the energy company to provide final electrical connections. TS/BEAR staff continue to liaise with SSE to ensure connections are carried out as soon as practicable.
• A83/82 – Following the introduction of the 20mph speed limits, we are continuing to collect and analyse traffic speed data to assess compliance across the network. The recently implemented measures are being closely monitored, and this evidence-led approach will help determine whether any additional interventions are required to improve compliance and maximise the safety benefits of the scheme. Over the coming months, further speed surveys will be undertaken, with targeted measures identified and delivered where necessary.
• A82 - Initial monitoring has identified that vehicle speeds within Tarbet remain a concern. As a result, additional measures are currently being investigated to further encourage compliance and improve safety for residents, visitors, and road users. We are developing a package of further interventions, with implementation currently planned for Autumn 2026, subject to the necessary approvals and programming.
• A82 - Temporary Average Speed Cameras (TASC) are now in place on the A82 between Luss–Tarbet. These will likely be in place until the end of October.
• A82 - Loch Lomond Lay-bys/Rest Area signing strategy & Junctions Improvement scheme design is still ongoing with BEAR progressing designs for introduction of VAS signs at key junctions such as Duck Bay, Cameron House, Luss junctions.
• A82 - Loch Lomond Golf Club VRS design is still ongoing & construction is currently planned for Autumn of this year.
• A82 - The filter material renewal & drainage upgrade works at Arden RAB and will continue this financial year, involves using a recycling technique that cleans and reuses existing stone within the drainage system. This method eliminates the need for excavation and replacement with new materials, significantly reducing waste, conserving resources, and lowering the overall carbon footprint of the scheme.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Transport ScotlandReport | 68 KB | DownloadRead as text |
Follow Bute and Cowal Area Community Planning Group at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | Community planning partnership management committee meeting highlightsDecision The Bute and Cowal Area Community Planning Group noted the contents of the report. (Reference: Report by Par... | Noted | Open |
| 3 Nov 2026 | Argyll and bute improvement plan - priorities updateDecision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Verbal update f... | Noted | Open |
| 3 Nov 2026 | Heartstart Cowal and Cowal Peninsula Community First RespondersDecision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Verbal update f... | Noted | Open |
| 3 Nov 2026 | Police Scotland UpdateDecision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Report by Polic... | Noted | Open |
| 3 Nov 2026 | Scottish Fire and Rescue Service UpdateDecision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Report by Scott... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.