Resolved
Decision The Oban, Lorn and the Isles Area Community Planning Group noted the information provided. (Reference: Report by Transport Scotland, dated 12 August 2026, submitted)
AI summaryOban, Lorn and the Isles Area Community Planning Group noted Transport Scotland's update covering completed and upcoming trunk road works, with Rest and Be Thankful maintenance resuming in September 2026.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
Decision The Oban, Lorn and the Isles Area Community Planning Group noted the information provided. (Reference: Report by Transport Scotland, dated 12 August 2026, submitted)
Argyll & Bute Community Planning Partnership Oban, Lorn and the Isles Area Community Planning Group Partnership update Date: 12 August 2026
Transport Scotland update August 2026 Partner update
We are well through our cyclic operations such as grass cutting, sign cleaning, electrical & drainage works etc. with the weekly safety inspections still ongoing.
TS/BEAR Scotland have recently completed works:
• A85 – Lochawe Speed Management scheme has been completed, including installation of permanent traffic calming road markings to encourage speed compliance
Upcoming works planned over the following months:
• A85 – Road markings and stud work is continuing between Loch Awe & Oban • A85 – Resurfacing works planned at Connel, St Conans Kirk, Arrivain and West of Ross Bridge • A85 – Further ditching works between Perth & Oban • A85 – Look & feel landscape works planned for between Perth & Oban for autumn/winter of this year • A828 – Look & feel landscape works planned for between Connel & Ballachulish for autumn/winter of this year • A828 – Appin footway improvements
Rest and Be Thankful update:
After a planned pause in traffic management operations at the Rest and Be Thankful, we intend to resume essential maintenance works from 14 September 2026. Initial activities will focus on the lower slopes adjacent to the A83 Trunk Road, with subsequent works including channel maintenance, debris flow barrier maintenance, and westbound drainage improvements. These critical interventions are programmed to continue through to spring 2027, helping to maintain the resilience, safety, and reliability of this key transport corridor. Embankment stabilisation works between Loch Restil & Butterbridge will continue until mid-September using temporary traffic signals. These works are to be completed and the TM removed before we continue with the planned maintenance works at the Rest & Be Thankful.
Other Points of Interest:
A85 - The implementation of the 20mph zones at multiple locations across the network is now complete. The recently installed 20mph interventions are being monitored to ensure compliance & over the forthcoming months we will continue to collect and analyse speed data, providing further interventions where required. There will be further work to make these speed limits permanent if the speed data shows compliance with the speed parameters of the 20mph project.
A85 – between Tyndrum & Bridge of Awe – Temporary average speed cameras have now been installed on the A85 between Tyndrum and Dalmally and will remain in place until October. These measures are intended to improve safety for road users, particularly motorcyclists, along this section of the route.
A85 – Kilchurn Bridge closures – We are planning a series of overnight closures at Kilchurn Bridge over the River Orchy to facilitate the replacement of two covers located on the bridge centreline. The works will be completed over four nights, with the A85 remaining open during the day. We have worked closely with bus operators to minimise disruption to public transport, and further details will be communicated by the BEAR media team in advance of the works.
A828 – Ledaig – Works to stabilise the Benderloch rock face are progressing, with loose rock removal, rock anchor installation and protective netting currently underway. Completion is expected by September, although traffic management and overnight road closures will continue to impact the network. A final phase of works is also being developed by BEAR Scotland and Transport Scotland to provide a long- term solution for the remaining section of the slope.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Transport Scotland UpdateReport | 151 KB | DownloadRead as text |
Follow Oban Lorn & the Isles Area Community Planning Group at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Aug 2026 | Community focusDecision The Oban, Lorn and the Isles Area Community Planning Group noted the information provided. (Reference: Prese... | Noted | Open |
| 12 Aug 2026 | Argyll and bute improvement plan - priorities updateDecision The Oban, Lorn and the Isles Area Community Planning Group noted the information provided. (Reference: Prese... | Noted | Open |
| 12 Aug 2026 | Community planning partnership management committee meeting highlightsDecision The Oban, Lorn and the Isles Area Community Planning Group noted the information provided. (Reference: Repor... | Noted | Open |
| 12 Aug 2026 | Police Scotland UpdateDecision The Oban, Lorn and the Isles Area Community Planning Group noted the information provided. (Reference: Repor... | Noted | Open |
| 12 Aug 2026 | Scottish Fire and Rescue UpdateDecision The Oban, Lorn and the Isles Area Community Planning Group noted the information provided. (Reference: Repor... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.