BUDGET OUTLOOK AND MEDIUM-TERM FINANCIAL PLANNING: 2027/28 TO 2029/30
NotedFinance2 papers
AI summaryArgyll and Bute HSCP Finance and Policy Committee noted a forecast £34m budget gap for 2027/28, including £18m linked to the NHS Greater Glasgow and Clyde service level agreement, and endorsed the budget planning timeline.
Written from the decision and the officer reportPDF Pro
OutcomeNotedBudget outlook and timeline endorsed
Money£34m forecast gap2027/28 budget gap, includes £18m SLA
What happens nextBudget approval March 2027By Integration Joint Board
Who it affectsHealth and social care servicesAcross Argyll and Bute
What was decided
The committee noted the forecast budget gap of £34m for 2027/28, including £18m relating to the service level agreement with NHS Greater Glasgow and Clyde. Report P70
The committee endorsed the timeline and process for developing the 2027/28 to 2029/30 budget and noted that savings planning continues in partnership with the Council and NHS Highland. Report P73, P74
The committee noted that expenditure control measures continue to be implemented, including vacancy monitoring, agency staffing reductions, and contract reviews. Report P26
Why
The HSCP is not operating on a financially sustainable basis and cannot finance current spend levels, particularly within health services, with the situation worsened by escalating SLA costs and a reduced Scottish Government baseline funding uplift from 3% to 2%. Report 1.2, P22, P52
The NHS outlook includes cost pressures such as £18.6m in charges from Glasgow for acute services, an £8.5m underlying deficit, and limited scope for further operational savings, requiring service change with proportionate impact assessments and consultation. Report 1.3, P52, P60
What happens next
Development of options and potential impacts for Social Work savings will take place in October to November 2026, with NHS savings proposals developed in October to November 2026. Report P73
Public engagement on the budget will run from November to December 2026, with budget proposals and integrated impact assessments finalised between January and February 2027. Report P74
The Integration Joint Board is expected to approve the 2027/28 budget in March 2027, with update reports provided to each Finance and Policy Committee meeting. Report P74, P75
The money
£34m Forecast total budget gap for 2027/28 in mid-range scenario Report P70
£18m Portion of 2027/28 gap relating to SLA with NHS GG&C
£11.7m Estimated NHS budget gap excluding SLA pressures for 2027/28 Report P58
£2.4m NHS reserve used to support 2026/27 NHS revenue budget Report P25
£500k Council allocation to support transformation projects Report P85
Options considered
Chosen: Endorse the budget outlook, timeline and process. Committee noted the risk and uncertainty and endorsed the approach to continue developing savings in partnership with the Council and NHS Highland Report P73
Chosen: Limit public engagement for 2027/28 budget process. Extensive engagement took place recently for 2026/27; in-person events will focus on actual proposals rather than the generality of the budget Report P122
Implications
Legal: The Integration Joint Board has a legal responsibility to set a balanced budget aligned to delivery of the Joint Strategic Plan. Report 5.1, P107
Equalities: Some proposals to address the estimated budget gap will require integrated impact assessments and can be expected to have adverse impact on those with protected characteristics. Report 8.1, P114
Risk: SLA costs have escalated to a strategic risk level; services in Argyll and Bute cost well in excess of baseline health funding, and the HSCP may be required to manage down local services to compensate for increased acute care charges. Report 10.1, P118, 1.3
Staffing: The financial plan requires a reduction in workforce numbers; the HSCP aims to reduce vacancies and reliance on agency and locum staff. Report P100
Other: Further efficiency and cost savings are required; few opportunities remain for housekeeping or operational savings, and most further savings require service change with consultation. Report 1.3, P43
Who and where
People receiving health and social care services in Argyll and Bute Report 1.3, P43
Older people and adults with lifelong conditions (learning disability, physical disability, mental health) Report P40, P45
Children and families receiving social work services Report P40
Third sector organisations funded by the HSCP Report P33, P40
Care at home providers and their staff Report P34, P45
Unpaid carers in the community Report 7.2, P111
HSCP workforce Report P100
Timeline
August 2026: Initial consideration of 2027/28 budget by Finance and Policy Committee and Senior Leadership Team Report P73
September 2026: Initial report on the SLA to be considered by the Integration Joint Board Report P73
October to November 2026: Development of options and potential impacts for Social Work and NHS savings proposals Report P73
November 2026: Consideration of initial options by Senior Leadership Team, Finance and Policy Committee and Integration Joint Board Report P73
November to December 2026: Public engagement period on budget proposals Report P74
December 2026: Scottish Government expected to publish its budget and public sector reform agenda Report 1.1
January to February 2027: Finalisation of budget proposals and integrated impact assessments Report P74
March 2027: Approval of 2027/28 budget by the Integration Joint Board Report 1.1, P74
Plain English for the jargon
HSCP: Health and Social Care Partnership, the integrated body responsible for planning and delivering health and social care services in Argyll and Bute
IJB: Integration Joint Board, the body that governs the HSCP and is responsible for approving its budget
SLA: Service Level Agreement, in this case the contract with NHS Greater Glasgow and Clyde for acute hospital services provided to Argyll and Bute residents
NRAC: NHS Resource Allocation Committee formula, used to distribute NHS funding across Scotland based on population needs
JSP: Joint Strategic Plan, the HSCP's planning document setting out strategic priorities for health and social care
NRAC: National Resource Allocation Committee, determines how NHS funding is distributed to health boards
CPI: Consumer Prices Index, a measure of inflation
RPI: Retail Prices Index, another measure of inflation
PFI: Private Finance Initiative, a method of funding public infrastructure projects
NSD: National Services Division, a part of NHS National Services Scotland
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
Decision The Finance and Policy Committee – 1. considered the budget outlook for 2027/28 to 2029/30 and noted the risk and uncertainty regarding cost and funding assumptions; 2. noted the forecast budget gap of £34m for 2027/28 including £18m relating to the SLA with NHS GG&C; 3. noted that work on the savings plan and approach to managing the NHS deficit was continuing in partnership with the Council and NHS Highland; 4. considered the strategic implications of the budget gap outlined in the submitted report; 5. endorsed the timeline and process outlined in the submitted report; and 6. noted expenditure control measures continued to be implemented. (Reference: Report by Head of Finance dated 18 August 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Argyll and Bute HSCP Finance and Policy Committee
Executive summary
1.1This report provides an updated budget outlook for 2027/28 and the following two years. It takes into account recent Government policy documents and nationally utilised assumptions in respect of funding and inflation uplifts. It is anticipated that the Scottish Government will publish its budget in December 2026 and will have also set out its public sector reform agenda by then. The HSCP will be in a better position to refine its financial modelling, at that time, however this will be too late to put in place service change plans in time for budget approval by the IJB in March 2027.
1.2As has been highlighted in financial reporting documents and by the External Auditor, the HSCP is not operating on a financially sustainable basis and, as a result, it is now required to make significant cost reductions. It does not expect to be able to finance current levels of spend in future years, particularly within health services. The situation has worsened as SLA costs have escalated and the Scottish Government have reduced their baseline funding uplift from 3% to 2%. The financial plan and savings programme will continue to evolve, as funding allocations are confirmed by Government and partners.
1.3The outlook aims to provide a framework for the development of the 2027/28 budget whilst placing it in a medium-term context. While the Scottish Government has recently published strategic direction / policy documents relating to Health and Social Care, funding levels have not been increased and there is no clear
1 commitment to fund increasing demand and costs within the system. At a high level there is still a commitment to protect and invest in Health and Social Care, however, the previous commitment to real terms funding increases is not feeding into formula funding allocations when the impact of inflation and increasing demand is taken into account.
1.3The situation across the Health and Social Care remains unsustainable with many IJBs and Health Boards reporting deficits. The financial context continues to worsen, and further efficiency and cost savings are required. Few opportunities remain for housekeeping or operational savings, and most further savings require service change along with proportionate impact assessments and consultation. Urgent work is required to develop and consult / engage on firm savings proposals to seek to balance the budget with the expectation that enhanced financial control measures and additional funding (NHS) will also be required. The scale of the NHS budget gap is such that it is now the case services to Argyll & Bute residents are costing well in excess of formula funding and the increase in costs for acute care presents a strategic risk to local service delivery. Appendix 1 provides recent summary financial data for HSCPs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Argyll and Bute HSCP Finance and Policy Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Unaudited annual accounts 2025/26Decision The Finance and Policy Committee – 1. reviewed the Unaudited Annual Accounts noting that these had been appr...
Infrastructure update - july 2026Decision The Finance and Policy Committee – 1. noted the contents of the submitted report; 2. noted the progress sinc...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.