Argyll and Bute HSCP Finance and Policy Committee, Tuesday 18 August 2026 at 10.30am

BUDGET OUTLOOK AND MEDIUM-TERM FINANCIAL PLANNING: 2027/28 TO 2029/30

Noted Finance 2 papers

AI summaryArgyll and Bute HSCP Finance and Policy Committee noted a forecast £34m budget gap for 2027/28, including £18m linked to the NHS Greater Glasgow and Clyde service level agreement, and endorsed the budget planning timeline.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBudget outlook and timeline endorsed
Money£34m forecast gap2027/28 budget gap, includes £18m SLA
What happens nextBudget approval March 2027By Integration Joint Board
Who it affectsHealth and social care servicesAcross Argyll and Bute

What was decided

The committee noted the forecast budget gap of £34m for 2027/28, including £18m relating to the service level agreement with NHS Greater Glasgow and Clyde. Report P70

The committee endorsed the timeline and process for developing the 2027/28 to 2029/30 budget and noted that savings planning continues in partnership with the Council and NHS Highland. Report P73, P74

The committee noted that expenditure control measures continue to be implemented, including vacancy monitoring, agency staffing reductions, and contract reviews. Report P26

Why

The HSCP is not operating on a financially sustainable basis and cannot finance current spend levels, particularly within health services, with the situation worsened by escalating SLA costs and a reduced Scottish Government baseline funding uplift from 3% to 2%. Report 1.2, P22, P52

The NHS outlook includes cost pressures such as £18.6m in charges from Glasgow for acute services, an £8.5m underlying deficit, and limited scope for further operational savings, requiring service change with proportionate impact assessments and consultation. Report 1.3, P52, P60

What happens next

Development of options and potential impacts for Social Work savings will take place in October to November 2026, with NHS savings proposals developed in October to November 2026. Report P73

Public engagement on the budget will run from November to December 2026, with budget proposals and integrated impact assessments finalised between January and February 2027. Report P74

The Integration Joint Board is expected to approve the 2027/28 budget in March 2027, with update reports provided to each Finance and Policy Committee meeting. Report P74, P75

The money

  • £34m Forecast total budget gap for 2027/28 in mid-range scenario Report P70
  • £18m Portion of 2027/28 gap relating to SLA with NHS GG&C
  • £11.7m Estimated NHS budget gap excluding SLA pressures for 2027/28 Report P58
  • £2.4m NHS reserve used to support 2026/27 NHS revenue budget Report P25
  • £500k Council allocation to support transformation projects Report P85

Options considered

  • Chosen: Endorse the budget outlook, timeline and process. Committee noted the risk and uncertainty and endorsed the approach to continue developing savings in partnership with the Council and NHS Highland Report P73
  • Chosen: Limit public engagement for 2027/28 budget process. Extensive engagement took place recently for 2026/27; in-person events will focus on actual proposals rather than the generality of the budget Report P122

Implications

  • Legal: The Integration Joint Board has a legal responsibility to set a balanced budget aligned to delivery of the Joint Strategic Plan. Report 5.1, P107
  • Equalities: Some proposals to address the estimated budget gap will require integrated impact assessments and can be expected to have adverse impact on those with protected characteristics. Report 8.1, P114
  • Risk: SLA costs have escalated to a strategic risk level; services in Argyll and Bute cost well in excess of baseline health funding, and the HSCP may be required to manage down local services to compensate for increased acute care charges. Report 10.1, P118, 1.3
  • Staffing: The financial plan requires a reduction in workforce numbers; the HSCP aims to reduce vacancies and reliance on agency and locum staff. Report P100
  • Other: Further efficiency and cost savings are required; few opportunities remain for housekeeping or operational savings, and most further savings require service change with consultation. Report 1.3, P43

Who and where

  • People receiving health and social care services in Argyll and Bute Report 1.3, P43
  • Older people and adults with lifelong conditions (learning disability, physical disability, mental health) Report P40, P45
  • Children and families receiving social work services Report P40
  • Third sector organisations funded by the HSCP Report P33, P40
  • Care at home providers and their staff Report P34, P45
  • Unpaid carers in the community Report 7.2, P111
  • HSCP workforce Report P100

Timeline

  • August 2026: Initial consideration of 2027/28 budget by Finance and Policy Committee and Senior Leadership Team Report P73
  • September 2026: Initial report on the SLA to be considered by the Integration Joint Board Report P73
  • October to November 2026: Development of options and potential impacts for Social Work and NHS savings proposals Report P73
  • November 2026: Consideration of initial options by Senior Leadership Team, Finance and Policy Committee and Integration Joint Board Report P73
  • November to December 2026: Public engagement period on budget proposals Report P74
  • December 2026: Scottish Government expected to publish its budget and public sector reform agenda Report 1.1
  • January to February 2027: Finalisation of budget proposals and integrated impact assessments Report P74
  • March 2027: Approval of 2027/28 budget by the Integration Joint Board Report 1.1, P74

Plain English for the jargon

  • HSCP: Health and Social Care Partnership, the integrated body responsible for planning and delivering health and social care services in Argyll and Bute
  • IJB: Integration Joint Board, the body that governs the HSCP and is responsible for approving its budget
  • SLA: Service Level Agreement, in this case the contract with NHS Greater Glasgow and Clyde for acute hospital services provided to Argyll and Bute residents
  • NRAC: NHS Resource Allocation Committee formula, used to distribute NHS funding across Scotland based on population needs
  • JSP: Joint Strategic Plan, the HSCP's planning document setting out strategic priorities for health and social care
  • NRAC: National Resource Allocation Committee, determines how NHS funding is distributed to health boards
  • CPI: Consumer Prices Index, a measure of inflation
  • RPI: Retail Prices Index, another measure of inflation
  • PFI: Private Finance Initiative, a method of funding public infrastructure projects
  • NSD: National Services Division, a part of NHS National Services Scotland
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

Decision The Finance and Policy Committee – 1. considered the budget outlook for 2027/28 to 2029/30 and noted the risk and uncertainty regarding cost and funding assumptions; 2. noted the forecast budget gap of £34m for 2027/28 including £18m relating to the SLA with NHS GG&C; 3. noted that work on the savings plan and approach to managing the NHS deficit was continuing in partnership with the Council and NHS Highland; 4. considered the strategic implications of the budget gap outlined in the submitted report; 5. endorsed the timeline and process outlined in the submitted report; and 6. noted expenditure control measures continued to be implemented. (Reference: Report by Head of Finance dated 18 August 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Argyll and Bute HSCP Finance and Policy Committee

Executive summary

1.1This report provides an updated budget outlook for 2027/28 and the following two years. It takes into account recent Government policy documents and nationally utilised assumptions in respect of funding and inflation uplifts. It is anticipated that the Scottish Government will publish its budget in December 2026 and will have also set out its public sector reform agenda by then. The HSCP will be in a better position to refine its financial modelling, at that time, however this will be too late to put in place service change plans in time for budget approval by the IJB in March 2027.

1.2As has been highlighted in financial reporting documents and by the External Auditor, the HSCP is not operating on a financially sustainable basis and, as a result, it is now required to make significant cost reductions. It does not expect to be able to finance current levels of spend in future years, particularly within health services. The situation has worsened as SLA costs have escalated and the Scottish Government have reduced their baseline funding uplift from 3% to 2%. The financial plan and savings programme will continue to evolve, as funding allocations are confirmed by Government and partners.

1.3The outlook aims to provide a framework for the development of the 2027/28 budget whilst placing it in a medium-term context. While the Scottish Government has recently published strategic direction / policy documents relating to Health and Social Care, funding levels have not been increased and there is no clear

1 commitment to fund increasing demand and costs within the system. At a high level there is still a commitment to protect and invest in Health and Social Care, however, the previous commitment to real terms funding increases is not feeding into formula funding allocations when the impact of inflation and increasing demand is taken into account.

1.3The situation across the Health and Social Care remains unsustainable with many IJBs and Health Boards reporting deficits. The financial context continues to worsen, and further efficiency and cost savings are required. Few opportunities remain for housekeeping or operational savings, and most further savings require service change along with proportionate impact assessments and consultation. Urgent work is required to develop and consult / engage on firm savings proposals to seek to balance the budget with the expectation that enhanced financial control measures and additional funding (NHS) will also be required. The scale of the NHS budget gap is such that it is now the case services to Argyll & Bute residents are costing well in excess of formula funding and the increase in costs for acute care presents a strategic risk to local service delivery. Appendix 1 provides recent summary financial data for HSCPs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
IJB Financial Position.26.27Appendix 1 453 KB Download
PDF
BUDGET OUTLOOK AND MEDIUM-TERM FINANCIAL PLANNING: 2027/28 TO 2029/30Report 581 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 7 attended
DM
Councillor Dougie McFadzeanChair, apologies
GB
Graham BellChair, present
KL
Karen LeachMember, present
KM
Kenny MathesonMember, present
GM
Councillor Gary MulvaneyMember, present
FT
Fiona ThomsonMember, present
HM
Hazel MacInnesSecretary, expected

On this subject at Argyll and Bute

Search all
  1. BUDGET OUTLOOK AND MEDIUM-TERM FINANCIAL PLANNING: 2027/28 TO 2029/30This decision
  2. Budget Outlook and Medium-Term Financial Planning: 2027/28 to 2029/30Noted
  3. Budget outlook 2027-28 to 2031-32Noted
  4. Budget outlook 2027-28 to 2031-32Noted
  5. Budget outlook 2026-27 to 2030-31Noted
  6. Budget outlook 2026-27 to 2030-31Noted

More from Argyll and Bute Argyll and Bute HSCP Finance and Policy Committee

All decisions
MeetingDecisionOutcome
18 Aug 2026 Finance and policy committee annual report - 2025/26Decision The Finance and Policy Committee – 1. approved the draft Committee Annual Report for 2025/26; and 2. request... Approved Open
18 Aug 2026 Unaudited annual accounts 2025/26Decision The Finance and Policy Committee – 1. reviewed the Unaudited Annual Accounts noting that these had been appr... Approved Open
18 Aug 2026 Budget monitoring - 3 months to 30 june 2026Decision The Finance and Policy Committee – 1. noted the HSCP was reporting a small year to date overspend of £0.7m; ... Noted Open
18 Aug 2026 Financial risks 2026-27Decision The Finance and Policy Committee – 1. considered the 2026/27 financial risks identified and noted the mitiga... Noted Open
18 Aug 2026 Infrastructure update - july 2026Decision The Finance and Policy Committee – 1. noted the contents of the submitted report; 2. noted the progress sinc... Noted Open