Argyll and Bute Council
Argyll and Bute HSCP Finance and Policy Committee, Tuesday 18 August 2026 at 10.30am

INFRASTRUCTURE UPDATE - JULY 2026

Noted Finance 1 paper

AI summaryArgyll and Bute HSCP committee notes infrastructure risk remains Very High, reviews progress on hospital fire safety, care home and key worker housing projects, and asks NHS Highland and the council to log infrastructure risks on their Strategic Risk Registers.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted
MoneyHSCP reserves depleted£900k Lorn and Islands fire works and £1,200k Islay fire works in 26/27
What happens nextPartners to log infrastructure riskScottish Government new capital project assessments due September 2026
Who it affectsHSCP staff, patients, residentsHospital, care home and key worker housing users across Argyll and Bute

What was decided

The committee noted the contents of the submitted report and the progress made since infrastructure risk was raised to Very High on the Strategic Risk Register. Report P7

The committee noted that actions to mitigate risk and make improvements are ongoing but considerable challenges remain, and the Very High risk rating is not being downgraded at this time. Report 10.1, P49

The committee agreed to recommend that NHS Highland and Argyll and Bute Council ensure infrastructure risks are captured on their Strategic Risk Registers. Report 2.1, P7

Why

HSCP services depend on building infrastructure owned by NHS Highland and Argyll and Bute Council, and significant backlog maintenance and equipment replacement needs have been identified against insufficient capital resource. Report 1.1, 1.2, P4

Several key projects, including Cowal Community Hospital redesign, Islay roof replacement and care home upgrades, are at risk because of funding constraints, scope reductions or being at an early stage. Report 1.4

Regulatory bodies are paying increased attention to infrastructure quality, particularly in care home inspections and fire service inspections of hospitals, and the age and condition of the estate continues to deteriorate. Report 3.1

What happens next

NHS Highland and Argyll and Bute Council are to be asked to ensure infrastructure risks are captured on their Strategic Risk Registers. Report 2.1

Initial assessments of new capital projects are expected to be considered by Scottish Government in September 2026, with successful projects not expected to start development until 2031 at the earliest. Report P14

A detailed decarbonisation plan for Raigmore and Lorn and Islands Hospital is due to be completed in March 2027 to inform future sustainability capital bids. Report P26

The money

  • £900K in 26/27 FY Lorn and Islands Hospital Fire Improvement Works, phases 1 and 2 of 8 Report P34
  • £1,200K in 26/27 FY Islay Hospital Fire Improvement Works Report P34
  • £250K secured this FY Cowal Community Hospital Fire Improvement Works design Report P35
  • £220k Birch Drive Islay key worker housing project, with £145k NHS contribution Report P35
  • £291k Struan Lodge rewire stop gap measures, from A and B Capital 24 month allocation Report P36
  • £200k NHS Highland formula capital allocation Campbeltown Hospital generator replacement and LV panel upgrades Report P36
  • £250k NHS Highland formula capital allocation 26/27 FY Cowal Hospital lift refurbishment Report P37
  • £73K from A&BC Capital allocation Thomson Court temporary generator connection point Report P37
  • £31K from A&BC Capital allocation Ardfenaig Care Home temporary generator connection point Report P37
  • £33K from A&BC Capital allocation Eadar Glinn Care Home temporary generator connection point Report P38
  • £198K from A&BC Capital allocation Eadar Glinn Care Home shower and window replacements Report P38
  • £803k from Argyll and Bute Council Capital allocation Kintyre Care Centre electrical upgrades, decorations, toilet refurbishment, window replacement Report P38
  • £259K from SG Sustainability Directorate Net Zero LED Lighting improvements across A and B NHS properties Report P39
  • £250K from SG Sustainability Directorate Net Zero Decarbonisation Plan for Lorn and Islands Hospital Report P39
  • £402k in 25/26 FY from S.Gov ADEL fund Former Argyll and Bute Hospital disposal initial phase Report P39
  • £407K in 26/27 Financial Year Mid Argyll Community Hospital X-Ray equipment replacement Report P39
  • £528k Campbeltown X-Ray replacement and re-modelling, completed Report P41
  • £2.4M from A&B Capital, Strategic Housing Fund and HSCP and Council reserves Tigh a Rudha care home refurbishment, completed Report P41
  • £465k Coll Nurses House, with £365k of HSCP reserves and £100k Strategic Housing Fund, completed Report P41
  • £250k NHS Highland formula capital allocation LIH Hospital Generator replacement, completed Report P41
  • £625k per year Estimated NHS Highland share of approximately £20M per year Scottish sustainability funding for FY 26/27 and 27/28 Report P25
  • £428k in 24/25 to £382k per annum in 27/28 HSCP capital budgets for care homes, children's homes, learning resource centres and offices Report P16

Options considered

  • Rejected: Downgrade infrastructure risk from Very High on Strategic Risk Register. Progress has been made but infrastructure continues to age and deteriorate and regulatory attention is increasing, so the risk is not judged to have reduced significantly enough Report 3.1, P49, 10.1

Implications

  • Financial: Insufficient funding to address backlog maintenance; HSCP reserves used to joint fund projects are now depleted and no further substantial projects can be facilitated this way. Report 6.1, P42
  • Financial: HSCP care home capital budgets reduced from £428k in 24/25 to £382k per annum in 27/28, with preventative maintenance funding increased to ease the burden. Report P16
  • Legal: Statutory enforcement agency warning notices and threat of enforcement continue, with preventable infrastructure problems cited as reasons for issuing notices; risk of enforcement action on Cowal Community Hospital if no action taken. Report P48, P35
  • Risk: Infrastructure risk remains classified as Very High on the HSCP Strategic Risk Register, with no change recommended at this time. Report 3.3, P44, 10.1
  • Risk: Scale of backlog maintenance means a building failure causing temporary or medium term closure is still increasing. Report P48
  • Staffing: Housing remains a significant barrier to HSCP recruitment; a temporary part time Housing Improvement Officer has been appointed and rental charges for HSCP owned properties are being reviewed. Report P20
  • Climate: 17 zero emission vehicles and 12 hybrid vehicles have been procured, reducing average fleet emissions of replaced vehicles from 101g/km to 62g/km, and EV charging infrastructure is being expanded. Report P27
  • Other: Cyber security risks are linked to infrastructure investment and are considered through the Digital Health and Care Programme Board. Report 9.1

Who and where

  • HSCP staff, patients and service users across Argyll and Bute Report 1.1, P10
  • Care home residents and staff at Tigh a Rudha, Kintyre Care Centre, Eadar Glinn, Ardfenaig and Thomson Court Report P36, P37, P38, P41
  • NHS Highland as owner and maintainer of hospital infrastructure Report 1.1, P11
  • Argyll and Bute Council as owner and maintainer of care home and other HSCP buildings Report 1.1, P15
  • Key workers and their families on Tiree, Coll, Islay and in Oban Report P21, P23
  • Hub North as facilitator of the Argyll and Bute place board covering Lochgilphead, Rothesay and Dunoon Report P10

Timeline

  • 2024: Audit and Risk committee decision to increase infrastructure risk to Very High on the Strategic Risk Register, reported to this committee in June 2024 Report 3.1
  • November 2025: Previous infrastructure update to this committee Report P2
  • 17th November 2025: Coll GP House anticipated completion Report P41
  • 18 August 2026: This report to the Finance and Policy Committee Report P76
  • September 2026: Initial assessments of new capital projects to be considered by Scottish Government Report P14
  • 26/27 FY: Funding in place for Lorn and Islands and Islay fire improvement works, Cowal lift refurbishment and Mid Argyll X-Ray replacement Report P34, P37, P39
  • March 2027: Completion due of detailed decarbonisation plan for Raigmore and Lorn and Islands Hospital Report P26
  • 2031 at the earliest: Successful new capital projects not expected to start development Report P14

Plain English for the jargon

  • HSCP: Health and Social Care Partnership, the joint body for Argyll and Bute covering NHS and council social care services
  • BCIP: Business Continuity Investment Plan, the Scottish Government prioritised maintenance only investment plan for Health Boards
  • ADEL fund: Scottish Government fund being applied for to support further phases of the former Argyll and Bute Hospital disposal
  • Our Modern Workspace (OMW): Argyll and Bute Council estates rationalisation project, in place since 2021
  • EPAG: Equipment Advisory Group, the NHS Highland group that approved formula capital spending on equipment purchase
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

Decision The Finance and Policy Committee – 1. noted the contents of the submitted report; 2. noted the progress since the increase of Infrastructure Risk to Very High on the HSCP Strategic Risk Register in June 2024; 3. noted that actions are on-going to mitigate risk and make improvements where possible but considerable challenges remain; and 4. agreed to recommend that NHS Highland and Argyll and Bute Council ensure infrastructure risks are captured on their Strategic Risk Registers. (Reference: Report by Head of Finance and Senior Manager Strategic Estates Development and Sustainability dated 18 August 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Argyll and Bute HSCP Finance and Policy Committee

Executive summary

1.1The delivery of HSCP services is reliant on the physical building infrastructure from which it operates. The infrastructure is owned by both partners (NHS Highland and Argyll & Bute Council) who are also responsible for its maintenance. The purpose of this report is to:

• Update the committee with progress on key projects since the last update in November 2025; and • Update the Committee on progress in managing infrastructure risk on the Strategic Risk Register classed as ‘Very High’.

1.2Governance arrangements relating to infrastructure are complex, The Infrastructure Transformation Board was established in 2023 to strengthen HSCP governance arrangements, the board continues to meet quarterly to update and discuss priorities. However, capital spend is not delegated to the HSCP, separate and very different governance arrangements exist within the Council and NHS Highland. The HSCP is represented at the relevant groups within both partners and relationships remain positive. The overall position is that significant backlog maintenance requirements and equipment replacement needs have been identified and there is insufficient capital resource to address these (nationally and locally). The outcome of this is that the risk of failures and/or loss of capacity due to failure to meet regulatory standards is increasing.

1 1.3 Delivery continues within a constrained capital environment, with investment focused primarily on statutory compliance, backlog maintenance and service resilience. Nationally, the Scottish Government’s Strategic Assessment approach requires NHS Boards to demonstrate long-term infrastructure alignment prior to project approval, reinforcing prioritisation and limiting progression of non- essential schemes.

1.4Progress is evident in funded compliance projects, including fire safety works at Lorn & Islands Hospital and Islay Hospital. However, several projects - the Cowal Community Hospital redesign, Islay roof replacement, and care home infrastructure upgrades - remain at risk due to funding constraints, scope reductions or are still at an early-stage of development. The overall programme reflects a shift toward risk-based investment, with very little capacity for major transformation projects without additional capital support.

Recommendations

2.1The Finance and Policy Committee are Recommended to:

• Note the contents of this report; • Note the progress since the increase of Infrastructure Risk to Very High on the Strategic Risk Register in November 2024; and • Note that actions are on-going to mitigate risk and make improvements where possible but there remain considerable long-term challenges to risk reduction. • Recommend that NHS Highland and Argyll & Bute Council ensure infrastructure risks are captured on their Strategic Risk Registers.

3. DETAIL OF REPORT

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
INFRASTRUCTURE UPDATE: JULY 2026Report 324 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 7 attended
DM
Councillor Dougie McFadzeanChair, apologies
GB
Graham BellChair, present
KL
Karen LeachMember, present
KM
Kenny MathesonMember, present
GM
Councillor Gary MulvaneyMember, present
FT
Fiona ThomsonMember, present
HM
Hazel MacInnesSecretary, expected

More from Argyll and Bute Argyll and Bute HSCP Finance and Policy Committee

All decisions
MeetingDecisionOutcome
18 Aug 2026 Finance and policy committee annual report - 2025/26Decision The Finance and Policy Committee – 1. approved the draft Committee Annual Report for 2025/26; and 2. request... Approved Open
18 Aug 2026 Unaudited annual accounts 2025/26Decision The Finance and Policy Committee – 1. reviewed the Unaudited Annual Accounts noting that these had been appr... Approved Open
18 Aug 2026 Budget monitoring - 3 months to 30 june 2026Decision The Finance and Policy Committee – 1. noted the HSCP was reporting a small year to date overspend of £0.7m; ... Noted Open
18 Aug 2026 Budget outlook and medium-term financial planning: 2027/28 to 2029/30Decision The Finance and Policy Committee – 1. considered the budget outlook for 2027/28 to 2029/30 and noted the ris... Noted Open
18 Aug 2026 Financial risks 2026-27Decision The Finance and Policy Committee – 1. considered the 2026/27 financial risks identified and noted the mitiga... Noted Open