AI summaryArgyll and Bute HSCP committee notes infrastructure risk remains Very High, reviews progress on hospital fire safety, care home and key worker housing projects, and asks NHS Highland and the council to log infrastructure risks on their Strategic Risk Registers.
Written from the decision and the officer reportPDF Pro
OutcomeNoted
MoneyHSCP reserves depleted£900k Lorn and Islands fire works and £1,200k Islay fire works in 26/27
What happens nextPartners to log infrastructure riskScottish Government new capital project assessments due September 2026
Who it affectsHSCP staff, patients, residentsHospital, care home and key worker housing users across Argyll and Bute
What was decided
The committee noted the contents of the submitted report and the progress made since infrastructure risk was raised to Very High on the Strategic Risk Register. Report P7
The committee noted that actions to mitigate risk and make improvements are ongoing but considerable challenges remain, and the Very High risk rating is not being downgraded at this time. Report 10.1, P49
The committee agreed to recommend that NHS Highland and Argyll and Bute Council ensure infrastructure risks are captured on their Strategic Risk Registers. Report 2.1, P7
Why
HSCP services depend on building infrastructure owned by NHS Highland and Argyll and Bute Council, and significant backlog maintenance and equipment replacement needs have been identified against insufficient capital resource. Report 1.1, 1.2, P4
Several key projects, including Cowal Community Hospital redesign, Islay roof replacement and care home upgrades, are at risk because of funding constraints, scope reductions or being at an early stage. Report 1.4
Regulatory bodies are paying increased attention to infrastructure quality, particularly in care home inspections and fire service inspections of hospitals, and the age and condition of the estate continues to deteriorate. Report 3.1
What happens next
NHS Highland and Argyll and Bute Council are to be asked to ensure infrastructure risks are captured on their Strategic Risk Registers. Report 2.1
Initial assessments of new capital projects are expected to be considered by Scottish Government in September 2026, with successful projects not expected to start development until 2031 at the earliest. Report P14
A detailed decarbonisation plan for Raigmore and Lorn and Islands Hospital is due to be completed in March 2027 to inform future sustainability capital bids. Report P26
The money
£900K in 26/27 FY Lorn and Islands Hospital Fire Improvement Works, phases 1 and 2 of 8 Report P34
£1,200K in 26/27 FY Islay Hospital Fire Improvement Works Report P34
£250K secured this FY Cowal Community Hospital Fire Improvement Works design Report P35
£291k Struan Lodge rewire stop gap measures, from A and B Capital 24 month allocation Report P36
£200k NHS Highland formula capital allocation Campbeltown Hospital generator replacement and LV panel upgrades Report P36
£250k NHS Highland formula capital allocation 26/27 FY Cowal Hospital lift refurbishment Report P37
£73K from A&BC Capital allocation Thomson Court temporary generator connection point Report P37
£31K from A&BC Capital allocation Ardfenaig Care Home temporary generator connection point Report P37
£33K from A&BC Capital allocation Eadar Glinn Care Home temporary generator connection point Report P38
£198K from A&BC Capital allocation Eadar Glinn Care Home shower and window replacements Report P38
£803k from Argyll and Bute Council Capital allocation Kintyre Care Centre electrical upgrades, decorations, toilet refurbishment, window replacement Report P38
£259K from SG Sustainability Directorate Net Zero LED Lighting improvements across A and B NHS properties Report P39
£250K from SG Sustainability Directorate Net Zero Decarbonisation Plan for Lorn and Islands Hospital Report P39
£402k in 25/26 FY from S.Gov ADEL fund Former Argyll and Bute Hospital disposal initial phase Report P39
£407K in 26/27 Financial Year Mid Argyll Community Hospital X-Ray equipment replacement Report P39
£528k Campbeltown X-Ray replacement and re-modelling, completed Report P41
£2.4M from A&B Capital, Strategic Housing Fund and HSCP and Council reserves Tigh a Rudha care home refurbishment, completed Report P41
£465k Coll Nurses House, with £365k of HSCP reserves and £100k Strategic Housing Fund, completed Report P41
£250k NHS Highland formula capital allocation LIH Hospital Generator replacement, completed Report P41
£625k per year Estimated NHS Highland share of approximately £20M per year Scottish sustainability funding for FY 26/27 and 27/28 Report P25
£428k in 24/25 to £382k per annum in 27/28 HSCP capital budgets for care homes, children's homes, learning resource centres and offices Report P16
Options considered
Rejected: Downgrade infrastructure risk from Very High on Strategic Risk Register. Progress has been made but infrastructure continues to age and deteriorate and regulatory attention is increasing, so the risk is not judged to have reduced significantly enough Report 3.1, P49, 10.1
Implications
Financial: Insufficient funding to address backlog maintenance; HSCP reserves used to joint fund projects are now depleted and no further substantial projects can be facilitated this way. Report 6.1, P42
Financial: HSCP care home capital budgets reduced from £428k in 24/25 to £382k per annum in 27/28, with preventative maintenance funding increased to ease the burden. Report P16
Legal: Statutory enforcement agency warning notices and threat of enforcement continue, with preventable infrastructure problems cited as reasons for issuing notices; risk of enforcement action on Cowal Community Hospital if no action taken. Report P48, P35
Risk: Infrastructure risk remains classified as Very High on the HSCP Strategic Risk Register, with no change recommended at this time. Report 3.3, P44, 10.1
Risk: Scale of backlog maintenance means a building failure causing temporary or medium term closure is still increasing. Report P48
Staffing: Housing remains a significant barrier to HSCP recruitment; a temporary part time Housing Improvement Officer has been appointed and rental charges for HSCP owned properties are being reviewed. Report P20
Climate: 17 zero emission vehicles and 12 hybrid vehicles have been procured, reducing average fleet emissions of replaced vehicles from 101g/km to 62g/km, and EV charging infrastructure is being expanded. Report P27
Other: Cyber security risks are linked to infrastructure investment and are considered through the Digital Health and Care Programme Board. Report 9.1
Who and where
HSCP staff, patients and service users across Argyll and Bute Report 1.1, P10
Care home residents and staff at Tigh a Rudha, Kintyre Care Centre, Eadar Glinn, Ardfenaig and Thomson Court Report P36, P37, P38, P41
NHS Highland as owner and maintainer of hospital infrastructure Report 1.1, P11
Argyll and Bute Council as owner and maintainer of care home and other HSCP buildings Report 1.1, P15
Key workers and their families on Tiree, Coll, Islay and in Oban Report P21, P23
Hub North as facilitator of the Argyll and Bute place board covering Lochgilphead, Rothesay and Dunoon Report P10
Timeline
2024: Audit and Risk committee decision to increase infrastructure risk to Very High on the Strategic Risk Register, reported to this committee in June 2024 Report 3.1
November 2025: Previous infrastructure update to this committee Report P2
17th November 2025: Coll GP House anticipated completion Report P41
18 August 2026: This report to the Finance and Policy Committee Report P76
September 2026: Initial assessments of new capital projects to be considered by Scottish Government Report P14
26/27 FY: Funding in place for Lorn and Islands and Islay fire improvement works, Cowal lift refurbishment and Mid Argyll X-Ray replacement Report P34, P37, P39
March 2027: Completion due of detailed decarbonisation plan for Raigmore and Lorn and Islands Hospital Report P26
2031 at the earliest: Successful new capital projects not expected to start development Report P14
Plain English for the jargon
HSCP: Health and Social Care Partnership, the joint body for Argyll and Bute covering NHS and council social care services
BCIP: Business Continuity Investment Plan, the Scottish Government prioritised maintenance only investment plan for Health Boards
ADEL fund: Scottish Government fund being applied for to support further phases of the former Argyll and Bute Hospital disposal
Our Modern Workspace (OMW): Argyll and Bute Council estates rationalisation project, in place since 2021
EPAG: Equipment Advisory Group, the NHS Highland group that approved formula capital spending on equipment purchase
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
Decision The Finance and Policy Committee – 1. noted the contents of the submitted report; 2. noted the progress since the increase of Infrastructure Risk to Very High on the HSCP Strategic Risk Register in June 2024; 3. noted that actions are on-going to mitigate risk and make improvements where possible but considerable challenges remain; and 4. agreed to recommend that NHS Highland and Argyll and Bute Council ensure infrastructure risks are captured on their Strategic Risk Registers. (Reference: Report by Head of Finance and Senior Manager Strategic Estates Development and Sustainability dated 18 August 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Argyll and Bute HSCP Finance and Policy Committee
Executive summary
1.1The delivery of HSCP services is reliant on the physical building infrastructure from which it operates. The infrastructure is owned by both partners (NHS Highland and Argyll & Bute Council) who are also responsible for its maintenance. The purpose of this report is to:
• Update the committee with progress on key projects since the last update in November 2025; and • Update the Committee on progress in managing infrastructure risk on the Strategic Risk Register classed as ‘Very High’.
1.2Governance arrangements relating to infrastructure are complex, The Infrastructure Transformation Board was established in 2023 to strengthen HSCP governance arrangements, the board continues to meet quarterly to update and discuss priorities. However, capital spend is not delegated to the HSCP, separate and very different governance arrangements exist within the Council and NHS Highland. The HSCP is represented at the relevant groups within both partners and relationships remain positive. The overall position is that significant backlog maintenance requirements and equipment replacement needs have been identified and there is insufficient capital resource to address these (nationally and locally). The outcome of this is that the risk of failures and/or loss of capacity due to failure to meet regulatory standards is increasing.
1 1.3 Delivery continues within a constrained capital environment, with investment focused primarily on statutory compliance, backlog maintenance and service resilience. Nationally, the Scottish Government’s Strategic Assessment approach requires NHS Boards to demonstrate long-term infrastructure alignment prior to project approval, reinforcing prioritisation and limiting progression of non- essential schemes.
1.4Progress is evident in funded compliance projects, including fire safety works at Lorn & Islands Hospital and Islay Hospital. However, several projects - the Cowal Community Hospital redesign, Islay roof replacement, and care home infrastructure upgrades - remain at risk due to funding constraints, scope reductions or are still at an early-stage of development. The overall programme reflects a shift toward risk-based investment, with very little capacity for major transformation projects without additional capital support.
Recommendations
2.1The Finance and Policy Committee are Recommended to:
• Note the contents of this report; • Note the progress since the increase of Infrastructure Risk to Very High on the Strategic Risk Register in November 2024; and • Note that actions are on-going to mitigate risk and make improvements where possible but there remain considerable long-term challenges to risk reduction. • Recommend that NHS Highland and Argyll & Bute Council ensure infrastructure risks are captured on their Strategic Risk Registers.
3. DETAIL OF REPORT
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Argyll and Bute HSCP Finance and Policy Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Unaudited annual accounts 2025/26Decision The Finance and Policy Committee – 1. reviewed the Unaudited Annual Accounts noting that these had been appr...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.