Internal and External Audit Report Follow Up 2025-26

Decided Finance 1 paper

AI summaryThe Audit and Scrutiny Committee endorsed the audit report, which records satisfactory progress and tracks 26 actions due by 30 September 2025 and 44 due after. [D] [4.1] [P8] [P12]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedThe committee endorsed the report [D]
MoneyNot stated
What happens nextOpen audit actions continue [3.3] [4.1]Delayed and rescheduled items have revised dates [3.3]
Who it affectsNot stated

What was decided

The Audit and Scrutiny Committee endorsed the contents of the audit report. [D]

The endorsed report says satisfactory progress continues in implementing audit actions. [D] [4.1] Report 4.1

Why

The report separates actions due by and after 30 September 2025. [3.1] Report 3.1

It records 26 actions in the first group and 44 in the second. [P8] [P12] Report P8, P12

Appendix 1 shows visual progress, Appendix 2 covers delays, rescheduling and evidence, and the report calls progress satisfactory. [3.2] [3.3] [4.1] Report 3.2, 3.3, 4.1

What happens next

The rescheduled short term let action covers enforcement policies, procedures and system work by 31 Dec 2025. [P24] [P25] Report P24, P25

Adult Services will complete and report the ASP audit on a six monthly basis by 31 Dec 2025. [P28] [P29] Report P28, P29

Planning will complete its training schedule by 31 Mar 2026. [P22] [P23] Report P22, P23

Options considered

  • Chosen: Endorse the contents of the report. The report recommended endorsement. [2.1] Report 2.1

Implications

  • Financial: No financial implications were identified. [5.1] Report 5.1
  • Legal: No legal implications were identified. [5.1] Report 5.1
  • Risk: No risk implications were identified. [5.1] Report 5.1
  • Climate: No climate change implications were identified. [5.1] Report 5.1
  • Equalities: No equalities or protected characteristics implications were identified. [5.1] Report 5.1
  • Staffing: No human resources implications were identified. [5.1] Report 5.1
  • Other: No policy, customer service or Consumer Duty implications were identified. [5.1] Report 5.1
  • Other: No Fairer Scotland Duty, Island Communities or Children's Rights and Wellbeing implications were identified. [5.1] Report 5.1

Who and where

  • Internal Audit service teams with open actions [P8] [P12] Report P8, P12
  • External Audit, with Nil actions [P8] [P12] Report P8, P12
  • HSCP adult services [P8] Report P8
  • HSCP finance and transformation services [P8] Report P8
  • HSCP strategic planning and performance services [P8] [P12] Report P8, P12
  • Education services [P8] [P12] Report P8, P12
  • Development and Economic Growth and Roads and Infrastructure Services [P8] [P12] Report P8, P12
  • Commercial Services, Legal and Regulatory Support, Financial Services, Children and Families and Criminal Justice, and LiveArgyll [P8] [P12] Report P8, P12

Timeline

  • 30 September 2025: The tables and appendices show action status at this date. [3.1] [P18] Report 3.1, P18
  • November 2025: Commercial Services planned an email, and payroll testing was due to begin. [P21] [P49] [P57] Report P21, P49, P57
  • 16 December 2025: The Chief Internal Auditor dated the report, and the committee endorsed it. [P16] [D] Report P16
  • 31 Dec 2025: Deadlines cover asbestos records, short term lets, ASP audit, information governance and audit training. [P20] [P21] [P24] [P25] [P28] [P29] [P30] [P31] [P32] [P43] [P44] Report P20, P21, P24, P25, P28, P29, P30, P31, P32, P43, P44
  • 31 Jan 2026: Housing procedures and IFRS 16 training have revised dates. [P54] [P56] Report P54, P56
  • 31 Mar 2026: Planning training and HSCP culture actions have revised dates. [P22] [P23] [P35] [P36] [P37] [P38] [P39] [P40] [P41] [P42] Report P22, P23, P35, P36, P37, P38, P39, P40, P41, P42
  • 31 May 2026: Pay Time and iTrent payroll actions have revised dates. [P48] [P49] [P57] [P58] Report P48, P49, P57, P58
  • 31 Dec 2027: The historical burial records update has a revised date. [P26] [P27] Report P26, P27

Plain English for the jargon

  • Audit action: An agreed action tracked for completion, delay, rescheduling or evidence. [3.1] [3.2] [3.3] [P20]
  • Evidence required: A status used where evidence is required to confirm completion. [3.3] [P7] [P53]
  • Rescheduled: An action given a revised completion date. [P20] [P21] [P22] [P23]
  • On course: A status in the table for actions due after 30 September 2025. [P9] [P10] [P11] [P12]
  • RMP: Records Management Plan submitted to the Keeper. [P30] [P31] [P32]
  • ASP: Adult Support and Protection audit. [P28] [P29]
  • PCCMT: Procurement Commercial and Contract Management Team. [P45] [P46]
  • IFRS 16: Leases compliance requirements. [P56]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

Decision The Audit and Scrutiny Committee endorsed the contents of the report. (Reference: Report by Chief Internal Auditor, dated 16 December 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Audit and Scrutiny Committee, 15 pages

Recommendations

2.1To endorse the contents of the report.

3.0DETAIL

3.1The two tables below provide a numerical summary of open audit actions with a split between actions due by and due after 30 September 2025.

3.2Appendix 1 provides a visual representation of progress in addressing agreed actions.

3.3Appendix 2 provides further detail on actions that have been delayed and rescheduled or where evidence is required to confirm completion. Table 1 – Actions due by 30 September 2025 Service

Rescheduled Complete

Evidence Required Delayed/

Total Internal Audit DH – Commercial Services 1 1 DH – Education Wellbeing, Inclusion & Achievement 1 1 DH – Legal & Regulatory Support 1 1 KF – Development & Economic Growth 1 2 3 KF – Roads & Infrastructure Services 3 1 4 H&SCP (SW) – Adult Services (Mental Health Learning Disability, 2 2 Addictions & Lifelong Conditions) H&SCP (SW) – Adult Services (Older Adults & Community 1 1 Hospitals) H&SCP (SW) – Finance/Transformation 1 1 H&SCP (SW) – Strategic Planning & Performance 1 1 2 H&SCP (IJB) – Adult Services (Older Adults & Community Hospitals) 1 1 H&SCP (IJB) – Finance/Transformation 2 2 H&SCP (IJB) – Strategic Planning & Performance 6 6 LiveArgyll 1 1 External Audit Nil TOTAL 8 17 1 26

Table 2 – Actions due after 30 September 2025 Service

Rescheduled On Course Complete

Delayed/

Total Internal Audit DH – Commercial Services 1 1 DH – Education Performance & Improvement 4 4 DH – Education Wellbeing, Inclusion & Achievement 5 5 DH – Legal & Regulatory Support 6 6 KF – Development & Economic Growth 1 1 KF – Financial Services 1 2 1 4 KF – Roads & Infrastructure Services 1 7 8 H&SCP (SW) – Children & Families and Criminal Justice 7 1 8 H&SCP (IJB) – Strategic Planning & Performance 7 7 External Audit Nil TOTAL 2 39 3 44 4.0 CONCLUSION

4.1Satisfactory progress continues to be made implementing audit actions.

5.0IMPLICATIONS

5.1Policy – None 5.2 Financial – None 5.3 Legal – None 5.4 HR – None 5.5 Customer Service – None 5.6 Risk – None 5.7 Climate Change – None 5.8 Fairer Scotland Duty – None 5.9 Equalities – protected characteristics – None 5.10 Consumer Duty – None 5.11 Island Communities – None 5.12 Children’s Rights and Wellbeing – None

Paul MacAskill Chief Internal Auditor 16 December 2025

For further information contact: Paul MacAskill, 01546 604108 [email protected]

APPENDICES Appendix 1 – Visual representation of progress in addressing agreed actions Appendix 2 – Action Plan Points Delayed & Rescheduled or Evidence Required Appendix 1 – Visual representation of progress in addressing agreed actions as at 30 September 2025 Appendix 2 – Action Plan Points - Delayed and Rescheduled or Evidence Required

Action Plan Points due by 30th September 2025

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal and External Audit Report Follow Up 2025-26Report 15 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Argyll and Bute

Search all
  1. Internal and External Audit Report Follow Up 2025-26This decision
  2. Internal and External Audit Report Follow Up 2026-27Decided
  3. Internal and External Audit Report Follow Up 2025-26Decided
  4. Internal and External Audit Report Follow Up 2025-26Decided
  5. Internal and External Audit Report Follow Up 2025-26Decided
  6. Internal and external audit report follow up report 2024-2025Agreed

More from Argyll and Bute Audit and Scrutiny Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Internal Audit and Counter Fraud Summary of ActivitiesDecision The Audit and Scrutiny Committee reviewed and endorsed the Summary of Activities report. (Reference: Report ... Decided Open
3 Sep 2026 Internal and External Audit Report Follow Up 2026-27Decision The Audit and Scrutiny Committee endorsed the contents of the report. (Reference: Report by Chief Internal A... Decided Open
3 Sep 2026 Internal Audit Reports to Audit and Scrutiny Committee 2026/2027Decision The Audit and Scrutiny Committee reviewed and endorsed the summary report and detail within each individual ... Decided Open
3 Sep 2026 External Audit Progress UpdateDecision The Audit and Scrutiny Committee agreed to note the information provided. Agreed Open
3 Sep 2026 Verbal Update by Chair(s) of Scrutiny PanelDecision The Audit and Scrutiny Committee noted the information provided. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies