PIERS AND HARBOURS MARINE ASSET MANAGEMENT PLAN - WORKS UPDATE
NotedCommittee1 paper
AI summaryArgyll and Bute Harbour Board noted updates on the Marine Asset Management Plan, including a £2.4m Iona Breakwater cost rise to £17.2m, with a £1.95m contractor offer to cap weather risk.
Written from the decision and the officer reportPDF Pro
OutcomeNotedNo new approvals; status update on Marine Asset Management Plan
MoneyIona contract: £17.2m forecastOriginal £14.8m, now £17,196,698 with £1.95m risk transfer offer pending
What happens nextCraignure consultant April 2026MDC appointment expected; FBC due March 2027 Harbour Board
Who it affectsFerry routes and island communitiesCalMac routes at Iona, Craignure, Port Askaig, Easdale, Luing, Jura
What was decided
The Harbour Board noted the updates on capital works currently being progressed within the Marine Asset Management Plan.
The update covered seven workstreams, with major focus on renewing or adapting infrastructure to support CalMac ferry services ahead of new vessels. Report 3.1, P4
Why
The Marine Asset Management Plan sets out programmed capital works and cost estimates for the next five years, kept flexible to respond to changing priorities, design, construction methods and market conditions. Report 3.1
Funding is primarily from prudential borrowing repaid via major port fees, with additional grants pursued from Crown Estate Scotland and Transport Scotland.
What happens next
A management and development consultant for the Craignure Terminal is expected to be appointed in April 2026, with a Final Business Case report to the March 2027 Harbour Board. Report 3.4
Officers will bring a further update on the Iona Breakwater weather risk transfer at the Harbour Board meeting. Report P8
Transport Scotland and CMAL plan to publish the Outline Business Case for Gourock, Dunoon and Kilcreggan ferry services in summer 2026. Report 3.9
The money
£17,196,698 Iona Breakwater current contract forecast (up from £14,785,026) Report P7
£2,411,672 Iona Breakwater net cost movement, +16.31% Report P7
£1,284,722 Iona weather-related costs to date, Aug 2025 to Feb 2026 Report P7
£1.95m Contractor offer to assume full weather risk at Iona, past and future Report P7
£47.9m Craignure Terminal current financial plan figure Report 3.4
£3m Craignure planned spend for 2026/27 Report 3.4
£5.6m Feolin and Eilean Dhuira other funding for 2026/27, not yet spent Report 3.10
Options considered
Rejected in report discussion: Retain weather risk on Iona Breakwater contract. Forecast total weather liability of £2.77m to £2.93m, with risk of further winter delays Report P7
Recommended in report, not yet decided: Transfer full weather risk to contractor at Iona for £1.95m. Caps exposure at £1.95m, avoids further winter delay, delivers by late summer 2026 Report P7
Implications
Financial: Iona contract has risen by £2,411,672, with drivers including adverse weather, seagrass-related standing time, and adjustments, partly offset by value engineering savings. Report P7
Financial: Increases to fees and charges are needed to maintain and develop marine assets, which may have a detrimental economic impact on fishermen, bulk importers, timber exporters, wind farm developers and cruise companies. Report P17, P18
Risk: Current Iona estimated completion of November 2026 places works back in a high-risk weather window, with potential further cost uplift. Report P7
Legal: No direct legal implications arising from the report.
Equalities: No direct equalities implications arising from the report.
Climate: No direct climate change impacts identified; due regard will be given as works progress. Report 5.7
Who and where
CalMac ferry passengers on routes served by Iona, Fionnphort, Gigha, Tayinloan, Lismore, Craignure, Port Askaig, Easdale, Luing, Dunoon, Gourock, Kilcreggan and Jura Report P4, 3.5
Residents of Easdale, Luing and Jura who may take part in surveys and engagement for the Strategic Outline Case and Jura service improvements Report 3.8, 3.10
Businesses using council marine facilities, including fishermen, bulk importers, timber exporters, wind farm developers and cruise companies Report P17
Timeline
April 2026: Anticipated appointment of Management and Development Consultant for Craignure Terminal Report 3.4
Summer 2026: Outline Business Case for Gourock, Dunoon and Kilcreggan ferry services to be published by Transport Scotland and CMAL Report 3.9
Late Summer 2026: Possible Iona Breakwater completion if weather risk is transferred to the contractor Report P7
Summer 2026: Design and tendering of permanent Oban pontoon and breakwater repair Report 3.11
November 2026: Current estimated completion date for Iona Breakwater under retained weather risk Report P7
Winter 2026/27: Installation of permanent Oban repair works Report 3.11
March 2027: Craignure Final Business Case report to be presented to the Harbour Board Report 3.4
2028 onwards: New Small Vessel Replacement Programme vessels begin service on Iona, Fionnphort, Gigha and Tayinloan routes Report 3.5
Plain English for the jargon
MAMP: Marine Asset Management Plan, the council's programme of capital works to develop and upgrade marine infrastructure
SVRP: Small Vessel Replacement Programme, led by Transport Scotland and CMAL to replace smaller aging CalMac ferries
CMAL: Caledonian Maritime Assets Limited, owner of CalMac ferries and associated harbour infrastructure
CFL: CalMac Ferry Limited, operator of ferry services
MDC: Management and Development Consultant being appointed for the Craignure Terminal
FBC: Final Business Case, the detailed business case stage before construction
STAG: Scottish Transport Appraisal Guidance, used to appraise transport investment options
SOC: Strategic Outline Case, an early-stage business case to define problems and shortlist options
NEC3: New Engineering Contract, third edition, used for the Iona Breakwater construction contract
RET: Road Equivalent Tariff, a ferry fares structure for islands
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4
Resolved
Decision The Argyll and Bute Harbour Board noted the updates on capital works currently being progressed within the Marine Asset Management Plan. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure, dated March 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
2.1Members are asked to consider and note the updates on capital works currently being progressed within the Marine Asset Management Plan.
3.0DETAIL
3.1The Marine Asset Management Plan (MAMP) outlines the Council’s programmed capital works to develop and upgrade marine infrastructure across Argyll and Bute. The plan provides cost estimates for the next five years while remaining flexible to respond to changing priorities, design developments, construction methods, and market conditions. A significant number of projects focus on renewing or adapting infrastructure to support CalMac Ferry Limited (CFL) services ahead of the arrival of new vessels. 3.2 Funding is primarily sourced through Prudential Borrowing, repaid via fees from major ports, with additional grants actively pursued from organisations such as Crown Estate Scotland and Transport Scotland. All projects undergo competitive tendering to secure value for money and high quality delivery. They are regularly monitored and re-forecast to manage risk, maintain progress, and ensure budgets are adjusted appropriately. 3.3 Alongside our maintenance, servicing and conservancy works, Marine Operations are presently engaged in several long, and shorter-term projects across Argyll & Bute which include:
• Craignure – New Ferry Terminal; • SVRP Projects which include Iona/Fionnphort and Gigha/Tayinloan • Port Askaig – Enabling works for new CalMac vessel; • Feolin – Jura passenger only service access; and • Easdale and Luing Strategic Outline Case • Dunoon, Gourock and Kilcreggan and; • Feolin and the Eilean Dhuira Funding
3.4Craignure Terminal The tender to appoint the Management and Development Consultant (MDC) is now complete, and officers are marking the responses. An appointment is anticipated to be made in April 2026. Once appointed, the MDC will advance the project to Final Business Case (FBC), develop the current design to RIBA Stage 3, and initiate many of the licensing, consent and permissions required in preparation for the construction phase. Officers currently estimate the FBC report will be presented to the March 2027 Harbour Board for approval. Spend to date: 2026/27: £3m (planned) Current financial plan figure: £47.9m Longterm Estimate £100m
3.5Small Vessel Replacement Programme (SVRP) The Iona Breakwater project is a key component in supporting Transport Scotland and CMAL’s Small Vessel Replacement Programme (SVRP), which will replace many of the smaller aging ferries on CalMac routes. Iona is one of two routes and four ports set to benefit from the introduction of the new vessels, scheduled to begin service from 2028 onwards. The other ports included in this programme are Fionnphort, Gigha, and Tayinloan. Transport Scotland has indicated that a partial funding grant will be made available to Argyll and Bute Council to support the essential works required at each of these ports. The grant letter indicates the following grants are available to Argyll and Bute Council: For Port Enabling Works • Tayinloan Dredging - £784,000 • Gigha Dredging - £150,000 • Gigha Shore Power Civils - £95,000 • Fionnphort Shore Power Civils - £47,000 • Lismore Dredging - £930,000 For Shore Power • Gigha - £1,282,609 • Fionnphort - £1,628,682
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Argyll and bute harbour board workplanDecision The Argyll and Bute Harbour Board noted the content of the workplan. (Reference: Argyll and Bute Harbour Boa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.