PIERS AND HARBOURS MARINE ASSET MANAGEMENT PLAN - WORKS UPDATE

Noted Committee 1 paper

AI summaryArgyll and Bute Harbour Board noted updates on the Marine Asset Management Plan, including a £2.4m Iona Breakwater cost rise to £17.2m, with a £1.95m contractor offer to cap weather risk.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo new approvals; status update on Marine Asset Management Plan
MoneyIona contract: £17.2m forecastOriginal £14.8m, now £17,196,698 with £1.95m risk transfer offer pending
What happens nextCraignure consultant April 2026MDC appointment expected; FBC due March 2027 Harbour Board
Who it affectsFerry routes and island communitiesCalMac routes at Iona, Craignure, Port Askaig, Easdale, Luing, Jura

What was decided

The Harbour Board noted the updates on capital works currently being progressed within the Marine Asset Management Plan.

The update covered seven workstreams, with major focus on renewing or adapting infrastructure to support CalMac ferry services ahead of new vessels. Report 3.1, P4

Why

The Marine Asset Management Plan sets out programmed capital works and cost estimates for the next five years, kept flexible to respond to changing priorities, design, construction methods and market conditions. Report 3.1

Funding is primarily from prudential borrowing repaid via major port fees, with additional grants pursued from Crown Estate Scotland and Transport Scotland.

What happens next

A management and development consultant for the Craignure Terminal is expected to be appointed in April 2026, with a Final Business Case report to the March 2027 Harbour Board. Report 3.4

Officers will bring a further update on the Iona Breakwater weather risk transfer at the Harbour Board meeting. Report P8

Transport Scotland and CMAL plan to publish the Outline Business Case for Gourock, Dunoon and Kilcreggan ferry services in summer 2026. Report 3.9

The money

  • £17,196,698 Iona Breakwater current contract forecast (up from £14,785,026) Report P7
  • £2,411,672 Iona Breakwater net cost movement, +16.31% Report P7
  • £1,284,722 Iona weather-related costs to date, Aug 2025 to Feb 2026 Report P7
  • £1.95m Contractor offer to assume full weather risk at Iona, past and future Report P7
  • £47.9m Craignure Terminal current financial plan figure Report 3.4
  • £100m Craignure Terminal long-term estimate Report 3.4
  • £3m Craignure planned spend for 2026/27 Report 3.4
  • £5.6m Feolin and Eilean Dhuira other funding for 2026/27, not yet spent Report 3.10

Options considered

  • Rejected in report discussion: Retain weather risk on Iona Breakwater contract. Forecast total weather liability of £2.77m to £2.93m, with risk of further winter delays Report P7
  • Recommended in report, not yet decided: Transfer full weather risk to contractor at Iona for £1.95m. Caps exposure at £1.95m, avoids further winter delay, delivers by late summer 2026 Report P7

Implications

  • Financial: Iona contract has risen by £2,411,672, with drivers including adverse weather, seagrass-related standing time, and adjustments, partly offset by value engineering savings. Report P7
  • Financial: Increases to fees and charges are needed to maintain and develop marine assets, which may have a detrimental economic impact on fishermen, bulk importers, timber exporters, wind farm developers and cruise companies. Report P17, P18
  • Risk: Current Iona estimated completion of November 2026 places works back in a high-risk weather window, with potential further cost uplift. Report P7
  • Legal: No direct legal implications arising from the report.
  • Equalities: No direct equalities implications arising from the report.
  • Climate: No direct climate change impacts identified; due regard will be given as works progress. Report 5.7

Who and where

  • CalMac ferry passengers on routes served by Iona, Fionnphort, Gigha, Tayinloan, Lismore, Craignure, Port Askaig, Easdale, Luing, Dunoon, Gourock, Kilcreggan and Jura Report P4, 3.5
  • Residents of Easdale, Luing and Jura who may take part in surveys and engagement for the Strategic Outline Case and Jura service improvements Report 3.8, 3.10
  • Businesses using council marine facilities, including fishermen, bulk importers, timber exporters, wind farm developers and cruise companies Report P17

Timeline

  • April 2026: Anticipated appointment of Management and Development Consultant for Craignure Terminal Report 3.4
  • Summer 2026: Outline Business Case for Gourock, Dunoon and Kilcreggan ferry services to be published by Transport Scotland and CMAL Report 3.9
  • Late Summer 2026: Possible Iona Breakwater completion if weather risk is transferred to the contractor Report P7
  • Summer 2026: Design and tendering of permanent Oban pontoon and breakwater repair Report 3.11
  • November 2026: Current estimated completion date for Iona Breakwater under retained weather risk Report P7
  • Winter 2026/27: Installation of permanent Oban repair works Report 3.11
  • March 2027: Craignure Final Business Case report to be presented to the Harbour Board Report 3.4
  • 2028 onwards: New Small Vessel Replacement Programme vessels begin service on Iona, Fionnphort, Gigha and Tayinloan routes Report 3.5

Plain English for the jargon

  • MAMP: Marine Asset Management Plan, the council's programme of capital works to develop and upgrade marine infrastructure
  • SVRP: Small Vessel Replacement Programme, led by Transport Scotland and CMAL to replace smaller aging CalMac ferries
  • CMAL: Caledonian Maritime Assets Limited, owner of CalMac ferries and associated harbour infrastructure
  • CFL: CalMac Ferry Limited, operator of ferry services
  • MDC: Management and Development Consultant being appointed for the Craignure Terminal
  • FBC: Final Business Case, the detailed business case stage before construction
  • STAG: Scottish Transport Appraisal Guidance, used to appraise transport investment options
  • SOC: Strategic Outline Case, an early-stage business case to define problems and shortlist options
  • NEC3: New Engineering Contract, third edition, used for the Iona Breakwater construction contract
  • RET: Road Equivalent Tariff, a ferry fares structure for islands
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Decision The Argyll and Bute Harbour Board noted the updates on capital works currently being progressed within the Marine Asset Management Plan. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure, dated March 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Argyll and Bute Harbour Board

Recommendations

2.1Members are asked to consider and note the updates on capital works currently being progressed within the Marine Asset Management Plan.

3.0DETAIL

3.1The Marine Asset Management Plan (MAMP) outlines the Council’s programmed capital works to develop and upgrade marine infrastructure across Argyll and Bute. The plan provides cost estimates for the next five years while remaining flexible to respond to changing priorities, design developments, construction methods, and market conditions. A significant number of projects focus on renewing or adapting infrastructure to support CalMac Ferry Limited (CFL) services ahead of the arrival of new vessels. 3.2 Funding is primarily sourced through Prudential Borrowing, repaid via fees from major ports, with additional grants actively pursued from organisations such as Crown Estate Scotland and Transport Scotland. All projects undergo competitive tendering to secure value for money and high quality delivery. They are regularly monitored and re-forecast to manage risk, maintain progress, and ensure budgets are adjusted appropriately. 3.3 Alongside our maintenance, servicing and conservancy works, Marine Operations are presently engaged in several long, and shorter-term projects across Argyll & Bute which include:

• Craignure – New Ferry Terminal; • SVRP Projects which include Iona/Fionnphort and Gigha/Tayinloan • Port Askaig – Enabling works for new CalMac vessel; • Feolin – Jura passenger only service access; and • Easdale and Luing Strategic Outline Case • Dunoon, Gourock and Kilcreggan and; • Feolin and the Eilean Dhuira Funding

3.4Craignure Terminal The tender to appoint the Management and Development Consultant (MDC) is now complete, and officers are marking the responses. An appointment is anticipated to be made in April 2026. Once appointed, the MDC will advance the project to Final Business Case (FBC), develop the current design to RIBA Stage 3, and initiate many of the licensing, consent and permissions required in preparation for the construction phase. Officers currently estimate the FBC report will be presented to the March 2027 Harbour Board for approval. Spend to date: 2026/27: £3m (planned) Current financial plan figure: £47.9m Longterm Estimate £100m

3.5Small Vessel Replacement Programme (SVRP) The Iona Breakwater project is a key component in supporting Transport Scotland and CMAL’s Small Vessel Replacement Programme (SVRP), which will replace many of the smaller aging ferries on CalMac routes. Iona is one of two routes and four ports set to benefit from the introduction of the new vessels, scheduled to begin service from 2028 onwards. The other ports included in this programme are Fionnphort, Gigha, and Tayinloan. Transport Scotland has indicated that a partial funding grant will be made available to Argyll and Bute Council to support the essential works required at each of these ports. The grant letter indicates the following grants are available to Argyll and Bute Council: For Port Enabling Works • Tayinloan Dredging - £784,000 • Gigha Dredging - £150,000 • Gigha Shore Power Civils - £95,000 • Fionnphort Shore Power Civils - £47,000 • Lismore Dredging - £930,000 For Shore Power • Gigha - £1,282,609 • Fionnphort - £1,628,682

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PIERS AND HARBOURS MARINE ASSET MANAGEMENT PLAN: WORKS UPDATEReport 193 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 11 attended
JS
Julieann SmallSecretary, expected
KM
Katie McKenzieSecretary, expected
JA
Councillor John ArmourVice-Chair, present
GB
Councillor Gordon BlairMember, present
MC
Councillor Maurice CorryMember, present
AK
Councillor Andrew KainMember, present
LM
Councillor Liz McCabeMember, absent
DM
Councillor Dougie McFadzeanMember, present
RM
Councillor Ross MorelandChair, present
AV
Councillor Andrew VennardMember, present
HM
Hazel MacInnesSecretary, expected

On this subject at Argyll and Bute

Search all
  1. PIERS AND HARBOURS MARINE ASSET MANAGEMENT PLAN - WORKS UPDATEThis decision
  2. Piers and Harbours - Marine Works UpdateNoted
  3. Piers and harbours marine asset management plan - works updateNoted
  4. Piers and harbours - performance reportingAgreed
  5. Piers and harbours marine asset management plan fees and charges 2027 / 2028Noted
  6. Piers and Harbours - Marine Works UpdateAgreed

More from Argyll and Bute Argyll and Bute Harbour Board

All decisions
MeetingDecisionOutcome
9 Oct 2026 Piers and harbours marine asset management plan - works updateDecision The Argyll and Bute Harbour Board noted the updates on capital works currently being progressed within the M... Noted Open
9 Oct 2026 Piers and harbours - performance reportingDecision The Argyll and Bute Harbour Board – 1. agreed the proposed approach and structure to annual performance repo... Agreed Open
9 Oct 2026 Carradale harbourDecision The Argyll and Bute Harbour Board noted the content of the report. (Reference: Report by Executive Director ... Noted Open
9 Oct 2026 Piers and harbours marine asset management plan fees and charges 2027 / 2028Decision The Argyll and Bute Harbour Board – 1. noted that officers were of the view that a review is required to con... Noted Open
9 Oct 2026 Argyll and bute harbour board workplanDecision The Argyll and Bute Harbour Board noted the content of the workplan. (Reference: Argyll and Bute Harbour Boa... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies