Budget Monitoring Report to 30 June 2019

Approved Executive 2 papers

Cabinet approved this item on Monday 2 September 2019. Below is the council's own wording, with the papers it was decided on.

Item178

Resolved

The Deputy Leader of the Council and Cabinet Member for Corporate Support, Councillor Oppler, introduced this item and stated that financial performance was monitored on a regular basis to ensure that spending was in line with Council policies and that net expenditure was contained within overall budget limits. Performance against approved budget to the end of June 2019 in relation to the General Fund, Housing Revenue Account (HRA) and capital was on track. The Financial Services Manager presented this report and stated that this was the first formal monitoring report for 2018/19. Further reports would be presented to Cabinet for the period ended September and December 2019 with an outturn report this time next year. The variation against expected spend at the end of June 2019 was £54k. The Financial Services Manager reiterated the situation in relation to homelessness and the continuing financial pressures from homelessness on nightly paid accommodation. She anticipated that there would be a requirement for a further supplementary estimate later in the year. In summary, the General Fund and HRA were on track, however, Members were asked to approve the HRA revenue and capital slippage highlighted in Paragraph 7.2 of the report, which linked to the favourable outturn position in the previous item. In receiving the report, questions were asked about the homelessness situation in terms of whether this had been foreseen and was a result of West Sussex County Council’s (WSCC’s) decision to withdraw its homelessness support grant to some charitable organisations and whether this was in line with the expected predictions voiced when that decision had been made. The Chief Executive responded stating that the Council had not seen a major impact to date, however, he did feel that the situation would worsen over time. Work was underway to try and produce figures so that there would not be the need to seek approval for further Supplementary Estimates in the future. It would be necessary to make sure that the budget for next year would be more realistic to keep within the movement of temporary accommodation and homelessness costs. This was an ongoing and real situation with the Council working alongside its partners across the District including charities, churches and other charitable authorities to try and help people with complex needs and people in general need. Members were reassured that the Council was attacking this issue from every angle including buying additional properties to house people. The Chairman asked how many properties had been purchased. The Director of Services outlined that the Council bought properties but these took a while to come on stream. Cabinet was informed that there was a full-on pipeline of purchases thought the precise number could not be provided at this time. Officers were working closely with the Cabinet Member for Residential Services on an ongoing programme. The Cabinet RESOLVED – That (1) the report in Appendix 1 be noted; (2) the significant anticipated overspend in relation to nightly paid accommodation be noted; (3) the HRA revenue and capital slippage ...
Word for word from the decision Arun published for this meeting. Source: democracy.arun.gov.uk

Follow this further

Built from Arun's papers

What the report saysPro

Report to Cabinet

ARUN DISTRICT COUNCIL REPORT TO AND DECISION OF CABINET ON 2 SEPTEMBER 2019

SUBJECT: Budget Monitoring Report to 30 June 2019

REPORT AUTHOR: Carolin Martlew, Financial Services Manager DATE: July 2019 EXTN: 37568 PORTFOLIO AREA: Corporate Support

EXECUTIVE SUMMARY: The Budget Monitoring report sets out the Capital, Housing Revenue and General Fund Revenue budget performance to the end of June 2019.

RECOMMENDATIONS Cabinet is requested to: (i) Note the report in Appendix 1; (ii) Note the significant anticipated overspend in relation to nightly paid accommodation; (iii) Approve the HRA revenue and capital slippage contained in Appendix 1 (paragraph 7.2); and (iv) Note that overall performance against budget is currently on track

1. BACKGROUND: The Council approved a General Fund revenue total net expenditure budget of £24.525 million; a Housing Revenue Account revenue total expenditure budget of £19.832 million; and a capital budget of £8.943 million for the year 2017/18. This report provides information to enable actual spending and income to be monitored against profiled budget for the period to 30 June 2019. 2. PROPOSAL(S): The Cabinet is requested to note the budget monitoring report in appendix 1. The report provides information on a management by exception basis to enable the reader to understand the overall performance of the council within the context of the budget book summary. 3. OPTIONS: n/a 4. CONSULTATION: Has consultation been undertaken with: YES NO Relevant Town/Parish Council  Relevant District Ward Councillors  Other groups/persons (please specify)  5. ARE THERE ANY IMPLICATIONS IN RELATION TO YES NO THE FOLLOWING COUNCIL POLICIES: (Explain in more detail at 6 below) Financial  Legal  Human Rights/Equality Impact Assessment  Community Safety including Section 17 of Crime & Disorder Act  Sustainability  Asset Management/Property/Land  Technology  Other (please explain)  6. IMPLICATIONS: The overall performance against budget is on track. However, the pressure on homelessness is continuing and a supplementary estimate will be required before the end of the financial year, which will reduce the planned level of the General Fund Balance.

7. REASON FOR THE DECISION: To ensure that spending is in line with approved Council policies, and that it is contained within overall budget limits. 8. EFFECTIVE DATE OF THE DECISION: 11 September 2019

9. BACKGROUND PAPERS: Revenue and Capital Estimates 2019-2020. http://www.arun.gov.uk/financial- information/

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget Monitoring Report to 30 June 2019Report 36 KB DownloadRead as text
PDF
Item 8: Appendix 1: Cabinet Budget Monitoring June 2019 2-9-19Appendix 314 KB Download

At this meeting

Whole meeting

Who was there

6 of 15 attended
DJ
Councillor Dr. James Walsh KStJ RDChairman, present
FO
Councillor Francis OpplerVice-Chair, present
MP
Councillor Mrs Pauline GregoryCommittee Member, apologies
ML
Councillor Martin LuryCommittee Member, present
DP
Councillor Daniel PurcheseCommittee Member, present
MS
Councillor Matt StanleyCommittee Member, present
MG
Councillor Mrs Gill YeatesCommittee Member, present
JB
Councillor Jamie BennettGuest, in attendance
TC
Councillor Terence ChapmanGuest, in attendance
JC
Councillor John CharlesGuest, in attendance
MC
Councillor Mike ClaydenGuest, in attendance
HC
Councillor Hugh CosterGuest, in attendance

All 15 on the meeting page

On this subject at Arun

Search all
  1. Budget Monitoring Report to 30 June 2019This decision
  2. Budget Monitoring Report - Quarter 1Noted
  3. Budget Monitoring ReportDecided
  4. Budget Monitoring Report to 31 December 2021Approved
  5. Budget Monitoring Report to 30 September 2021Decided
  6. Budget Monitoring Report to 31 December 2020Noted

More from Arun Cabinet

All decisions
MeetingDecisionOutcome
22 Mar 2021 Urgent BusinessRESOLVED That a letter be sent to West Sussex County Council urging reconsideration of the proposed speed limit on th... Decided Open
22 Mar 2021 Place St Maur and Esplanade Project, Bognor RegisThe Cabinet RESOLVED The designs presented at the meeting for the Place St Maur and the Esplanade, be approved and th... Approved Open
22 Mar 2021 Arun Improvement Programme - UpdateThe Cabinet RESOLVED To note the activities of the Arun Improvement Programme. Noted Open
22 Mar 2021 Options to Progress Webcast Improvement ProjectThe Cabinet RECOMMEND TO FULL COUNCIL – That (1) That the upgrades to the webcasting system set out in the table with... Approved Open
22 Mar 2021 Customer Services StrategyThe Cabinet RESOLVED To formally adopt the 2021-2026 and approve the process of implementation to embed it into the o... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies