CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Arun District Council
Policy and Resources Committee, Thursday 9 December 2021 at 6.00pm

Budget Monitoring Report to 30 September 2021

Decided Committee 2 papers

Policy and Resources Committee decided this item on Thursday 9 December 2021. Below is the council's own wording, with the papers it was decided on.

Item510

Resolved

RESOLVED – That (1) Any specific project related General Fund revenue underspend continues to be transferred to earmarked reserves as per previous policy to allow projects to be completed; (2) The Housing Revenue Account repairs and maintenance (Planned and Responsive) budget be closely monitored to ensure that any necessary corrective action is taken if required; and (3) The Capital, Asset Management and Projects programme be reviewed to determine future projections and deliverability of current projects.
Word for word from the decision Arun published for this meeting. Source: democracy.arun.gov.uk

Follow this further

Built from Arun's papers

What the report saysPro

Report to Policy and Resources Committee

ARUN DISTRICT COUNCIL REPORT TO AND DECISION OF THE POLICY AND FINANCE COMMITTEE ON 9 DECEMBER 2021

SUBJECT: Budget Monitoring Report to 30 September 2021

REPORT AUTHOR: Carolin Martlew, Interim Group Head of Corporate Support and S151 Officer DATE: November 2021 EXTN: 01903 737568 AREA: Corporate Support

EXECUTIVE SUMMARY: The Budget Monitoring Report sets out the Capital, Housing Revenue and General Fund Revenue budget performance to the end of September 2021.

RECOMMENDATIONS: It is recommended that the Policy and Finance Committee approve that: (i) Any specific project related General Fund revenue underspend continues to be transferred to earmarked reserves as per previous policy to allow projects to be completed; (ii) The Housing Revenue Account repairs and maintenance (Planned and Responsive) budget be closely monitored to ensure that any necessary corrective action is taken if required; and (iii) The Capital, Asset Management and Projects programme be reviewed to determine future projections and deliverability of current projects.

1. BACKGROUND: The Council approved a General Fund revenue total net expenditure budget of £25.733 million; a Housing Revenue Account revenue total expenditure budget of £18.980 million; and a capital budget of £7.960 million for the year 2021/22. This report provides information to enable actual spending and income to be monitored against profiled budget for the period to 30 September 2021. 2. PROPOSAL(S): The Committee is requested to consider the budget monitoring report in Appendix 1. The report provides information on a management by exception basis to enable the reader to understand the overall performance of the council within the context of the budget book summary. The report highlights the significant additional expenditure and loss of income due to the Covid-19 pandemic and any other factors. 3. OPTIONS: N/A 4. CONSULTATION: Has consultation been undertaken with: YES NO Relevant Town/Parish Council  Relevant District Ward Councillors  Other groups/persons (please specify)  5. ARE THERE ANY IMPLICATIONS IN RELATION TO YES NO THE FOLLOWING COUNCIL POLICIES: (Explain in more detail at 6 below) Financial  Legal  Human Rights/Equality Impact Assessment  Community Safety including Section 17 of Crime &  Disorder Act Sustainability  Asset Management/Property/Land  Technology  Other (please explain)  6. IMPLICATIONS: Financial It is sound governance to monitor spending against budget during the financial year. Such control allows the Council to take prompt corrective action if spending or income significantly varies from the approved budgets. The Council continues to incur additional expenditure and loss of income due to the COVID-19 pandemic and net expenditure is monitored closely to ensure that corrective action continues to be taken if necessary. Transfers to earmarked reserves were required in 2020/21 in relation to Collection Fund transactions that impact the General Fund in 2021/22. These are also reviewed and monitored as part of the process.

7. REASON FOR THE DECISION: To ensure that spending is in line with approved Council policies, and that it is contained within overall budget limits.

8. BACKGROUND PAPERS: Revenue and Capital Estimates 2021-2022. http://www.arun.gov.uk/financial-information/

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget Monitoring Report to 30 September 2021Report 37 KB DownloadRead as text
PDF
Final Budget Monitoring Report September 2021Report 338 KB Download

At this meeting

Whole meeting

Who was there

8 of 9 attended
SG
Councillor Shaun GunnerChair, present
JP
Councillor Jacky PendletonVice-Chair, present
AC
Councillor Andy CooperCommittee Member, present
TD
Councillor Tony DixonCommittee Member, present
FO
Councillor Francis OpplerCommittee Member, present
GR
Councillor Grant RobertsCommittee Member, present
ES
Councillor Emily SeexCommittee Member, absent
MS
Councillor Matt StanleyCommittee Member, present
DJ
Councillor Dr. James Walsh KStJ RDCommittee Member, present

On this subject at Arun

Search all
  1. Budget Monitoring Report to 30 September 2021This decision
  2. Budget Monitoring Report - Quarter 1Noted
  3. Budget Monitoring ReportDecided
  4. Budget Monitoring Report to 31 December 2021Approved
  5. Budget Monitoring Report to 31 December 2020Noted
  6. Budget Monitoring Report to 30 September 2020Noted

More from Arun Policy and Resources Committee

All decisions
MeetingDecisionOutcome
2 Jul 2026 Start TimesRESOLVED That its start times for meetings for this new Municipal Year be 6.00 pm. Decided Open
2 Jul 2026 Adoption of the Resolution FrameworkRESOLVED - To (1) Approve the adoption of the Resolution Framework as the Council’s primary approach for managing con... Approved Open
2 Jul 2026 Budget 2027/27 - ProcessRESOLVED To approve the budget process for 2027/28 as outlined in the report. Approved Open
12 Mar 2026 Pay Policy Statement 2026RESOLVED That the contents of the /27 as set out in Appendix 1 be noted. The Committee then RECOMMEND TO FULL COUNCIL... Noted Open
12 Mar 2026 Q3 Performance Report for the Key Performance Indicators (KPIs) which form part of the Council's Vision 2022-2026RESOLVED – That it (1) Approves that we no longer collect information for KPI CP36, the number of new homes completed... Approved Open