RESOLVED That a virement of £269k from the inflationary pressure reserve, to cover in year costs associated with rising inflationary costs and the recent nationally negotiated pay deal for Biffa staff on the Combined Cleansing Services Contract, be noted.
Word for word from the decision Arun published for this meeting.Source: democracy.arun.gov.uk
1.1The purpose of this report is to make financial arrangements to ensure the in-year budget is available to cover additional costs required to support delivery of the Combined Services Cleansing Contract for 2022/23 2. RECOMMENDATIONS
2.1It is recommended that the Environment Committee note a virement of £269k from the inflationary pressure reserve, to cover in year costs associated with rising inflationary costs and the recent nationally negotiated pay deal for Biffa staff on the Combined Cleansing Services Contract.
Executive summary
3.1Due to rising national inflation, supply chain and wage pressures within the waste industry and collections sector, an agreed pay settlement between the Council’s contractor Biffa and the GMB Union in August 2022 averted the threat of summer holiday strike action for waste services in Arun. The result is that a virement from inflation contingency budget is required for this financial year to meet the increased costs of the Combined Cleansing Services Contract.
4. DETAIL
4.1On the 19th May 2022, Members of the Environment Committee agreed to a series of recommendations relating to a proposed three-year extension offer for the Combined Cleansing Services Contract (CCSC) with Biffa. The extension would run from 1st February 2023 until 31st January 2026.
4.2Contained within the May report to the Environment Committee was confirmation that the costed service options included a commitment to the Real Living Wage (RLW) for operatives and aligning all wages, including Large Goods Vehicle (LGV) drivers, with market rates for the region which are negotiated on a national level. This was recommended on the basis that almost every one of the 120 plus staff working on the CCSC are residents of Arun, as well as being necessary to sustain the contract and its future delivery through staff retention. A new hire fleet of vehicles was also required to replace the aged current fleet, which is beyond life expectancy.
4.3The report outlined that costs were based on 2021/22 rates and therefore indexation would be calculated back over the previous 24 months from February 2021 – February 2023. This is required to ensure that the starting position is correct on the extension commencement date.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Orders for DogsIt was agreed to include a question relating to Bested Brooks in the consultation to gather views and the needs for r...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.