RESOLVED that 1) the content of the report be noted; 2) the principles and agreed objectives (as shown in paragraph 4.3 of Appendix E) established by the Bognor Regis Beach Access Working Party be applied additionally to Littlehampton Beach.
Word for word from the decision Arun published for this meeting.Source: democracy.arun.gov.uk
1.1This report is to provide Members with an update on the progress of the Beach Access project against the actions agreed by the Environment Committee 27 February 2023. 1.2 This project is an iterative piece of work and outcomes from the project are looking to be extended to other areas of our coastline.
Recommendations
2.1It is recommended that the Committee:
1) note the content of this report;
2) considers the recommendations from Economy Committee as follows:
“That the principles and agreed objectives (4.3) established by the Bognor Regis Beach Access Working Party be applied additionally to Littlehampton Beach.”
Executive summary
3.1This report summarises the activities of the project since the last update in November 2023. The steps are referenced against the actions agreed by the committee which has been the guiding framework for this project.
3.2A Stakeholder Engagement Workshop was facilitated at The Shed, Bognor Regis in April 2024. The group were provided a presentation by Coastal Partners and then asked to consider the different stages of the access chain and give feedback and suggestions.
3.3A Stakeholder Engagement Group was established by asking interested parties to provide contact details for future correspondence.
3.4In collaboration with The Property, Estates & Facilities Manager and The Group Head of Technical Services, the project has secured an annual contribution of £7,650 covering the next 3 years. This has been achieved through setting aside 5% of Beach Hut revenue.
4 DETAIL
Background
A report setting out recommendations to improve access to the beach for all was approved in February 2023. The report followed the conclusion of the Bognor Regis Beach Access Working Party (BRBAWP) and recommendations which came from this work. The report set out objectives and short, medium and longer-term actions. The report can be found at the link under the background documents at the end of this report. 4.2 Beach Access Objectives
The following table sets out the objectives agreed in February this year.
No. Action Status 1 Establish and engage with a user / stakeholder group for ongoing Complete dialogue.
2 Apply the latest national guidance for equality of access to the Ongoing natural environment.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Orders for DogsIt was agreed to include a question relating to Bested Brooks in the consultation to gather views and the needs for r...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.